Firth Construction Co. v. United States

41 Cont. Cas. Fed. 76,970, 36 Fed. Cl. 268, 1996 U.S. Claims LEXIS 129, 1996 WL 409079
CourtUnited States Court of Federal Claims
DecidedJuly 22, 1996
DocketNo. 96-393C
StatusPublished
Cited by23 cases

This text of 41 Cont. Cas. Fed. 76,970 (Firth Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Firth Construction Co. v. United States, 41 Cont. Cas. Fed. 76,970, 36 Fed. Cl. 268, 1996 U.S. Claims LEXIS 129, 1996 WL 409079 (uscfc 1996).

Opinion

ORDER ON MOTION FOR PRELIMINARY AND PERMANENT INJUNCTION

BRUGGINK, Judge.

This is an action brought pursuant to 28 U.S.C. § 1491(a)(8) (1994). It concerns a dispute over the award of a contract to lay additional railroad track at Fort Campbell, Kentucky, by the Louisville District of the United States Army Corps of Engineers (“Corps”). Firth Construction Co. (“Firth”) seeks an order permanently enjoining an award to the apparent low bidder, M.R. Dillard Construction Co. (“Dillard”). Dillard has been served with all the pleadings here and has made an appearance to defend its interests. The dispute has been the subject of an opinion by the General Accounting Office (“GAO”). The Government voluntarily agreed not to make the award to Dillard prior to July 23, 1996. The parties have agreed to merge consideration of the motions for preliminary and permanent injunctions. Argument was heard on July 18, 1996. For the following reasons, the court grants the permanent injunction sought by Firth.

BACKGROUND1

The Corps issued Solicitation No. DACA27-96-B-0014 on January 10, 1996. The invitation for bids (“IFB”) was on Standard Form (“SF”) 1442, as required by the Federal Acquisition Regulations (“FAR”). 48 C.F.R. § 53.236-l(e).2 Offerors were required to complete the SF 1442 in responding to the IFB. Six amendments were issued to the IFB using SF 30s. Only one is relevant to the resolution of this dispute. An SF 30 was issued on February 2, 1996, announcing Amendment No. 0003. Its only effect was to change the bid opening date from February 13 to February 22, 1996. The SF 30 bore the legend: “Page 1 is deleted and page 1 (Arndt. # 0003), enclosed, is substituted therefor.” Attached to the SF 30 was a revised SF 1442, reflecting the new bid opening date.3

The Corps received fifteen responses to the IFB. Dillard was the apparent low bidder, at $13,425,372. Firth submitted the second lowest bid, at $13,519,737.62. The high bid was $16,925,486. The Corps’ “Synopsis of bid opening” noted a number of defects in Dillard’s submission. Dillard was bidder “#2.” The synopsis records under “Infor-malities,” that “# 2 did not complete [Repre[270]*270sentations & Certifications] (11(a)).” 4 Under “Other remarks,” it states that “# 2 failed to submit SF 1442 (Amendment 0003). Request completed SF 1442 (front & back page) if # 2 is successful low bidder.”

The GAO’s opinion recites that Dillard’s bid package included the first page of the original SF 1442. The record assembled by the parties reflects no such page. The circled number “2”, placed on Dillard’s submission by the Corps at the bid opening, appears on its SF 24, the bid bond. Normally the bidder’s number would appear on the first page of the SF 1442, as that would be the covering document for a bidder’s package.

The agency offered the affidavit of Ms. Denise Gill, a procurement technician for the Corps. She observed the opening of the bids and was tasked with reviewing the bidding papers for discrepancies. Ms. Gill recites that Dillard’s bid did not include either the front or back page of an SF 1442. The only evidence to the contrary is contained in the affidavit of Harry Q. Horner, General Superintendent for Dillard. Mr. Horner participated in putting together Dillard’s bid. He avers that Dillard’s submission included page one of the original SF 1442. The court need not resolve this issue, however. The GAO opinion places no reliance on the presence of the first page of an SF 1442. It is undisputed that the back page of the original SF 1442 was not submitted. Nor is there any dispute that no part of the new SF 1442 accompanied the cover sheet of Amendment 0003 when it was returned by Dillard as part of its bid package.

In addition to the name, address, and phone number of the offeror, the missing second page of the SF 1442 indicates the bid amount and the minimum bid acceptance period. It also reflects an acknowledgement of amendments as well as the requirement to submit performance and payment bonds, and it calls for the name, title and signature of a person authorized to bind the company to the offer.

