Alan J. Haynes Construction Systems, Inc. v. United States

33 Cont. Cas. Fed. 74,506, 10 Cl. Ct. 526, 1986 U.S. Claims LEXIS 830
CourtUnited States Court of Claims
DecidedJuly 25, 1986
DocketNo. 381-85C
StatusPublished
Cited by13 cases

This text of 33 Cont. Cas. Fed. 74,506 (Alan J. Haynes Construction Systems, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alan J. Haynes Construction Systems, Inc. v. United States, 33 Cont. Cas. Fed. 74,506, 10 Cl. Ct. 526, 1986 U.S. Claims LEXIS 830 (cc 1986).

Opinion

OPINION ON DEFENDANT’S MOTION TO DISMISS, OR IN THE ALTERNATIVE, FOR SUMMARY JUDGMENT

PHILIP R. MILLER, Judge:

This suit arises from a contract awarded September 21, 1981, to plaintiff, Alan J. Haynes Construction Systems, Inc., by the Department of the Air Force for the painting of three jet fuel storage tanks at Davis-Monthan Air Force Base in Arizona for the fixed price of $63,965. Plaintiff seeks a declaration that it is not obligated under the warranty clause of its contract to repaint these tanks, because the problems requiring such effort are not due to defective workmanship by plaintiff, but rather are the result of defective contract specifications on the part of defendant. Defendant moves for dismissal on the ground that this court lacks jurisdiction because plaintiff seeks only declaratory relief, or alternatively, because plaintiff has not submitted any claim to the contracting officer, as required by the Contract Disputes Act (CDA), 41 U.S.C. § 605(a).

Statement of the Case

By June 15, 1982, plaintiff had completed painting the three storage tanks as required under its contract with the Air Force. The Air Force accepted the work and made final payment to plaintiff.

By letter dated October 18, 1982, the Air Force requested that the tanks be repaired to correct areas where the undercoat was “bleeding through” the top coat. The request was made pursuant to the contract warranty provision, which states:

[T]he Contractor warrants that work performed under this contract conforms to the contract requirements and is free of any defect of equipment, material or design furnished, or workmanship performed by the Contractor * * *. Such [527]*527warranty shall continue for a period of one year from the date of final acceptance of the work * * *. Under this warranty, the Contractor shall remedy at his own expense any such failure to conform or any such defect. * * *

Plaintiff responded in writing that it would make the necessary repairs.

On March 14, 1983, the contracting officer notified plaintiff that the paint was again “bleeding through” and that plaintiff was still obligated by its warranty to make the necessary repairs. On June 3, 1983, the contracting officer notified plaintiff that its repairs were unsatisfactory, and demanded that plaintiff reperform.

On June 23, 1983, plaintiff wrote to the contracting officer that the “problems you are experiencing are design problems” due to defective government contract specifications. Plaintiff asserted that it was not responsible under the warranty clause for defective government design, and declined to repaint the tanks. The contracting officer disagreed, and by letter dated October 14, 1983, directed plaintiff to repaint the tanks. Plaintiff did not respond, and the contracting officer reissued this direction on March 20, 1984. By letter dated March 28, 1984, plaintiff reiterated that it was not liable and stated: “[W]e do not intend to repaint the tanks on this project.”

On May 23, 1984, the contracting officer issued a written final decision rejecting the contractor’s denial of liability and assertions of defective government specifications, and demanded that the tanks be repainted by plaintiff.

Plaintiff filed suit here on June 26, 1985.

Contentions of the Parties

Defendant contends that plaintiff’s suit must be dismissed because the Contract Disputes Act, 41 U.S.C. § 609(a), does not confer authority on the Claims Court to render judgment on a claim seeking only declaratory relief.

Alternatively, defendant contends that if such jurisdiction exists, plaintiff should not be permitted to circumvent the “changes” clause of its contract. According to defendant, if repainting is not required under the warranty, as plaintiff asserts, then the direction by the contracting officer to repaint the tanks is a constructive change, which plaintiff may not challenge by suit. Instead, plaintiff must perform the work and seek equitable adjustment under its contract remedies. Until it submits such a claim to the contracting officer, defendant contends that plaintiff’s claim is premature. Id. § 605(a). Defendant asserts that plaintiff’s letters do not suffice as a claim under the CD A.

