Walsky Construction Co. v. United States

31 Cont. Cas. Fed. 71,677, 3 Cl. Ct. 615, 1983 U.S. Claims LEXIS 1599
CourtUnited States Court of Claims
DecidedOctober 20, 1983
DocketNo. 672-82C
StatusPublished
Cited by13 cases

This text of 31 Cont. Cas. Fed. 71,677 (Walsky Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walsky Construction Co. v. United States, 31 Cont. Cas. Fed. 71,677, 3 Cl. Ct. 615, 1983 U.S. Claims LEXIS 1599 (cc 1983).

Opinion

OPINION

WOOD, Judge:

In this case, arising under the Contract Disputes Act of 1978, 41 U.S.C. §§ 601 et seq. (Supp. V 1981), plaintiff sues to recover a total of $58,994.03 (plus interest and attorney fees) alleged to be due pursuant to a contract between plaintiff and defendant for the construction of a T-bar ski lift at Fort Greeley, Alaska.

Defendant has moved to dismiss the complaint because of plaintiff’s failure to certify “its claim * * * in excess of $50,000.00, as required by * * * ” section 6(e)(1) of the 1978 act, 41 U.S.C. § 605(c)(1) (Supp. V 1981).1 In opposing the motion, plaintiff asserts that this action involves three separate and independent claims, each of which is for less than $50,000, and that certification is therefore not required.

For the reasons hereinafter appearing, it is concluded that plaintiff has presented to [617]*617the court, without having first certified it, one unitary claim (the “repair work” claim) for more than $50,000, and requiring certification, together with a separate and independent claim (the “as-built drawings” claim) for less than $50,000, and not requiring certification. Warchol Constr. Co., Inc. v. United States, 2 Cl.Ct. 384 (1983); Fidelity and Deposit Co. of Maryland v. United States, 2 Cl.Ct. 137 (1983); B.D. Click Co., Inc., ASBCA No. 25609, 81-2 BCA (CCH) ¶ 15,394 (1981).

I

The facts necessary to disposition of the pending motion, as they appear from plaintiff’s complaint and the exhibits attached to plaintiff’s opposition to defendant’s motion to dismiss, are as follows.

On August 20, 1979, defendant, acting through the Alaska District, Army Corps of Engineers, awarded to plaintiff a contract calling for the construction of a T-bar ski lift at the Black Rapids Training Site, Fort Greeley, Alaska, at a lump-sum price of $212,480. The contract contained a provision imposing upon plaintiff, for a period of a year following defendant’s acceptance of the contract work, “warranty obligations.”2

Plaintiff received notice to proceed September 21, 1979. By September 20, 1980, the contract work was “essentially complete.” On October 16, 1980, defendant’s resident contracting officer advised plaintiff that all “physical work is completed and recommended for acceptance,” and reminded it that the contract “provides for a warranty of construction effective until 19 September 1981.”

The contract required that plaintiff submit “as-built drawings” to defendant. Defendant withheld $4,500 of the contract price pending receipt of such drawings. The complaint alleges submission of the as-built drawings to defendant, wrongful rejection of them, resubmission of the drawings on three subsequent occasions, and a continued government refusal both to accept the drawings and to pay the balance of the contract price withheld in consequence of them.

While this controversy persisted, another, more serious, problem surfaced. In December 1980, plaintiff was informed that the T-bar ski lift was inoperative, and that under the contract warranty provision plaintiff was obligated to place “this facility back into operation immediately.”

A blow-by-blow description of the prolonged and bitter dispute that ensued is not really necessary here. It is enough to say that plaintiff alleges that the contracting officer required plaintiff to perform both what plaintiff refers to as “non-warranty repair work” between December 17, 1980, and late October 1981, and certain repair and other work under a contract modification between May and September 1981.3 The contract modification dealt with realignment and adjustment of the ski lift, but also included the as-built drawings referred to above, and an expanded operations and maintenance manual as well.4

For the “non-warranty repair work” plaintiff’s administrative claim (as amended prior to the commencement of this action) was, and its present claim is, $41,944.03; for its other “repair work,” plaintiff claimed administratively, and here claims, at least [618]*618$12,550.00. In short, the sums demanded for repair work exceeded, and exceed, $50,-000.

