Alaska Pulp Corp. v. United States

48 Fed. Cl. 655, 2001 U.S. Claims LEXIS 19, 2001 WL 185178
CourtUnited States Court of Federal Claims
DecidedFebruary 14, 2001
DocketNo. 95-153C
StatusPublished
Cited by6 cases

This text of 48 Fed. Cl. 655 (Alaska Pulp Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alaska Pulp Corp. v. United States, 48 Fed. Cl. 655, 2001 U.S. Claims LEXIS 19, 2001 WL 185178 (uscfc 2001).

Opinion

OPINION

BASKIR, Chief Judge.

Plaintiff, Alaska Pulp Corporation (“APC”), alleges that the United States Forest Service in various ways breached its timber contract. Among other things, APC claims that the government’s implementation of the Tongass Timber Reform Act, Pub.L. No. 101-626, 104 Stat. 4426 (1990) (“TTRA”), repudiated and materially breached the contract with APC. The matter before us is APC’s motion for partial summary judgment regarding the government’s liability on the TTRA claim.

While admitting that the TTRA breached the contract, defendant contends that APC has failed to establish that it was materially harmed by the statutory provisions. Furthermore, defendant asserts that even if the government repudiated the contract, it may not be held hable because the TTRA was not the operative cause of APC’s economic problems, and because APC waived its repudiation claim.

We reject each of defendant’s arguments and GRANT plaintiffs motion for partial summary judgment as to liability.

BACKGROUND

We have dealt extensively with some of the facts of this case in adjudging other cross-motions for summary judgment. Previously the issues involved the proper interpretation of the contractual obligations of the parties, specifically whether APC was required to operate a pulp mill for the entire period of the contract. We held that it was not. Alaska Pulp Corporation v. United States, No. 95-153C (Fed.Cl., May 25, 2000)(unpub.) We repeat many of those same, undisputed facts below.

The Contract

In October 1957 the United States Forest Service and a Japanese company then known as the Alaska Lumber & Pulp Co., Inc. (subsequently renamed Alaska Pulp Corporation), entered into Timber Sale Contract No. 12-11-010-1545 (“Contract”), a 50-year contract for the sale of timber in the Tongass National Forest in the then-territory of Alaska. The United States Forest Service permitted APC to cut timber and purchase the logs, and APC agreed to do so subject to certain conditions.

The contract also provided for the manufacture of the raw materials harvested. With limited exceptions, the purchaser was not free to export unprocessed timber for primary manufacture elsewhere — this restriction is referred to as the “primary manufacture” or “processing” requirement. Initially, APC met the primary manufacture requirement by processing timber through a pulp mill and a saw mill it erected pursuant to the contract. Lower quality logs, which made up a large percentage of the timber in the Ton-gass, were processed into pulp and sold to support rayon and paper markets in Japan. In addition to pulp manufacturing, APC cut higher quality sawlogs, processed locally via its saw mill.

The arrangement was mutually beneficial, at least at its inception. The Japanese corporation, faced with scarce timber resources in its own country, secured a long-term source for timber products. The United States, on the other hand, made productive use of its national forests and sparked industrial development in Southeastern Alaska. Plaintiff operated the pulp mill from 1961 until 1993, temporarily suspending operations on a few occasions for various reasons. However, over the course of time the market for pulp weakened, making that aspect of the timber contract less desirable than it once was to APC. The landscape changed for the government, as well. Although the promotion of industry in Alaska was still a goal of the United States, it is fair to say that an environmental conservation agenda dormant at the contract’s inception made its way to the forefront of United States domestic policy by the early 1990’s. That and the perception that long-term contractors like APC enjoyed unfair competitive advantages over independent timber purchasers in Alaska, made this contract potentially costly for the United States. In fact, these issues prompt[657]*657ed legislation that was introduced in Congress to terminate APC’s timber contract.

Early Legal Disputes

Thirty years into the contract the parties began repositioning themselves. As plaintiff describes it, a dispute arose “over the economics of the timber” supplied under the contract. PI. Br. at 5. In 1987, APC filed a suit in this Court (Cl.Ct. No. 675-87) seeking over $80 million in damages. A period of negotiations culminated in 1990 with the “settlement contract.” Pursuant to the settlement, APC abdicated much of its role in the selection of timber for harvesting. Defendant agreed to incorporate into the contract the “mid-market test,” which applied certain cost and pricing criteria to timber offerings to achieve an economic return on the timber. The “test” was apparently intended to rectify some of the complaints that led to the lawsuit and to compensate for APC’s diminished role in timber selection under the contract amendments. The settlement contract was executed by APC and the Forest Service in June 1990 and its modifications were put into effect as of July 1,1990.

Enactment of the TTRA

With the ink on the settlement barely dry, Congress five months later passed the Ton-gass Timber Reform Act on November 28, 1990. The thrust of the TTRA was a specific directive to the Department of Agriculture and its subordinate agency, the Forest Service, to modify its contract with APC and another cited contractor. The statute declared several goals and, specifically identifying APC’s contract, ordered that the agreement be unilaterally modified in order to carry out these goals. The Forest Service implemented the statute on February 26, 1991, transmitting to APC a revised text of the contract reflecting the unilateral modifications. Three of these unilateral changes are cited by APC as material breaches: (1) the mandatory “mid-market test” just negotiated as part of the settlement contract was now optional on the part of the Forest Service; (2) the pricing mechanism was changed to remove any advantage APC enjoyed over competitively bid independent timber sales; and (3) utility logs were now to be counted as part of the quantity APC could log.

Relations After the TTRA

The period between the enactment of the TTRA in November 1990 and the government’s decision to terminate the contract in early 1994 is central to the dispute between the parties, and particularly to the issues immediately before us. While plaintiff objected to the unilateral changes imposed by TTRA, it continued to perform under the contract, at least in part. The government contends that APC acquiesced in the government’s performance as modified by the Act and thus waived any rights it might have had under a repudiation/material breach theory. Plaintiff argues that it continued to observe the contract even as it pursued negotiations in an effort to preserve the basic contractual relationship. Apparently these negotiations continued from early 1991 before the new terms went into effect, at least until APC challenged the TTRA terms in U.S. District Court in June 1993, and perhaps even after it brought that suit.

Plaintiffs suit in United States District Court in Alaska sought to nullify the TTRA changes and to enforce the terms of the settlement contract, citing the Administrative Procedures Act, 5 U.S.C. §§ 701-706, and the Declaratory Judgment Act, 28 U.S.C. § 2201. Alaska Pulp Corporation v. United States, Case No. J93-010 (D.Alaska 1993).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Industrial Door Contractors, Inc. v. United States
79 Fed. Cl. 413 (Federal Claims, 2007)
Precision Pine & Timber, Inc. v. United States
62 Fed. Cl. 635 (Federal Claims, 2004)
Alaska Pulp Corp. v. United States
59 Fed. Cl. 400 (Federal Claims, 2004)
Westfed Holdings, Inc. v. United States
52 Fed. Cl. 135 (Federal Claims, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
48 Fed. Cl. 655, 2001 U.S. Claims LEXIS 19, 2001 WL 185178, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alaska-pulp-corp-v-united-states-uscfc-2001.