Grunley Walsh International, LLC v. United States

78 Fed. Cl. 35, 2007 WL 2323983
CourtUnited States Court of Federal Claims
DecidedAugust 13, 2007
DocketNo. 07-492
StatusPublished
Cited by14 cases

This text of 78 Fed. Cl. 35 (Grunley Walsh International, LLC v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grunley Walsh International, LLC v. United States, 78 Fed. Cl. 35, 2007 WL 2323983 (uscfc 2007).

Opinion

OPINION & ORDER

FUTEY, Judge.

This bid protest is before the court on the parties’ cross-motions for judgment upon the administrative record. Plaintiff asks this court to order the Department of State (“DOS”) to reinstate its pre-qualification for the FY 2007 New Embassy Compounds Design-Build Construction Program (“NEC Program”). Plaintiff alleges that the DOS’s decision to revoke plaintiffs pre-qualification was irrational, arbitrary, and capricious because a decision of the Government Accountability Office (“GAO”), upon which the DOS relied, was contrary to the plain meaning of the statute and did not give due deference to the DOS’s previous interpretation. Plaintiff argues that the business volume requirement contained in section 402 of the Omnibus Diplomatic Security and Antiterrorism Act of 1986, codified at 22 U.S.C. § 4852 (2000), requires that a bidder has achieved a total business volume equal to the value of the contract by cumulating three out of the previous five years. The GAO decided that three out of the previous five year's must individually equal the value of the contract. The DOS followed the GAO’s interpretation and withdrew plaintiffs and intervenor’s prequalification for the FY 2007 NEC Program. Plaintiff argues both that the GAO’s decision was wrong and that the DOS’s new interpretation is proeedurally deficient due to the lack of notice and comment rule making and a lack of reasoned and cogent explanation. American International Contractors (Special Projects), Inc. (“AIC-SP”) filed a motion to intervene as similarly situated to plaintiff. That motion was granted. Intervenor did not file a brief but did participate at oral argument. Defendant argues that the DOS’s new interpretation based on the GAO’s recommendation is reasonable because it gives effect to the legislative intent behind the statute and is entitled to deference as a statutory interpretation by an agency that is charged with administering it. Upon review of the record, the statute, and the parties’ respective arguments, the court concludes [37]*37that the DOS’s withdrawal of plaintiffs and intervenor’s pre-qualification was irrational, arbitrary, capricious, and not in accordance with the law.

Factual Background

At issue in this case is the opportunity to bid on ten contracts to construct embassies around the world in the DOS’s FY 2007 NEC Program. On January 3, 2007, the DOS issued a Notice of Solicitation for Submissions for Contractor Pre-Qualification (“the Pre-Qualification Notice’’), which requested prospective bidders to send certifications of their compliance with the requirements of 22 U.S.C. § 4852 in order to pre-qualify to bid on the embassy projects.1 The Pre-Qualification Notice informed offerors that the solicitation would consist of two phases: a prequalification phase and a request for proposals from the pre-qualified offerors. The Notice stated that “[tjhose Offerors determined to be pre-qualified in accordance with this notice will be issued a formal Request for Proposal (RFP) for each project and invited to submit proposed pricing in Phase II.”2

Section 4 of the Pre-Qualification Notice detailed the pre-qualification requirements. The relevant part instructed offerors that the acquisition was limited to bidders qualified as a “United States Person” as defined in section 402 of the Omnibus Diplomatic Security and Antiterrorism Act of 1986 (“the Act”).3 Prospective bidders were thus instructed to complete and submit certifications 4 to show that they met the requirements of section 402. Section 402 of the Act states, “The term ‘United States Person’ means a person which — with respect to a construction project ..., has achieved total business volume equal to or greater than the value of the project being bid in 3 years of the 5-year period before the date specified in subparagraph (C)(i)____” 22 U.S.C. § 4852(c)(2)(E) (2000). The Pre-Qualification Notice also allowed for previously pre-qualified offerors to submit a Letter of Interest in lieu of certifications if they had been pre-qualified for certain projects under the FY 2006 NEC Program. Plaintiff qualified as a previously pre-qualified offeror and submitted its Letter of Interest on January 17, 2007.5