Materials submitted as part of Dillard’s bid package included the first page of the SF 30, acknowledging the amendment of the bid opening date. The signature of “M.R. Dillard, Owner” on the SF 30 was not an original, however, it was a stamp. No corporate resolution approving the use of such a stamp was enclosed. An Optional Form 336, which contained the total bid price and an abbreviated procurement integrity statement was included and bore the stamped signature of M.R. Dillard. Similarly, Dillard’s stamped signature was placed on the Bid Bond. The package also included Section K, containing various certifications and representations, although the response to part 11(a) was omitted. Finally, the bid package included a Certificate of Procurement Integrity (“CPI”), signed by Harry Horner. No title or office for Mr. Homer was provided with the submission, however.

As the apparent low bidder, the Corps advised Dillard that it had failed to submit a completed SF 1442. On February 28, six days after bid opening, Dillard faxed a completed form to the Corps, signed by M.R. Dillard. An original version was later submitted. On March 7,1996, the Corps awarded Contract No. DACA27-96-C-0040 to Dillard.

On March 11, 1996, Firth filed a protest with the Corps. Two days later, the Office of Counsel advised the Contracting Division that the award to Dillard was improper because its bid was non-responsive due to the lack of an original signature on the SF 1442, and due to the absence of any other satisfactory indication that the bidder intended to be bound. Based on this advice, by letter dated April 17, 1996, the Contracting Officer (“CO”) cancelled the award to Dillard, on the grounds that the contract was “invalid.”5

On April 26, Dillard protested the cancellation to the GAO. During the protest, Dillard submitted evidence that Horner was authorized to bind the company. On June 28, [271]*2711996, GAO sustained Dillard’s protest, concluding that Homer’s signature on the CPI was sufficient to render Dillard’s submission responsive. The GAO decision constitutes a recommendation to the Corps. The Corps has announced its intention to follow the recommendation and award the contract to Dillard. Accordingly, this action by Firth followed.

DISCUSSION

Jurisdiction

The court has jurisdiction over contract disputes pursuant to the Tucker Act. 28 U.S.C. § 1491(a)(1) (1994). The response to an invitation for bids by a bidder forms an implied contract, the terms of which require the Government to fairly and honestly consider an offeror’s bid. Keco Indus., Inc. v. United States, 192 Ct.Cl. 773, 780, 428 F.2d 1233, 1235 (1970). Once jurisdiction over the implied contract attaches, the court has authority to enjoin award of the contemplated procurement contract. 28 U.S.C. § 1491(a)(3).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wavelink, Inc v. United States
Federal Claims, 2021
Systems Application & Technologies, Inc. v. United States
100 Fed. Cl. 687 (Federal Claims, 2011)
Jacobs Technology Inc. v. United States
100 Fed. Cl. 186 (Federal Claims, 2011)
Ceres Gulf, Inc. v. United States
94 Fed. Cl. 303 (Federal Claims, 2010)
SP Systems, Inc. v. United States
86 Fed. Cl. 1 (Federal Claims, 2009)
Grunley Walsh International, LLC v. United States
78 Fed. Cl. 35 (Federal Claims, 2007)
NVT Technologies, Inc. v. United States
73 Fed. Cl. 459 (Federal Claims, 2006)
Armour of America v. United States
69 Fed. Cl. 587 (Federal Claims, 2006)
KSEND v. United States
69 Fed. Cl. 103 (Federal Claims, 2005)
Orion International Technologies v. United States
66 Fed. Cl. 569 (Federal Claims, 2005)
Waste Stream Environmental, Inc. v. Lynn Water & Sewer Commission
15 Mass. L. Rptr. 723 (Massachusetts Superior Court, 2003)
Brazos Electric Power Cooperative, Inc. v. United States
49 Fed. Cl. 398 (Federal Claims, 2001)
Alaska Pulp Corp. v. United States
48 Fed. Cl. 655 (Federal Claims, 2001)
Sucesion J. Serralles, Inc. v. United States
46 Fed. Cl. 773 (Federal Claims, 2000)
Lamirage, Inc. v. United States
44 Fed. Cl. 192 (Federal Claims, 1999)
Ryan Co. v. United States
43 Fed. Cl. 646 (Federal Claims, 1999)
Southern Foods Group, L.P. v. State, Department of Education
974 P.2d 1033 (Hawaii Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
41 Cont. Cas. Fed. 76,970, 36 Fed. Cl. 268, 1996 U.S. Claims LEXIS 129, 1996 WL 409079, Counsel Stack Legal Research, https://law.counselstack.com/opinion/firth-construction-co-v-united-states-uscfc-1996.