Turner Construction Co., Inc. v. United States

94 Fed. Cl. 561, 2010 WL 2795079
CourtUnited States Court of Federal Claims
DecidedJuly 16, 2010
DocketNo. 10-195C
StatusPublished
Cited by37 cases

This text of 94 Fed. Cl. 561 (Turner Construction Co., Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Turner Construction Co., Inc. v. United States, 94 Fed. Cl. 561, 2010 WL 2795079 (uscfc 2010).

Opinion

OPINION AND ORDER

FUTEY, Judge.

This is a post-award bid protest related to a contract for the replacement of Fort Ben-ning’s Martin Army Community Hospital (“the Hospital”). The United States Army [563]*563Corps of Engineers (“the Army”) awarded that contract to Turner Construction Company (“Turner”) on September 28, 2009. Turner’s two rivals for the contract, McCarthy/Hunt, JV (“MeCarthy/Hunt”), and B.L. Harbert-Brasfield & Gome, JV (“Har-bert/Gorrie”), who now intervene in this case, filed bid protests with the Government Accountability Office (“GAO”) in November 2009. The GAO on February 16, 2010 recommended that the Army strip Turner of the contract due to organizational conflicts of interest (“OCIs”) and re-procure the contract, with Turner eliminated from the competition. The Army announced on March 19, 2010 that it would follow GAO’s recommendation and not waive the OCIs. Turner then filed this bid protest on March 31, 2010.

Turner argues that the Army’s decision to strip Turner of the contract was arbitrary and capricious for three primary reasons: (1) because the GAO recommendation, which the Army implemented, lacked a rational basis; (2) because the Army did not conduct a full and independent evaluation of the GAO recommendation prior to implementing it; and (3) because the Army did not reasonably evaluate a request to waive the OCIs that were found. In its defense, defendant argues that the GAO recommendation was rational and that no precedent supports either a requirement to fully document a waiver decision or to evaluate a GAO recommendation.

The parties have made cross-motions for Judgment on the Administrative Record, under Rule 52.1(c) of the Rules of the United States Court of Federal Claims (“the Rules”). When resolving this type of motion, a court must make factual findings based upon the administrative record. See Bannum, Inc. v. United States, 404 F.3d 1346, 1356 (Fed.Cir. 2005). The parties have submitted numerous briefs, and oral argument was held on June 11, 2010.

I. Background

The Hospital is a 250-bed facility that serves more than 86,000 beneficiaries. The number of beneficiaries will grow to close to 100,000 by 2012. To provide for that increased demand, the Army sought bids for “the design and construction of a state-of-the-art full service medical treatment facility....”1

A. The Army Began the Bidding Process for the Hospital Project in Tune 2008.

In June 2008, the Army issued request for proposals (“RFP”) No. W912HN-07-R-0112 for a design-build contract to renovate the Hospital. The procurement would proceed in two phases. During Phase I, the Army would receive performance and capability information from potential offerors. The Army would select up to three offerors to move on to Phase II and provide these offer-ors with the Technical Provisions for the project. Using these requirements, the Phase II offerors would submit their proposals to the Army, who would evaluate the offerors’ technical capabilities and estimates and select the proposal that contained the best value for the Army. The RFP highlighted two important non-price factors to be considered in this evaluation: 1) “Design Technical” and 2) “Remaining Performance Capability.” According to the Army, “Design Technical” was the most important factor and contained four sub-factors.2 All of these non-price factors combined were of equal weight to the price of the contract. Although the RFP originally only contemplated an addition to the Hospital, the project expanded in July 2008 to encompass a complete replacement of the Hospital.

The Army held an industry forum in August 2008 to inform potential offerors of the opportunity at Fort Benning. On October 3, 2008, four firms, including Turner, submitted Phase I proposals. Two months later, on December 9, the Army’s Source Selection Evaluation Board (“SSEB”) selected three of these offerors to continue on to Phase II of the bid process: Turner, McCarthy/Hunt, and Harbert/Gorrie.

[564]*564B. The Army Awarded a Design Contract to TISMM/HOK to Provide “All Services Necessary" in Preparing the Plans, Specifications and Other Materials for the Hospital Project.

Due to the complexity of the project, the Army had previously entered into a design contract to obtain technical assistance. This contract, Contract No. W912HN-07-C-0038, was awarded to the Joint Venture of Hayes, Seay, Mattern & Mattern (“HSMM”) and Hellmuth, Obata & Kassbaum, Inc. (“HOK”) on June 8, 2007. Under the terms of the design contract, HSMM/HOK were to provide “all services necessary in the preparation of design documents, including plans, specifications, supporting design analysis, design narrative, cost estimates, etc. to construct a replacement hospital” at Fort Ben-ning.3 [* * *] the Army’s Senior Project Manager for the Hospital project, described this contract as encompassing “preparing the design concept” and assisting the Army with “preparation of [the RFP] and technical evaluation of proposals for the subsequent design-build contract.”4

At the time the design contract was awarded and throughout the procurement of the Hospital contract, HSMM was owned by AE-COM. AECOM is a “global provider of professional technical and management support services to a broad range of markets, including transportation, facilities, environmental, energy, water and government.” 5 After AE-COM acquired HSMM, HSMM employees began to transition to being part of the AE-COM corporate structure.6

C. The Army Awarded the Hospital Contract to Turner, with Ellerbe Becket as its Subcontractor in Charge of Design.

The Phase II offerors for the Hospital project submitted their proposals to the Army on July 7, 2009. Beginning on July 13, 2009, the Army’s Technical Review Board (“TRB”) met in Savannah, Georgia to evaluate the proposals. The TRB consisted of 34 members, four of whom were from HSMM. The TRB submitted comments that were reviewed by the SSEB on July 27-31, 2009. Using these comments, the SSEB prepared a report that ranked the proposals. Of the three Phase II offerors, Turner [* * *]. For the four Design Technical subfactors, which the Contracting Officer (“CO”) considered the most important to the project, Turner received an Above Average rating on three, [* * *]. Turner also submitted the lowest priced proposal, with an estimate of L* * *J MeCarthy/Hunt’s proposal and [* * *J Har-bert/Gorrie’s proposal.

The three offerors gave oral presentations to the Army on August 17-18, 2009; the four HSMM employees, who were part of the TRB, attended these presentations but did not ask any questions. On August 24, 2009, after i’eviewing the SSEB report, cost estimates, and presentations, the Source Selection Authority determined that Turner represented the best value for the Army. On September 28, 2009, the Army awarded Turner the contract in the amount of $333,359,000.

For the Hospital contract, Ellerbe Becket (“EB”) served as a subcontractor to Turner to provide “overall project design coordination for all design consultants....”7 This work was valued at approximately [* * *J, which would be split between EB and a firm that it was partnered with in a joint venture.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
94 Fed. Cl. 561, 2010 WL 2795079, Counsel Stack Legal Research, https://law.counselstack.com/opinion/turner-construction-co-inc-v-united-states-uscfc-2010.