H.H.O. Co. v. United States

34 Cont. Cas. Fed. 75,256, 12 Cl. Ct. 147, 1987 U.S. Claims LEXIS 57
CourtUnited States Court of Claims
DecidedApril 9, 1987
DocketNos. 113-83C, 201-86C
StatusPublished
Cited by17 cases

This text of 34 Cont. Cas. Fed. 75,256 (H.H.O. Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H.H.O. Co. v. United States, 34 Cont. Cas. Fed. 75,256, 12 Cl. Ct. 147, 1987 U.S. Claims LEXIS 57 (cc 1987).

Opinion

MEMORANDUM OPINION

LYDON, Judge:

In these direct access consolidated cases, brought under the Contract Disputes Act of 1978, 41 U.S.C. § 609(a) (1982), plaintiff, in complaints filed on March 25, 1986, (Docket No. 201-86C) and March 2, 1983 (Docket No. 113-83C) seeks to recover additional compensation relative to four Forest Service road construction contracts it entered into with the Department of Agriculture. Three of these contracts are the subject matter of the complaint in Docket No. 201-86C. These three contracts are identified as the Hoodoo Way Road No. 51 (Hoodoo contract) (No. 50-04H1-3-9182C); the East Six Mile Opted Timber Sale Roads (East Six Mile Contract) (No. 50-04H1-3-9264C); and the Alligator Opted Timber Sale Roads (Alligator contract) (No. 50-04H1-2-9052C). One of these contracts is the subject matter of the complaint in Docket No. 113-83C. This contract is identified as the Fishloop Opted Timber Sales Roads Project (Fishloop contract) (No. 50-04-HL-0-8010C).

Defendant has moved to dismiss these complaints on various grounds. In its motion, defendant asserts that four of the ten causes of action set forth in the consolidated complaints must be dismissed because plaintiff failed to bring suit within one-year of the challenged contracting officer’s final decision; that two of the ten causes of action must be dismissed because they were not submitted to the contracting officer in a timely manner as required by the contract; that three of the ten causes of action must be dismissed because they are no more than a repetition of plaintiff’s other barred causes of action; and that one of the ten causes of action must be dismissed because said cause of action had not been submitted to the contracting officer for decision. Plaintiff opposes defendant’s motion. Oral argument was waived by the parties.

FACTS

A. The Hoodoo Contract—Count I; First, Second Alternative and Third Alternative Cause of Action

Plaintiff and the Forest Service entered into the Hoodoo contract on March 15, 1983. The contract involved the reconstruction of the Hoodoo Way Road No. 51 in the Wallowa-Whitman National Forest, Oregon. Plaintiff, for the contract price of $162,531.30, was to provide additional drainage to an existing road, including the installation of culvert pipe, blind drains and cross drains.

During performance of the Hoodoo contract, a number of disputes arose as a result of which plaintiff filed six claims, uncertified, with the contracting officer. These claims were the subject of a final decision by the contracting officer dated October 26, 1983, in which these six claims were denied. These claims are contained in plaintiff's First Cause of Action and are to be found in Parts VI—IX, and XI of the complaint in Docket No. 201-86C.

The first of these six claims is based on the contention that a delay by the Forest Service in the issuance of a Notice to Proceed on all work items forced plaintiff to alter its schedule of operations thereby effectively accelerating its work performance. While a start work order had been issued for April 19, 1983, this order was applicable only to drilling and blasting work because an access road was closed to heavy equipment due to adverse conditions. A total work order to proceed was issued on June 6, 1983. No specific dollar amount was claimed by plaintiff in its submission to the contracting officer. This is the same claim set forth in Part VI, paragraphs 1 and 2 of the complaint in Docket No. 201-86C. The complaint does not assign a specific dollar amount to this claim.

The second of these six claims is based on the excavation for placement of perforated pipe, where rock was encountered which had to be drilled and shot. Plaintiff claimed that a differing site condition was encountered which plaintiff could not discover prior to bidding because the Forest [150]*150Service would not allow it to move equipment to the site to dig test holes. Plaintiff sought excess costs from the contracting officer of $18,725.40. This is the same claim set forth in Part VII of the complaint in Docket No. 201-86C although plaintiff has increased the amount of the claim to $23,482.