The DOS replied to plaintiff by letter on February 23, 2007, stating that it anticipated plaintiffs pre-qualification for all projects on which it intended to bid, but it also requested updated certifications to be submitted before a final determination of qualification.6 Plaintiff submitted its updated pamphlet of certifications on March 1, 2007.7 The DOS replied to plaintiff via a letter dated April 9, 2007, notifying plaintiff that it had been pre-qualified to bid on all ten NEC Program projects.8 The letter also informed plaintiff that all prequalified offerors could expect to receive RFPs in May of 2007.9

On March 8, 2007, Caddell Construction Co., Inc. (“Caddell”) filed a protest at the GAO, protesting a contract under the FY 2006 NEC Program. Caddell was an unsuccessful offeror on a contract to build a new embassy complex in Djibouti, Djibouti. Plaintiff was also an unsuccessful offeror on the Djibouti contract but was not party to the protest at the GAO. Caddell claimed, in relevant part, that the successful offeror, AIC-SP, did not qualify to bid on the project because it did not meet the business volume requirement contained in section 402 of the Act. Caddell argued that, in order to qualify as a “United States Person,” the offeror had to have a total business volume equal to the value of the project bid in each of the three [38]*38out of five previous years. Put another way, three out the previous five years must individually equal the value of the project being bid on. AIC-SP’s business volume did not meet Caddell’s proposed interpretation.

The GAO issued its opinion on June 15, 2007.10 The GAO decided that the best interpretation of the statute requires offerors to meet the business volume requirement in each of three out of the past five years.11 The GAO decided that the language of the statute was ambiguous. Relying heavily on the legislative history of the Act, it decided that the three individual years interpretation gave better effect to the purpose of the statute. The GAO afforded no deference to the DOS’s previous interpretation, under which plaintiff had been pre-qualified for the FY 2006 and 2007 NEC Programs, because it was not “the result of either a rulemaking or an adjudication.”12

In a letter dated June 21, 2007, the DOS informed plaintiff that its pre-qualification had been withdrawn due to the GAO decision: “Pending any further litigation, the Department has decided to follow the recommendations of GAO in the Caddell protest and to apply the standard prescribed by GAO to its FY2007 NEC projects.”13 Plaintiff filed its complaint in this court on July 2, 2007. The Abbreviated Administrative Record was filed on July 9, 2007.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wavelink, Inc v. United States
Federal Claims, 2021
Caddell Construction Company v. United States
123 Fed. Cl. 469 (Federal Claims, 2015)
Pernix Group, Inc. v. United States
121 Fed. Cl. 592 (Federal Claims, 2015)
Caddell Construction Co., Inc. v. United States
111 Fed. Cl. 49 (Federal Claims, 2013)
One Largo Metro, Llc v. United States
109 Fed. Cl. 39 (Federal Claims, 2013)
Navarro Research & Engineering, Inc. v. United States
106 Fed. Cl. 386 (Federal Claims, 2012)
CBY Design Builders v. United States
105 Fed. Cl. 303 (Federal Claims, 2012)
Systems Application & Technologies, Inc. v. United States
100 Fed. Cl. 687 (Federal Claims, 2011)
Jacobs Technology Inc. v. United States
100 Fed. Cl. 186 (Federal Claims, 2011)
Turner Construction Co., Inc. v. United States
94 Fed. Cl. 561 (Federal Claims, 2010)
SP Systems, Inc. v. United States
86 Fed. Cl. 1 (Federal Claims, 2009)
Centech Group, Inc. v. United States
78 Fed. Cl. 496 (Federal Claims, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
78 Fed. Cl. 35, 2007 WL 2323983, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grunley-walsh-international-llc-v-united-states-uscfc-2007.