L.P. Consulting Group, Inc. v. United States

66 Fed. Cl. 238, 2005 U.S. Claims LEXIS 182, 2005 WL 1592954
CourtUnited States Court of Federal Claims
DecidedJuly 7, 2005
DocketNo. 98-868 C
StatusPublished
Cited by40 cases

This text of 66 Fed. Cl. 238 (L.P. Consulting Group, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L.P. Consulting Group, Inc. v. United States, 66 Fed. Cl. 238, 2005 U.S. Claims LEXIS 182, 2005 WL 1592954 (uscfc 2005).

Opinion

OPINION

ALLEGRA, Judge.

This government contract case, before the court on cross-motions for summary judgment, involves a series of claims under the Contract Disputes Act of 1978(CDA) (41 U.S.C. § 609(a)). Plaintiff alleges that no less than twelve contracts arose out of two Indefinite Quantity Contracts (IQC), under which defendant allegedly promised plaintiff work on various projects. Plaintiff alleges that this work did not materialize and that it is owed lost profits on the contested project awards, as well as statutory interest under the CDA. For the reasons that follow, the court finds in favor of defendant.

I. BACKGROUND

In May of 1994, the United States Postal Service (USPS) awarded L.P. Consulting, Inc., the plaintiff herein (plaintiff), IQC No. 162640-94-B-0083, with a two-year term. On June 3, 1996, and June 6, 1996, USPS awarded two more IQCs to plaintiff, numbered 162640-96-B-0098 and 162640-96-B-0094, respectively. The latter contracts, which are the foci of this case, also had two-year terms and covered general construction work at postal facilities in North Central Illinois. Each contract entitled plaintiff to a minimum of $10,000 in work. Although the parties dispute the actual amount that plaintiff received under the contracts, they agree that it received more than $1,000,000 worth of work orders under the 1994 contract and over $440,000 on the 1996 contracts.

[240]*240All three IQCs specified that “work will be done on work orders issued as required.” They each further provided that “[p]rice proposals mil be required for each Work Order.” (Emphasis in original). After the price proposal had been submitted, the IQCs specified the steps to finalize a work order:

No work will be performed until a written work order has been signed by the contractor and the contracting officer and written Notice to Proceed with the work under the work order has been issued by the contracting officer and received by the contractor.

This same provision warned — “[a]ny work performed by the contractor under a work order before receipt of a written Notice to Proceed for that work order will be at the contractor’s own risk.” Other provisions of the contract emphasized, in various ways, that work should not be performed until a formal written work order and a notice to proceed had been issued, stating, inter alia, that: (i) “[t]he date for beginning work under a work order may not be less than three calendar days nor more than ten calendar days from the date of receipt the contractor of the Notice to Proceed;” (ii) “[i]f the Notice to Proceed under a work order is not received by the contractor before the expiration date of the contract, the work order will be considered terminated for the convenience of the Postal Service;” and (iii) “[w]here ... ‘acceptance,’ or words of a similar nature are used, it must be understood that such words refer to actions to be taken, in writing, by the Contracting Officer unless otherwise stated.” Finally, the IQCs emphasized that “[t]he Postal Service reserves the right to undertake, by Postal Service sources or others, the same type of work or similar work as contracted for in this contract, in the area covered by this contract, while this contract is in force.”

In the case subjudice, plaintiff asseverates that it had contracts to perform twelve projects on which it prepared draft work orders. It alleges that once it submitted the draft work orders, it either had express or implied-in-fact contracts with defendant to perform the work, and that defendant breached those contracts when it either chose not to proceed with the work or awarded the work to another contractor. On March 3, 1998, plaintiff submitted a claim to this effect to the contracting officer, in connection with four of the alleged projects. On April 13, 1998, plaintiff resubmitted this claim in certified form and submitted a certified claim in connection with eight more projects. On August 11, 1998, plaintiff submitted an amended certification for the above claims. After the claims were denied, on November 13, 1998, plaintiff filed suit in this court under the CDA, seeking a total of $135,337 for losses it allegedly sustained when defendant allegedly breached either the express or implied-in-fact contracts associated with the work orders. The case was subsequently stayed. On January 14, 2005, defendant filed a motion for summary judgment; on February 18, 2005, plaintiff filed a cross-motion for summary judgment. On June 14, 2005, the court conducted oral argument on the cross-motions.

