AAI Corp. v. United States

37 Cont. Cas. Fed. 76,038, 22 Cl. Ct. 541, 1991 U.S. Claims LEXIS 51, 1991 WL 21706
CourtUnited States Court of Claims
DecidedFebruary 22, 1991
DocketNo. 253-89C
StatusPublished
Cited by14 cases

This text of 37 Cont. Cas. Fed. 76,038 (AAI Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AAI Corp. v. United States, 37 Cont. Cas. Fed. 76,038, 22 Cl. Ct. 541, 1991 U.S. Claims LEXIS 51, 1991 WL 21706 (cc 1991).

Opinion

OPINION

MARGOLIS, Judge.

This government contracts case is before the court on the defendant’s motion to dismiss the plaintiff’s complaint for lack of subject matter jurisdiction, pursuant to RUSCC 12(b)(1) and (h)(3). The plaintiff seeks to recover its share of acquisition savings resulting from the defendant’s alleged acceptance of a Value Engineering Change Proposal (“VECP”) submitted in connection with a contract between the parties. The defendant argues that this court lacks jurisdiction to adjudicate the plaintiff's claim because it was not considered in its present form by the defendant’s contracting officer. The defendant also contends that this court lacks jurisdiction over what the defendant contends is a request for declaratory relief. After careful review of the record and hearing oral argument, this court grants the defendant’s motion to dismiss with respect to the plaintiff’s claim for future contract savings not yet realized by the defendant, but denies the defendant’s motion to dismiss with respect to all other issues.

FACTS

The plaintiff, AAI Corporation (“AAI”), is a Maryland corporation engaged in research and development, often on behalf of various defense agencies of the defendant, the United States. The parties executed a fixed price, incentive research and development contract, Contract No. F08635-84-C[542]*5420079, on October 31, 1983. The defendant contracted with AAI to develop and fabricate a Timer, Actuator, Fin and Fuse assembly (“TAFF” or “timer”) to be used on non-nuclear bombs by the Air Force Strategic Air Command.

The contract was modified numerous times. On November 18, 1985, modification number P00009 added two options to the contract. Option I was for Low Rate Initial Production (LRIP) of a maximum of 5000 Units. Option II was for the production of 18,000-20,000 units. Modification P00009 also amended the original contract to incorporate certain Federal Acquisition Regulation (“FAR”) clauses, replacing certain Defense Acquisition Regulation (“DAR”) clauses. FAR provision 52.248-1, 48 C.F.R. § 52.248-1 (1984), entitled “Value Engineering,” was incorporated into the contract. The Value Engineering Clause in this provision states that “[t]he Contractor is encouraged to develop, prepare and submit value engineering change proposals (“VECP’s”) voluntarily. The Contractor shall share in any net acquisition savings realized from accepted VECP’s, in accordance with the incentive sharing rates in paragraph (f) below.”1

On January 30, 1987, modification number P00011 established prices and quantities for the two options added by modification P00009. Option I was priced at $2,219,624 for a quantity of 1500 units and related items, and Option II was priced at $4,582,660 for a quantity of 14,000 units and related items. Modification P00011 also exercised Option I, for 1500 units and related items.

AAI claims that, in accordance with the Value Engineering Clause, it aggressively undertook a redesign effort to reduce the cost of fabricating the timer to be produced under the contract, separate and apart from the work required under the contract. During a design review with the government, on August 4-5, 1987, AAI submitted, on August 5, what AAI contends was a preliminary VECP. AAI alleges that the design presented by AAI at the design review incorporated all changes required by the contract’s statement of work and all VECP changes. By letter of August 12, 1987, defendant “authorized [AAI] to proceed with the fabrication of the preproduction sample in accordance with the design presented at the design review.” By letter dated August 26, 1987, the government disapproved the preliminary VECP, indicating that these changes were part of the existing contract. AAI, however, contends that the authorization to proceed letter constituted acceptance, or constructive acceptance, of the VECP because the VECP changes were incorporated in the design presented at the design review.

