Arko Executive Services, Inc. v. United States

78 Fed. Cl. 420, 2007 U.S. Claims LEXIS 286, 2007 WL 2705904
CourtUnited States Court of Federal Claims
DecidedSeptember 12, 2007
DocketNos. 05-1193C, 06-0296C
StatusPublished
Cited by7 cases

This text of 78 Fed. Cl. 420 (Arko Executive Services, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arko Executive Services, Inc. v. United States, 78 Fed. Cl. 420, 2007 U.S. Claims LEXIS 286, 2007 WL 2705904 (uscfc 2007).

Opinion

OPINION

ALLEGRA, Judge.

This case, which arises under the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613, stems from a contract between plaintiff, Arko Executive Services, Inc. (Arko), and the United States to provide guard services at the United States Embassy in Nicosia, Cyprus (the Embassy). Plaintiff claims that it is entitled to additional compensation owing to the extension of this contract. Defendant argues that the extension was properly made under the option to extend services clause found in one provision of the Federal Acquisition Regulation (FAR), 48 C.F.R. § 52.217-8, while plaintiff asserts that the extension could have occurred only under the continuity of services clause found in another FAR provision, 48 C.F.R. § 52.237-3. Unlike the former clause, the latter provides for the reimbursement of certain extraordinary costs, the recoverability of which forms the crux of this dispute.

I. BACKGROUND

Arko is a Georgia corporation that provides private security services. The United States Department of State (State Department) retained Arko to provide security guard services to the Embassy. This agreement was embodied in Contract No. S-CY-600-00-0006 (the “contract”).

Section F.4.1. of the contract, entitled “Period of Performance,” specified that “[t]he period of this contract is from the date of Notice to Proceed and continuing for 12 months, with four, one-year options to renew.” Other portions of section F.4. provided for the continued performance of the contractor pursuant to two standard FAR provisions, FAR §§ 52.217-8 and 52.217-9. The first of these, entitled “Option to Extend Services,” which was incorporated by reference, provided, in pertinent part:

The Government may require continued performance of any services within the lim[422]*422its and at the rates specified in the contract ... The option provision may be exercised more than once, but the total extension of performance hereunder shall not exceed 6 months. The Contracting Officer may exercise the option by written notice to the Contractor within [the period specified in the Schedule].

48 C.F.R. § 52.217-8. The second provision, FAR § 52.217-9, “Option to Extend the Term of the Contract,” which was incorporated in full text in section 1.1.2. of the contract, allowed the government to renew the contract for an additional one-year term by written notice to the contractor, provided certain notice provisions were observed. This clause also provided that the “total duration of this contract, including the exercise of any options under this clause, shall not exceed five years.” FAR § 52.217-9(e).

The contract contained yet another extension provision, FAR § 52.237-3, entitled “Continuity of Services[,]” which, as restated in section 1.1.2. of the contract, provided that the contractor shall “furnish phase-in, phaseout services for up to 90 days after [the] contract expires” upon written notice from the contracting officer. FAR § 52.237-3(b). This clause, inter alia, required the contractor to “negotiate in good faith a plan with a successor to determine the nature and extent of phase-in, phase-out services required,” which plan “shall specify a training program and a date for transferring responsibilities for each division of work described in the plan.” Id. FAR § 52.237-3(d) provided for reimbursement of “all reasonable phase-in, phase-out costs ... and a fee (profit) not to exceed a pro rata portion of the fee (profit) under this contract.”

The government exercised all four one-year options available under FAR § 52.217-9 and F.4.2., thereby extending the contract to March 31, 2005. In the midst of the last option year, the State Department, on November 10, 2004, issued a solicitation for a successor contract. On February 8, 2005, Arko wrote the State Department’s contracting officer and asked whether its services would be required “beyond the March 31, 2005 expiration date of the contract.” Receiving no response, on February 15, 2005, Arko sent an e-mail to the contracting officer stating that it assumed that its services would not be needed after March 31, 2005. The contracting officer replied that the Embassy did not anticipate the need for these services.

Nonetheless, in early March 2005, it became evident to the contracting officer that, due to unforeseen delays, the State Department would not have a successor contractor in place by April 1, 2005. On March 4, 2005, the contracting officer tendered Modification No. 21 to Arko’s project manager in Cyprus. That modification called for Arko to provide guard services from April 1, 2005, to April 30, 2005, citing, as authority for this modification, FAR § 52.217-8 “Option to Extend Services.” Appended to the modification was a document setting forth prices for the work. The modification stated that all other terms and conditions of the contract remain the same. Arko disagreed that FAR § 52.217-8 provided authority to extend services after March 31, 2005, arguing instead that FAR § 52.237-3 provided the sole basis for doing so. On March 14, 2005, Arko informed the contracting officer that it would continue to provide guard services, but would do so under protest and seek compensation under FAR § 52.237-3 for the services provided commencing April 1, 2005.

On March 18, 2005, the contracting officer issued a final decision reiterating that he was requesting the extended services pursuant to FAR § 52.217-8, that compensation would be in accordance with the prices given in the modification, and that services would now be needed for additional month, making the total extension period from April 1, 2005, to May 31, 2005. The decision further explained: “In addition, fearing that 30 days may not be enough the Embassy feels compelled to amend the extension to 60 days. This will allow enough time for the new contractor to be fully operational and will avoid having to extend later on.” Arko provided the guard services from April 1, 2005, through May 31, 2005, again under protest. On April 26, 2005, the State Department awarded a contract to Wackenhut International with a start date of June 1, 2005.

[423]*423On November 10, 2005, Arko filed a complaint in this court seeking a determination that the contracting officer’s final decision was “void, unenforceable, arbitrary, capricious, and not in accordance with law and should be set aside (with the amount due Plaintiff to be determined),” and that Arko was entitled to compensation pursuant to FAR § 52.237-3. This initial complaint did not seek an explicit amount of monetary damages. On January 18, 2006, Arko submitted a $184,010.10 claim to the contracting officer for reimbursement for “phase-out” work provided after March 31, 2005. On March 21, 2006, the contracting officer denied this claim on the basis that services were provided pursuant to FAR § 52.217-8 at the rates indicated in the modification. On April 14, 2006, plaintiff filed a second complaint (06-296C) seeking $184,010.10 in damages, as well as fees and costs. On May 12, 2006, the court consolidated these cases.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Emiabata v. United States
102 Fed. Cl. 787 (Federal Claims, 2012)
Angelica Textile Services, Inc. v. United States
95 Fed. Cl. 208 (Federal Claims, 2010)
NEQ, LLC v. United States
88 Fed. Cl. 38 (Federal Claims, 2009)
Clearmeadow Investments, LLC v. United States
87 Fed. Cl. 509 (Federal Claims, 2009)
Abbott Laboratories v. United States
84 Fed. Cl. 96 (Federal Claims, 2008)
Information Systems & Networks, Corp. v. United States
81 Fed. Cl. 740 (Federal Claims, 2008)
Schortmann v. United States
82 Fed. Cl. 1 (Federal Claims, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
78 Fed. Cl. 420, 2007 U.S. Claims LEXIS 286, 2007 WL 2705904, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arko-executive-services-inc-v-united-states-uscfc-2007.