II. DISCUSSION

Summary judgment is appropriate when there is no genuine dispute as to any material fact and the moving party is entitled to judgment as a matter of law. RCFC 56; Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247-48, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). Disputes over facts that are not outcome-determinative will not preclude the entry of summary judgment. Id. at 248, 106 S.Ct. 2505; Cornejo-Ortega v. United States, 61 Fed.Cl. 371, 373 (2004). The court must determine whether the evidence presents a disagreement sufficient to require submission to fact finding, or whether it is so one-sided that one party must prevail as a matter of law. Anderson, 477 U.S. at 250-52, 106 S.Ct. 2505; United Medical Supply Co., Inc. v. United States, 63 Fed.Cl. 430, 435 (2005). In doing this, all facts must be construed in a light most favorable to the nonmoving party and all inferences drawn from the evidence must be viewed in the light most favorable to the party opposing the motion. Matsushita Elec. Indus. Co., Ltd. v. Zenith Radio Corp., 475 U.S. 574, 587, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986) (citing United States v. Diebold, 369 U.S. 654, 655, 82 S.Ct. 993, 8 L.Ed.2d 176 (1962)).

[241]*241At issue is whether plaintiff had actual or implied-in-fact contracts with the USPS to perform the work listed on the draft work orders it prepared. Plaintiff concedes that the requirements for creating express contracts under the 1996 IQCs were not met — as to each of the twelve projects, neither the requisite written work order nor a notice to proceed were issued. As such, under the terms of the IQCs, plaintiff proceeded at its “own risk.” Conventio vincit legem.

Nonetheless, plaintiff argues that, owing to a prior course of conduct, the USPS waived both the formal written work order and notice to proceed requirements. The doctrine of waiver applies when defendant

has administered an initially unambiguous contract in such a way as to give a reasonably intelligent and alert opposite party the impression that a contract requirement has been suspended or waived .... [T]he requirement cannot be suddenly revived to the prejudice of a party who has changed his position in reliance on the supposed suspension.

Gresham & Co., Inc. v. United States, 200 Ct.Cl. 97, 470 F.2d 542, 555 (1972).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northrop Grumman Computing Systems, Inc. v. United States
120 Fed. Cl. 460 (Federal Claims, 2015)
Urban v. United States
119 Fed. Cl. 57 (Federal Claims, 2014)
Lakeshore Engineering Services, Inc. v. United States
110 Fed. Cl. 230 (Federal Claims, 2013)
Robert F. Goeller and Jeanette M. Goeller v. United States
109 Fed. Cl. 534 (Federal Claims, 2013)
Burgess v. United States
109 Fed. Cl. 223 (Federal Claims, 2013)
Douglas R. Bigelow Trust v. United States
107 Fed. Cl. 490 (Federal Claims, 2012)
Dobyns v. United States
106 Fed. Cl. 748 (Federal Claims, 2012)
Alli v. United States
105 Fed. Cl. 440 (Federal Claims, 2012)
Pew Forest Products v. United States
105 Fed. Cl. 59 (Federal Claims, 2012)
Emiabata v. United States
102 Fed. Cl. 787 (Federal Claims, 2012)
Carolina Plating Works, Inc. v. United States
102 Fed. Cl. 555 (Federal Claims, 2011)
Presidio Advisors, LLC v. United States
101 Fed. Cl. 393 (Federal Claims, 2011)
Jicarilla Apache Nation v. United States
100 Fed. Cl. 726 (Federal Claims, 2011)
AEY, Inc. v. United States
99 Fed. Cl. 300 (Federal Claims, 2011)
Parkwood Associates Ltd. Partnership v. United States
97 Fed. Cl. 809 (Federal Claims, 2011)
Lublin Corp. v. United States
98 Fed. Cl. 53 (Federal Claims, 2011)
Stovall v. United States
94 Fed. Cl. 336 (Federal Claims, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
66 Fed. Cl. 238, 2005 U.S. Claims LEXIS 182, 2005 WL 1592954, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lp-consulting-group-inc-v-united-states-uscfc-2005.