The third of these six claims consisted of two parts and was based on broad contentions that the specifications, items and quantities governing certain contract work were misleading. In the first part, plaintiff claimed that bid item specifications for blind drains failed to include granular back-fill material, filter cloth and six-inch pipe and that a bid item needs to be added to the contract to pay for this material. There was no indication that plaintiff assigned a dollar amount to this claim when submitted to the contracting officer. This particular claim is set forth in Part VIII of the complaint in Docket No. 201-86C and seeks $19,017 as an equitable adjustment. In the second part, plaintiff claimed that he was required by work order C to place more crushed aggregate surfacing rock than called for by the contract. Plaintiff claimed it should be paid for 154 additional cubic yards of rock at a unit price of $10.00 per yard. ($1,540). This particular claim is set forth in Part XI of the complaint in Docket No. 201-86C and seeks $1,931.00.

The fourth of these six claims is based on “troubles” the plaintiff had in finding rock to satisfy the Forest Service. The contract did not designate a rock source. This claim is set forth in Part VI, paragraphs 3 and 4 of the complaint in Docket No. 201-86C. Plaintiff did not request a specific dollar amount from the contracting officer on this claim nor did it set out a specific dollar amount for this claim in its complaint. In its complaint under Part VI, however, plaintiff seeks a combined $178,695 for the First and Fourth of the six claims presented to the contracting officer.

The fifth of these six claims concerned delays in progress payments. It does not appear that plaintiff has asserted any such claim in its complaint under the Hoodoo contract.

The sixth of these six claims was based on the contention that the Forest Service tore up long sections of road and left them in such a condition that caused damage to plaintiffs hauling equipment. There is no indication plaintiff attached a dollar amount to this claim before the contracting officer. This claim is set forth in Part IX of the complaint in Docket No. 201-86C.

On December 8, 1983, the Forest Service terminated the Hoodoo contract for default because the project had not been completed by the extended completion date of October 5, 1983. In this termination decision, plaintiff was advised of his appeal rights, particularly of his right to bring action directly in court within twelve months of the date plaintiff received the decision. There is no allegation, nor evidence, that any repro-curement costs were assessed against plaintiff as a result of this default termination. In its complaint in Docket No. 201-86C, plaintiff challenges the validity of this 1983 default termination in Part XV, paragraph 11, and Parts XVII, XVIII, and XIX (labeled in plaintiffs complaint as a “Third and Partial Alternative cause of action, and as an alternative to Plaintiffs second cause of action * * * ”).

In its complaint in Docket No. 201-86C, plaintiff pleads as a “Second and Partial Alternative to its first cause of action,” that defendant breached the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meltech Corporation, Inc.
Armed Services Board of Contract Appeals, 2025
TRG Construction Inc. v. District of Columbia Water & Sewer Authority
70 A.3d 1164 (District of Columbia Court of Appeals, 2013)
SUFI Network Services, Inc. v. United States
108 Fed. Cl. 287 (Federal Claims, 2012)
AAB Joint Venture v. United States
75 Fed. Cl. 414 (Federal Claims, 2007)
Renda Marine, Inc. v. United States
71 Fed. Cl. 782 (Federal Claims, 2006)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
Northrop Corp. v. General Motors Corp.
807 N.E.2d 70 (Indiana Court of Appeals, 2004)
Witherington Construction Corp. v. United States
45 Fed. Cl. 208 (Federal Claims, 1999)
General Motors Corp. v. Northrop Corp.
685 N.E.2d 127 (Indiana Court of Appeals, 1997)
Coastal Industries, Inc. v. United States
39 Cont. Cas. Fed. 76,722 (Federal Claims, 1994)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Reliance Insurance v. United States
38 Cont. Cas. Fed. 76,494 (Federal Claims, 1993)
Krueger v. United States
38 Cont. Cas. Fed. 76,399 (Court of Claims, 1992)
SGW, Inc. v. United States
36 Cont. Cas. Fed. 75,848 (Court of Claims, 1990)
Placeway Construction Corp. v. United States
35 Cont. Cas. Fed. 75,709 (Court of Claims, 1989)
Big Chief Drilling Co. v. United States
15 Cl. Ct. 295 (Court of Claims, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
34 Cont. Cas. Fed. 75,256, 12 Cl. Ct. 147, 1987 U.S. Claims LEXIS 57, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hho-co-v-united-states-cc-1987.