Unified Industries, Inc. v. United States

37 Cont. Cas. Fed. 76,226, 24 Cl. Ct. 570, 1991 U.S. Claims LEXIS 562, 1991 WL 255867
CourtUnited States Court of Claims
DecidedDecember 2, 1991
DocketNo. 91-1441C
StatusPublished
Cited by11 cases

This text of 37 Cont. Cas. Fed. 76,226 (Unified Industries, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Unified Industries, Inc. v. United States, 37 Cont. Cas. Fed. 76,226, 24 Cl. Ct. 570, 1991 U.S. Claims LEXIS 562, 1991 WL 255867 (cc 1991).

Opinion

OPINION

SMITH, Chief Judge.

On September 27,1991, defendant moved to dismiss Counts II to IV of plaintiff’s complaint.1 After careful consideration of the jurisdictional issues raised by defendant’s motion, the court grants the motion as it applies to Count III of the complaint, grants in part and denies in part the motion as it applies to Count IV, and denies the motion as it applies to Count II as amended pursuant to the court’s order of November 14, 1991.

FACTS

This case involves a procurement undertaken by the Navy for the management of the Source Data System (SDS). SDS is the automatic data processing pay system for members of the Navy stationed within the continental United States. The SDS program began in 1978, when the initial SDS contract was awarded to RGI, Inc. (RGI).

In February 1989, the Navy issued a solicitation for a follow-on to the SDS contract. Plaintiff submitted a proposal for the SDS follow-on along with four other contractors, including RGI. The Navy determined that only plaintiff and RGI were in the competitive range and technically capable of performing the contract. On November 15, 1989, the Navy awarded the follow-on contract to RGI. On November 22, plaintiff protested the award before the General Accounting Office (GAO). On April 2, 1990, the GAO issued a decision sustaining the protest and recommending remedial action.

During the GAO’s disposition of the plaintiff’s first bid protest, the Navy stayed performance of RGI’s protested award and extended RGI’s performance period under its existing contract. Plaintiff then filed another protest before the GAO challenging those extensions as improper sole-source awards of bridge contracts to RGI. On December 19, 1990, the GAO rejected this protest, finding the Navy’s actions reasonable under the circumstances.

On January 9,1991, the Contracting Officer (CO) disqualified plaintiff from further competition for the follow-on SDS contract because plaintiff had acquired access to computer diskettes containing proprietary information of RGI, thereby gaining unfair competitive advantage. Plaintiff admits having this information, which allegedly showed that RGI employees were paid wages below that required by federal law. Plaintiff voluntarily conveyed this information to the government prior to its disqualification, presumably in an unsuccessful attempt to discredit RGI.

In accordance with the GAO’s ruling in the first bid protest, the Navy resolicited proposals for award of the SDS follow-on contract. On April 1, 1991, the Navy also issued RGI a further extension of its existing SDS contract. The April 1 option is significant for the court’s consideration of the government’s motion because it contained a clause affording the government a six month extension option beyond that [572]*572originally provided for in the original SDS contract.

On July 10, 1991, the Navy awarded the follow-on SDS contract to Computer Data Systems, Inc. (CDSI). On July 19, 1991, RGI protested that award before the General Services Board of Contract Appeals (GSBCA). In a July 31, 1991 order, following a suspension hearing, the GSBCA suspended performance of the contract awarded to CDSI, pursuant to the Brooks Act, pending a decision on RGI’s protest. The Board suspended performance of the new SDS contract with CDSI because RGI had an existing contract under which needed pay and personnel services could continue to be provided in the interim. Plaintiff filed its complaint and its motion for a preliminary injunction in this court on September 19, 1991. The court held a status conference on September 24, 1991 to determine the urgency of the relief sought by plaintiff. At that conference, the government raised the issue whether this court had jurisdiction over plaintiff’s motion for a preliminary injunction. On September 27, 1991, defendant filed a motion to dismiss Counts II to IV of plaintiff’s complaint.

