International Business Investments, Inc. v. United States

36 Cont. Cas. Fed. 75,826, 19 Cl. Ct. 715, 1990 U.S. Claims LEXIS 48, 1990 WL 28192
CourtUnited States Court of Claims
DecidedMarch 16, 1990
DocketNo. 543-87C
StatusPublished
Cited by2 cases

This text of 36 Cont. Cas. Fed. 75,826 (International Business Investments, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
International Business Investments, Inc. v. United States, 36 Cont. Cas. Fed. 75,826, 19 Cl. Ct. 715, 1990 U.S. Claims LEXIS 48, 1990 WL 28192 (cc 1990).

Opinion

OPINION

SMITH, Chief Judge.

This case, which is before the court on cross-motions for summary judgment, involves the application of prompt payment discounts to contracts between the government and a private contractor. The issues presented are: (i) whether the contractor is entitled to recover all prompt payment discounts taken during the course of the contract, where the contractor believed that the amount of the discount was too high at the time it was taken; and (ii) whether the government's exercise of contractual options to extend the contract entitles the contractor to interest on the overdiscounted amounts under the Prompt Payment Act, 31 U.S.C. §§ 3901-3906 (1982) (PPA), as well as under the Contract Disputes Act, 41 U.S.C. §§ 601-613 (1982) (CDA), where the original contract was executed prior to the effective date of the PPA, but the options were exercised after such date. For the reasons given below, the court grants partial summary judgment for defendant and partial summary judgment for plaintiff.

FACTS

Contract no. N62467-81-C-2765 was awarded to International Business Investments, Inc. (IBI), by the United States Navy, on September 28, 1981. The contract required IBI to provide security guard services at the Naval Air Station located in Key West, Florida. While the contract provided for an initial term of one year, it also gave the Navy the right to exercise two one-year options to renew. Both option years were taken by the Navy, and further modifications to the contract extended it for a fourth year. The contract completion date was September 30, 1985.

IBI’s proposal included a two-percent discount for prompt payment within twenty calendar days after the Navy’s receipt of a [717]*717proper invoice. IBI’s bid was second-lowest on its face, but the Navy deemed IBI’s bid to be lowest because of anticipated application of the two-percent prompt payment discount. During the first year of the contract the government took all prompt payment discounts properly due it.

Beginning with the first option year, which started on October 1, 1982, various contract modifications incorporated statutorily mandated wage increases into the contract.1 These modifications increased each invoice by the amount of the increased wages. The prompt payment discount taken by the government also increased by two percent of the increased wages. The contract did not contain terms covering the application of the prompt payment discount to the portion of the contract price increased to reflect revised wage determinations.

IBI avers in an affidavit in support of its cross-motion for summary judgment, that it told Navy officials in 1982 that the amount of the discount attributed to the increased wage was wrongfully taken. Defendant counters in an affidavit of the contracting officer (CO) that no such conversations took place. The first written indication of a dispute did not occur until October 17, 1985, at the expiration of the contract, in a letter from plaintiff to the CO.

On December 22, 1986, plaintiff filed a claim with the CO. In that claim, plaintiff sought to recover all prompt payment discounts taken, as well as interest under the PPA. The CO, relying upon Jets Services Inc., ASBCA No. 19070, 74-2 BCA 1110,649 (1974), agreed that the amount of the discount related to the wage increases— $3,603.68 — was wrongfully taken.2 The CO also awarded interest under the CDA, running from the time the claim was filed with the CO until his decision was rendered. However, the CO declined to award interest under the PPA, concluding that the exercise of options to extend the contract made after the October 1, 1982 effective date of the PPA did not create a new contract covered by the PPA, but merely served to renew the original one. In addition, the CO declined to pay plaintiff the full amount of all prompt payment discounts taken — approximately $42,000— finding that the Navy had taken its discount in good faith and without knowledge of impropriety. This appeal followed.

DISCUSSION

I. Prompt payment discounts.

The first issue for the court to resolve is whether IBI is entitled to recover all prompt payment discounts taken by the Navy, as a matter of law.

Summary judgment is appropriate where the pleadings, affidavits, and other papers before the court show that there is no genuine issue of material fact, and that the moving party is entitled to judgment as a matter of law. RUSCC 56(c). The burden is on the opponent of the motion to come forth with a showing of genuinely disputed material facts. Celotex Corp. v. Catrett, 477 U.S. 317,106 S.Ct. 2548, 91 L.Ed.2d 265 (1986); Sweats Fashions, Inc. v. Pannill Knitting Co., 833 F.2d 1560 (Fed.Cir.1987). However, the party opposing summary judgment must show an evidentiary conflict on the record; mere denials or condu[718]*718sory statements are not sufficient to defeat a summary judgment motion. Barmag Barmer Maschinenfabrik AG v. Murata Machinery, Ltd., 731 F.2d 831, 836 (Fed.Cir.1984).

Defendant’s central argument for summary judgment is that the CO has already granted the full relief to which plaintiff is entitled by law under the facts of the case. IBI, on the other hand, argues for summary judgment because the Navy’s overapplication of the discount rate transformed the full payments into partial payments, and therefore since full payment was not timely made, the Navy was not entitled to prompt payment discounts at all.

The court initially notes that the facts are minimally disputed. The main issue presented is whether plaintiff is entitled as a matter of law to payment of all prompt payment discounts taken by the Navy during the course of the option years of this contract. These years cover the three year period from October 1, 1982 to September 30, 1985. During this period, the Navy took prompt payment discounts on all invoices presented to it. In doing so, however, the Navy erred in applying the discount to that portion of the invoices representing increased wages. Plaintiff argues that this mistake recasts full payments into partial payments, entitling it to recover all of the discounts taken.

Plaintiff’s argument relies heavily upon ISS Energy Services, Inc., GSBCA No. 7679, 85-3 BCA 1118,178 (1985), Dan’s Janitorial Service, Inc., ASBCA No. 29486, 86-3 BCA 1119,238 (1986), and Commercial Systems, Inc., B-213466, 84-1 CPD It 532 (1984). In ISS Energy Services, the General Services Board of Contract Appeals held that partial payment of an undisputed invoice within the discount period does not entitle the government to the prompt payment discount. However, as the government argues, ISS Energy Services is distinguishable from the present case. In ISS Energy Services,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

International Business Investments, Inc. v. United States
36 Cont. Cas. Fed. 75,906 (Court of Claims, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
36 Cont. Cas. Fed. 75,826, 19 Cl. Ct. 715, 1990 U.S. Claims LEXIS 48, 1990 WL 28192, Counsel Stack Legal Research, https://law.counselstack.com/opinion/international-business-investments-inc-v-united-states-cc-1990.