Dulien Steel Products, Inc. v. United States

143 Ct. Cl. 484, 1958 U.S. Ct. Cl. LEXIS 178, 1958 WL 7346
CourtUnited States Court of Claims
DecidedJuly 16, 1958
DocketNo. 50193
StatusPublished
Cited by2 cases

This text of 143 Ct. Cl. 484 (Dulien Steel Products, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dulien Steel Products, Inc. v. United States, 143 Ct. Cl. 484, 1958 U.S. Ct. Cl. LEXIS 178, 1958 WL 7346 (cc 1958).

Opinion

Opinion

per curiam:

This case involves claims for shortages in a War Assets Administration sale of surplus property in 1949. The plaintiff claims the defendant breached the contract in not delivering to plaintiff certain items involved in the contract. The Government counterclaims for the unpaid balance of the purchase price, plus interest from the date of default.

The commissioner was directed to make findings of fact and to recommend legal conclusions in the light of the findings of fact under Rule 45 (a) of the Rules of this court.

Pursuant to such reference, the commissioner has submitted his findings of fact and conclusions of law.

[486]*486The court, after having considered the evidence, the briefs and argument of counsel, agrees with the result arrived at by the commissioner and adopts the findings and opinion of Commissioner W. Ney Evans, as hereinafter set forth, except for the tube claim based on the item listed as “Cracking Case” in the brochure. As to the tube claim, we agree with the result arrived at by the commissioner but for this additional reason: The contract contained special conditions of sale which incorporated an agreed formula under which the Government would be paid for overages and plaintiff would be credited for shortages. The formula contained a provision that “The acquisition costs listed in the sales brochure shall be controlling.” The sales brochure listed:

CEACKING-CASE: Type C-23 Houdry, Spec. #SP-2434T2-1, Badger & Sons Co., Drawing #HC-46,11'5" I. D. 1 Ys" thick shell, Material Silicon Firebox steel, w/tube elements, baffles, plates, flanges, etc. for vert, mounting.
Propr loc: #1 Acq. $1,017,000.00

The evidence shows that the cracking case alone had an acquisition cost to the Government in excess of $1,017,000. Therefore, plaintiff as a result of the transaction received an article which had cost the Government at least as much as set forth in the brochure. This was all plaintiff could expect- — it got all the Government contracted to sell and all it contracted to buy.

In all other respects we agree with the Commissioner and adopt the findings and opinion as printed below.

Plaintiff is therefore entitled to recover $15,730.08 on its petition, and defendant is entitled to recover $179,690.25 on its counterclaim. Defendant’s recovery is offset by the amount of plaintiff’s judgment on the petition leaving a net recovery by the Government on its counterclaim in the amount of $163,960.17, with interest at four percent from June 13,1949.

It is so ordered.

[487]*487OPINION OP COMMISSIONER

Tbe contract in suit was founded upon the acceptance by War Assets Administration1 of plaintiff’s bid for surplus property consisting of equipment and accessories for refining gasoline. The offering by WAA and the bid submitted by plaintiff were subject to certain standardized conditions (selected by WAA), which were restated in the formal contract and in the sales documents.2 In formalizing the contract, however (after conditional acceptance of the bid but before delivery of the sales documents), the parties wrote into the contract certain other provisions initiated by WAA and not theretofore used by it. These provisions called for a joint inventory of the property at the time of its delivery and for the application of an adjustment formula whereby plaintiff would be given credit for shortages disclosed by the inventory or pay extra for overages.

The inventory disclosed shortages but no overages. Plaintiff thereupon demanded adjustments according to its interpretation of the contract, the bulk of which (in dollar volume) defendant refused to make. Plaintiff thereupon ceased making scheduled payments on the contract price, contending that credits rightfully due would, if allowed, exceed the unpaid balance. Defendant duly demanded first a resumption of scheduled payments and then payment of the whole balance. In time, the General Accounting Office issued to plaintiff a Certificate of Indebtedness demanding payment, with interest, of the unpaid balance adjusted by minor credits. Plaintiff then filed this suit. Answering the petition, defendant asserted a counterclaim in conformity with GAO’s Certificate of Indebtedness.

The purchase price was $852,775. The amount paid thereon by plaintiff was $173,084.75, leaving an unpaid balance of $179,690.25.

By this suit plaintiff demands allowances under the contract, pursuant to the adjustment formula, for five alleged shortages, totaling $223,172.41, as follows: (1) tube elements [488]*488alleged to have been, missing from cracking cases, $212,-386.83; (2) 19 valves, $6,650.80; (3) spare parts, $2,850.23; (4) eight pumps, $1,110.24; (5) structural steel, $174.81. In addition, plaintiff claims the market value ($4,944) of two hoists and a depropanizer tank, in lieu of allowances under the adjustment formula, because defendant disposed of these items after the sale to plaintiff had become final. The total of plaintiff’s demands is $228,116.41. Conceding defendant’s right to recover on its counterclaim the unpaid balance of the purchase price ($179,690.25), plaintiff demands judgment for the difference, $48,426.16.

Defendant counterclaims for (1) the principal sum of $171,517.09 (representing the initial unpaid balance of the purchase price adjusted by four credits totaling $8,173.16), plus (2) interest on the principal sum at the rate of 4 percent per annum from June 13, 1949, until paid.

The four credits allowed by defendant (totaling $8,173.16) were computed by the adjustment formula as for shortages, as follows: (1) 19 valves; credit, $6,650.80; (2) 8 pumps; credit, $1,110.24; (3) structural steel; credit, $174.81; and (4) the two hoists and depropanizer tank; credit, $237.31.

The foregoing allowances eliminated from controversy the adjustments for shortages of valves, pumps, and structural steel. Defendant concedes and plaintiff accepts credit on account of them in the amount of $7,935.85.

The controversy relates to defendant’s refusal to recognize the absence of the tube elements and the spare parts as shortages compensable under the adjustment formula and to plaintiff’s refusal similarly to recognize the absence of the tank and hoists as shortages so compensable.

Inasmuch as defendant disposed of the tank and two hoists after the sale to plaintiff had become final, plaintiff contends that the adjustment formula provisions (whereby it would be entitled to the $237.31 credit tendered by defendant) do not apply; but that the failure to deliver the items amounted, under the circumstances, to a breach of contract, for which plaintiff is entitled to recover the market price of the equipment ($4,944).

[489]*489Defendant contends (1) that the inventory and adjustment provisions were intended by the parties to apply to all shortages of any items in the list; and (2) that, in any event, the disposition of the items after the sale to plaintiff would amount to a conversion, comprising a tort, over which this court has no jurisdiction.

The evidence sustains plaintiff’s contention on the factual issue, i. e., the intention of the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
143 Ct. Cl. 484, 1958 U.S. Ct. Cl. LEXIS 178, 1958 WL 7346, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dulien-steel-products-inc-v-united-states-cc-1958.