Plaintiff opposes dismissal. It argues that the jurisdiction of this court is clear and unambiguous under 28 U.S.C. § 1491(a)(2):

* * * The Claims Court shall have jurisdiction to render judgment upon any claim by or against, or any dispute with, a contractor arising under section 10(a)(1) of the Contract Disputes Act of 1978.

It further argues that it seeks review of a government claim brought against it, i.e., the final decision by the contracting officer dated May 23, 1984 that plaintiff is obligated to repaint the tanks under its warranty clause. As a government claim, there would be no requirement for plaintiff to submit a claim. 41 U.S.C. § 605(a). Alternatively, it argues that even if cast as a claim against the government, plaintiff has submitted a claim sufficient under § 605(a) and received a final decision upon which suit may be brought.

Discussion

The court concludes that it lacks jurisdiction over a claim seeking only declaratory relief, and, therefore, finds it unnecessary to determine whether the basis of this suit is a claim by the government against plaintiff, or vice versa, or the sufficiency of plaintiff’s claim. Plaintiff seeks no money judgment but asks only relief from the decision by the contracting officer that it is obligated to repaint the tanks under its warranty. Nor does plaintiff seek relief from a money claim against it. Defendant has neither declared plaintiff in [528]*528breach and assessed damages, nor sought reimbursement for the cost of having the tanks painted by someone other than plaintiff.

Plaintiff misconstrues 28 U.S.C. § 1491(a)(2). This provision is the codification of the Contract Disputes Act’s “all disputes clause,” by which Congress ended, for purposes of jurisdiction of the courts and the contract boards, the prior distinction between “claims” and “disputes” arising under or relating to the contract. See H.R.Rep. 1556, 95th Cong., 2d Sess. 15-18 (1978). Although read literally this language supports jurisdiction over a suit seeking declaratory relief, there is nothing in the legislative history of this clause to indicate that it was meant to confer equitable jurisdiction on the Claims Court. To the contrary, the legislative history of the Contract Disputes Act compels the conclusion that, except in narrow circumstances, Congress did not intend to expand this court’s traditional jurisdiction, limited to money claims (United States v. King, 395 U.S. 1, 89 S.Ct. 1501, 23 L.Ed.2d 52 (1969)), into equitable and declaratory relief. Accord Williams International Corp. v. United States, 7 Cl.Ct. 726, 728-31 (1985).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Todd Construction, L.P. v. United States
85 Fed. Cl. 34 (Federal Claims, 2008)
Boeing Co. v. United States
38 Cont. Cas. Fed. 76,332 (Court of Claims, 1992)
AAI Corp. v. United States
37 Cont. Cas. Fed. 76,038 (Court of Claims, 1991)
Aviation v. United States
36 Cont. Cas. Fed. 75,963 (Court of Claims, 1990)
Continental Heller Construction v. United States
36 Cont. Cas. Fed. 75,944 (Court of Claims, 1990)
Overall Roofing & Construction Inc. v. United States
36 Cont. Cas. Fed. 75,849 (Court of Claims, 1990)
Ward-Schmid Co. v. United States
45 Cont. Cas. Fed. 75,748 (Court of Claims, 1989)
Placeway Construction Corp. v. United States
35 Cont. Cas. Fed. 75,709 (Court of Claims, 1989)
Claude E. Atkins Enterprises, Inc. v. United States
35 Cont. Cas. Fed. 75,582 (Court of Claims, 1988)
Mega Construction Co. v. United States
34 Cont. Cas. Fed. 75,445 (Court of Claims, 1988)
Ralcon, Inc. v. United States
34 Cont. Cas. Fed. 75,377 (Court of Claims, 1987)
St. Johns Oil Co. v. United States
33 Cont. Cas. Fed. 75,182 (Court of Claims, 1987)
Industrial Coatings, Inc. v. United States
33 Cont. Cas. Fed. 74,722 (Court of Claims, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
33 Cont. Cas. Fed. 74,506, 10 Cl. Ct. 526, 1986 U.S. Claims LEXIS 830, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alan-j-haynes-construction-systems-inc-v-united-states-cc-1986.