On October 1, 1991, the GSBCA issued a decision granting RGI’s protest. The Board found that the Navy failed to treat RGI and CDSI equally both in evaluating the two offerors’ proposals and during procurement discussions. The Board ordered the Navy to (1) reevaluate the offerors’ technical proposals in a consistent fashion and (2) to reopen discussions with RGI and CDSI. Finally, the Board reinstituted the Navy’s procurement authority which, as noted above, had been suspended during the pendency of the protest.

DISCUSSION

1. Plaintiff’s motion for a preliminary injunction

Plaintiff seeks equitable relief in Counts II to IV of its complaint:

Count II seeks a declaration that CDSI is not a responsible source for the award of the contract and seeks to enjoin the Navy from issuing any notice or authority to CDSI that would direct or allow it to enter into performance under the contract it was awarded on July 10, 1991; Count III seeks declaratory judgment that the award of sole source bridge contracts to RGI violates 10 U.S.C. Chapter 137 and asks the court to enjoin all future bridge contracts and to terminate any present bridge contract within fourteen days of the court’s order;
Count IV seeks a declaration that plaintiff was the only responsible source in the competitive range and requests an injunction mandating the Navy award the contract to plaintiff or, alternatively, enter into negotiations only with plaintiff for the award of the contract.

Oral argument on defendant’s motion to dismiss took place on November 13, 1991. After the argument, the court issued an order dated November 14, 1991, granting plaintiff leave to amend its complaint to reassert Counts II and IV. Plaintiff so amended its complaint on November 22, 1991. The following opinion sets forth the oral ruling given the parties on November 20, 1991.

II. Defendant’s motion to dismiss for lack of jurisdiction

A. Count II

In its motion, defendant argues that because the complaint was filed after the award of the Source Data Systems (SDS) contracts at issue—(1) the original contract, and extensions to that contract, awarded to RGI and (2) the follow-on contract awarded to CDSI—the court lacks subject matter jurisdiction to grant the injunctive relief plaintiff seeks in Count II.2 Defendant bases its Count II dismissal argument on the Tucker Act, which defines this court’s equitable jurisdiction:

To afford complete relief on any contract claim brought before the contract is awarded, the court shall have exclusive jurisdiction to grant declaratory judgments and such equitable and extraordi[573]*573nary relief as it deems proper, including but not limited to injunctive relief.

28 U.S.C. § 1491(a)(3) (Supp.1991) (emphasis added). Defendant argues that because plaintiff filed its complaint after the award of the two contracts at issue, the Tucker Act precludes this court from granting the equitable relief plaintiff seeks.

The court agrees with defendant that the Tucker Act precluded this court from having jurisdiction over Count II before the GSBCA rendered its decision on RGI’s bid protest.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Square One Armoring Service, Inc. v. United States
123 Fed. Cl. 309 (Federal Claims, 2015)
Ceres Gulf, Inc. v. United States
94 Fed. Cl. 303 (Federal Claims, 2010)
Arko Executive Services, Inc. v. United States
78 Fed. Cl. 420 (Federal Claims, 2007)
Micalizzi v. Rumsfeld
247 F. Supp. 2d 556 (D. Vermont, 2003)
Storage Technology Corp. v. CCL Service Corp.
94 F. Supp. 2d 697 (D. Maryland, 2000)
Fore Systems Federal, Inc. v. United States
40 Fed. Cl. 490 (Federal Claims, 1998)
Hydro Engineering, Inc. v. United States
41 Cont. Cas. Fed. 77,135 (Federal Claims, 1997)
Firth Construction Co. v. United States
41 Cont. Cas. Fed. 76,970 (Federal Claims, 1996)
Ims Services, Inc. v. United States
40 Cont. Cas. Fed. 76,757 (Federal Claims, 1994)
Aerolease Long Beach v. United States
31 Fed. Cl. 342 (Federal Claims, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
37 Cont. Cas. Fed. 76,226, 24 Cl. Ct. 570, 1991 U.S. Claims LEXIS 562, 1991 WL 255867, Counsel Stack Legal Research, https://law.counselstack.com/opinion/unified-industries-inc-v-united-states-cc-1991.