AAI submitted a formal VECP, dated October 14, 1987, to the government on October 19, 1987. AAI asserted that the net unit cost savings would be $45.43 computed for a forecasted production run of 14,000 units. Under the contract’s Value Engineering Clause, FAR 52.248-l(b), “net acquisition savings” includes instant contract savings,2 concurrent contract savings,3 and future contract savings.4 The [543]*543plaintiff claimed that it was entitled to a share of the acquisition savings. With regard to the Low Rate Initial Production of 1500 units resulting from the exercise of Option I by modification P00011, AAI stated that “there [were] no net instant contract savings anticipated due to the rather extensive contractor implementation costs being experienced.”5 Plaintiffs Exhibit 10, page 70, ¶ 5.5.1.

Although the final implementation costs cannot be determined as yet, the current delta has already offset a good portion of the total unit cost savings available. The program plan is to complete the LRIP effort with the current funding, by achieving a 100% offset between the instant contract savings and the implementation costs, which would allow a no-cost implementation of the VECP under the instant contract.

Id. In other words, at this point in time, AAI anticipated that implementation costs would be offset by instant contract savings, leaving no instant contract savings or, more properly stated, no negative instant contract savings.6

The Air Force responded to the VECP with a letter dated October 28, 1987 disapproving the VECP on the ground that the design changes resulted from work required by the original contract, and therefore there was no VECP as defined by the FAR.

AAI then submitted a claim to the Air Force contracting officer on December 18, 1987 asserting that (1) the VECP complies with the FAR definition of a VECP; (2) the design changes included in the VECP were not developed as a result of contractual requirements; and (3) AAI is entitled to share in the savings resulting from the VECP. The Air Force asked for clarification as to the amount of the claim on January 12, 1988. AAI's response of January 14, 1988, reaffirmed that “there are no instant contract savings or negative instant contract savings anticipated on the instant contract.” In other words, the plaintiff anticipated that implementation costs would be offset by instant contract savings, leaving no instant contract savings or negative instant contract savings. AAI also repeated its claim to a portion of savings related to hypothetical future contracts.

Option II was awarded, by modification P00017 effective September 15, 1988, for the production of 14,000 units. The Air Force contracting officer ultimately denied the VECP claim on June 30, 1988. The contracting officer stated that “the Government considers the design to be resultant from the funded redesign effort to correct a deficiency of the TAFF” and that the “Air Force never at any time accepted or recognized the alleged VECP from AAI.”

AAI then filed its original complaint in this court, dated May 5,1989, appealing the decision of the contracting officer and seeking its share of acquisition savings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Al-Juthoor Contracting Co. v. United States
129 Fed. Cl. 599 (Federal Claims, 2016)
North Star Alaska Housing Corp. v. United States
76 Fed. Cl. 158 (Federal Claims, 2007)
Pueblo of Zuni v. United States
467 F. Supp. 2d 1099 (D. New Mexico, 2006)
Modeer v. United States
68 Fed. Cl. 131 (Federal Claims, 2005)
Hawkins & Powers Aviation, Inc. v. United States
46 Fed. Cl. 238 (Federal Claims, 2000)
Croman Corp. v. United States
44 Fed. Cl. 796 (Federal Claims, 1999)
Metric Constructors, Inc. v. United States
44 Fed. Cl. 513 (Federal Claims, 1999)
Johnson Controls World Services, Inc. v. United States
43 Cont. Cas. Fed. 77,468 (Federal Claims, 1999)
Robin Industries, Inc. v. United States
29 Fed. Cl. 122 (Federal Claims, 1993)
John Massman Contracting Co. v. United States
38 Cont. Cas. Fed. 76,515 (Federal Claims, 1993)
Chinook Research Laboratories, Inc. v. United States
22 Cl. Ct. 853 (Court of Claims, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
37 Cont. Cas. Fed. 76,038, 22 Cl. Ct. 541, 1991 U.S. Claims LEXIS 51, 1991 WL 21706, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aai-corp-v-united-states-cc-1991.