Aviation v. United States

36 Cont. Cas. Fed. 75,963, 21 Cl. Ct. 782, 1990 U.S. Claims LEXIS 424, 1990 WL 172992
United States Court of Claims·Decided November 8, 1990·No. No. 90-430C·Published·Cited by 3 cases

Opinion

ORDER

MOODY R. TIDWELL, III, Judge:

On July 24, 1990, this court issued an Order allowing defendant’s motion to dismiss on the grounds that the court lacked jurisdiction to adjudicate the claim as being filed out of time. 20 Cl.Ct. 780. The court dismissed the complaint without prejudice. The facts are set forth in the July 24 Order, and will not be repeated here except as necessary.

FACTS

On July 25, 1990, defendant filed a motion for reconsideration requesting that the court vacate the judgement and dismiss the case with prejudice. On August 23, 1990, defendant filed a second motion for leave to cite supplemental authority. That motion was allowed. In it defendant suggested that, inasmuch as the court lacked jurisdiction to hear the case, it would be inappropriate for the “court to reach the merits of the claim and dismiss ‘with prejudice.’ ” 1 [783] On August 6, 1990, plaintiff filed its own motion for reconsideration asking the court to vacate its order of dismissal and direct the contracting officer to issue a final decision addressing plaintiff's claim for termination for the convenience of the government.

This case stems from plaintiff’s contract with the Department of the Army executed on June 27, 1987, to produce military gear with a production run of two years, and an option to produce an additional quantity. On August 8, 1988, the Army unilaterally cancelled the second production year. Thereafter, because plaintiff failed to meet its delivery schedule on one item due in the first year of the contract, the Army, on May 5,1989, informed plaintiff by telegram that the late item was terminated for default, effective that date.2 Plaintiff received the telegram on May 8, 1989. By certified letter dated May 15, 1989, the contracting officer partially terminated the contract — for the one late item — as of the May 5, 1989 telegram. On May 19, 1989, plaintiff received the May 15 certified letter that “confirmed” the telegraphed termination notice. The May 15 letter contained the mandatory Federal Acquisition Regulations (FAR) language informing plaintiff of the reason for the termination for default, and plaintiff’s appeal rights. The FAR requiring this language, which has the full force and effect of law, Longview Crop Ins. Agency v. United States, 20 Cl.Ct. 564, 571 (1990) (citations omitted), states that the period for appeal runs from the day the contractor receives the letter of termination. FAR appeal rights give a plaintiff ninety days to appeal the termination for default to the Armed Services Board of Contract Appeals (ASBCA), and one year to appeal to this court. The May 15 letter was somewhat unclear regarding the exact date on which the period for appeal began to run.3

Plaintiff did not appeal the termination for default to the ASBCA, but on May 16, 1990, did submit a claim to the contracting officer requesting reimbursement of costs expended in attempting to comply with the portion of the contract defendant had terminated for default. Plaintiff further challenged the validity of the default termination, requesting that it be converted into a termination for the convenience of the government.4 Two days later, on May 18, 1990, plaintiff filed its action here seeking de novo consideration of the termination.

DISCUSSION

The court was, and remains of the opinion that it cannot consider the May 5, 1989 telegram a proper notice of termination because it did not contain the language required by the Contract Disputes Act, 41 U.S.C. § 601, et. seq., and FAR 52.249-8, fully advising plaintiff of its appeal rights. Plaintiff is correct in its argument on reconsideration that a final decision of the contracting officer which does not state the appeal rights is defective, and does not start the limitations period for appeal or review. Pathman Constr. Co., Inc. v. United States, 817 F.2d 1573, 1579 [784] (Fed.Cir.1987). Neither would such a defective final decision start the clock running on the time for submitting to the contracting officer a termination for convenience claim. The effective date of the termination for default was May 19, 1989, the date plaintiff received the certified letter. See Handel v. United States, 16 Cl.Ct. 70, 72 (1988); 41 U.S.C. § 609(a)(3) (1982). Plaintiff timely filed suit on May 18, 1990, one day prior to the running of the statute of limitations. However, the matter does not end there. In its complaint, plaintiff characterized its claim as one for “conversion of a termination for default to a termination for convenience,” for “termination for convenience costs,” or, in the alternative, for an equal amount for expenses incurred notwithstanding the termination for default.

Free access — add to your briefcase to read the full text and ask questions with AI

Aviation v. United States, 36 Cont. Cas. Fed. 75,963, 21 Cl. Ct. 782, 1990 U.S. Claims LEXIS 424, 1990 WL 172992 (cc 1990).

36 Cont. Cas. Fed. 75,963 (Aviation v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Scott Aviation v. The United States
953 F.2d 1377 (Federal Circuit, 1992)
Scott Aviation v. United States
37 Cont. Cas. Fed. 76,139 (Court of Claims, 1991)
Government Systems Advisors, Inc. v. United States
25 Cl. Ct. 554 (Court of Claims, 1990)