In passing, it should be noted that, on September 28,1981, plaintiff had submitted to defendant an invoice for $33,400, consisting of an amount allegedly “past due,” plus a “partial billing” for extra work, and a separate request (absent payment) for a contracting officer’s decision. The record also suggests that on February 1, 1982, plaintiff submitted to defendant a demand for a contracting officer’s decision.5 On March 17, 1982, defendant (which by that time had asserted a claim of more than $20,000 in reprocurement costs against plaintiff), advised it that since “the total amount in dispute exceeds $50,000.00,” certification of plaintiff’s claim was a prerequisite to its consideration by the contracting officer. Cf. General Dynamics Corporation Electric Boat Division, ASBCA No. 25919, 82-1 BCA (CCH) ¶ 15,616 (1982). In August 1982, prior to the filing of this suit, plaintiff increased its own monetary demands under the contract to a total of $58,994.03. Accordingly, whether or not defendant’s March 17,1982, advice was appropriate need not be, and is not, considered here.

II

The Contract Disputes Act of 1978 recognizes that a single government contract may well give rise to two or more entirely separate claims, and provides that, in such a situation, the contractor may pursue its rights by filing “two or more [separate] suits,” in either the same forum or in separate ones, as it may prefer. 41 U.S.C. § 609 (Supp. V 1981); see, e.g., Dravo-Groves v. United States, 231 Ct.Cl.—(Order, July 16, 1982); Warwick Construction, Inc. v. United States, 225 Ct.Cl. 567, 650 F.2d 289 (1980); E.D.S. Federal Corp. v. United States, 1 Cl.Ct. 212 (1983).

The certification provision relied upon by defendant in this case appears in conjunction with Congressional reference to a “submitted claim * * * of more than $50,-000,” and requires the contractor to make certain specified certifications with respect to “the claim * * Section 6(c)(1), 41 U.S.C. § 605(c)(1) (Supp. V 1981) (emphasis supplied). The words of the statute, the setting in which they appear, and the decisions interpreting and applying them make it plain that not every group of claims having an aggregate value of more than $50,000 need be certified to be a valid “claim” under section 6(c)(1). Where multiple claims, each of which is for less than $50,000, exist, the claims must be carefully examined to determine whether they are separate and individual claims not requiring certification, or merely portions of a single, unified, “claim” which, to be a valid claim, must be certified if amounting to more than $50,000 in the aggregate. Warchol Constr. Co., Inc. v. United States, supra, 2 Cl.Ct. at 389; B.D. Click Co., Inc., supra, 81-2 BCA (CCH) at 76,263-64.

Where there are several

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fidelity & Deposit Company of Maryland
Armed Services Board of Contract Appeals, 2023
Reliance Insurance v. United States
38 Cont. Cas. Fed. 76,494 (Federal Claims, 1993)
AAI Corp. v. United States
37 Cont. Cas. Fed. 76,038 (Court of Claims, 1991)
Placeway Construction Corporation v. The United States
920 F.2d 903 (Federal Circuit, 1990)
H. Richard Westerhold v. The United States
899 F.2d 1227 (Federal Circuit, 1990)
Spirit Leveling Contractors v. United States
36 Cont. Cas. Fed. 75,770 (Court of Claims, 1989)
Placeway Construction Corp. v. United States
35 Cont. Cas. Fed. 75,709 (Court of Claims, 1989)
City of El Centro v. United States
35 Cont. Cas. Fed. 75,724 (Court of Claims, 1989)
Acousti Engineering Co. v. United States
35 Cont. Cas. Fed. 75,580 (Court of Claims, 1988)
Bromley Contracting Co. v. United States
34 Cont. Cas. Fed. 75,515 (Court of Claims, 1988)
H.H.O. Co. v. United States
34 Cont. Cas. Fed. 75,256 (Court of Claims, 1987)
LDG Timber Enterprises, Inc. v. United States
32 Cont. Cas. Fed. 73,681 (Court of Claims, 1985)
Black Star Security, Inc. v. United States
32 Cont. Cas. Fed. 72,431 (Court of Claims, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
31 Cont. Cas. Fed. 71,677, 3 Cl. Ct. 615, 1983 U.S. Claims LEXIS 1599, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walsky-construction-co-v-united-states-cc-1983.