Pathman Construction Company, Inc. v. The United States

817 F.2d 1573, 34 Cont. Cas. Fed. 75,250, 1987 U.S. App. LEXIS 262
CourtCourt of Appeals for the Federal Circuit
DecidedMay 4, 1987
DocketAppeal 86-1537
StatusPublished
Cited by53 cases

This text of 817 F.2d 1573 (Pathman Construction Company, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pathman Construction Company, Inc. v. The United States, 817 F.2d 1573, 34 Cont. Cas. Fed. 75,250, 1987 U.S. App. LEXIS 262 (Fed. Cir. 1987).

Opinion

FRIEDMAN, Circuit Judge.

The principal issue in this appeal from the United States Claims Court is whether, under the Contract Disputes Act of 1978, Pub.L. No. 95-563, 92 Stat. 2383 (1978) (codified as amended at 41 U.S.C. §§ 601-609 (1982 & Supp.1985)) (Disputes Act), the twelve-month period within which a contractor must file in that court a suit challenging a decision of a contracting officer begins to run when the claim submitted to the contracting officer is “deemed denied” because the contracting officer has not decided the claim within the period the Disputes Act specified. The Claims Court held that the limitations period began to run when the claim was deemed denied and dismissed the suit as untimely because it had not been filed within twelve months of such “deemed denial.” We hold, however, that the limitations period does not begin to run until the contracting officer renders an actual written decision on the contractor’s claim, and we therefore reverse the Claims Court.

I

A. The appellant, Pathman Construction Company, Inc. (Pathman), entered into a contract with the United States General Services Administration (Administration) to install interior furnishings in a federal office building. The project was substantially completed on September 23, 1975, although various finishing items and work under change orders continued into 1976.

*1575 On September 28, 1976, Pathman submitted a claim for equitable adjustment of $428,608.17, seeking delay-related costs for itself and its two principal subcontractors. Pathman subsequently amended its claim to $522,907.58. Pathman and representatives of the Administration had numerous meetings in an attempt to settle the claims. Although settlement offers were made and discussed, the parties failed to reach agreement.

On May 10, 1978, the contracting officer informed Pathman that the government acknowledged Pathman’s entitlement to an equitable adjustment and offered $202,-000.00 in settlement. Pathman rejected the offer. The contracting officer then “requested an audit of [Pathman’s] records, relative to [the] contract, for the purpose of determining the extent of ... entitlement to extend overhead costs,” and told Path-man that no further action would be taken on its claim until after the auditors had completed review of Pathman’s records and submitted their recommendations. The audit was conducted during May, June, and July, and the audit report was issued on August 17, 1978.

Despite repeated requests by Pathman for a decision on its claim, no decision was forthcoming. On February 16, 1981, Path-man submitted a written request to the contracting officer for a final decision. Pathman expressed its concern that the decision of the contracting officer was “long overdue” and its hope that its claim be handled as “expeditiously” as possible. Again, no decision was rendered.

On May 6, 1983, Pathman submitted a second written request for the contracting officer’s decision. The request included the certification that is required for claims in excess of $50,000. See 41 U.S.C. § 605(c)(1) (1982). Pathman thereafter made additional written requests that the contracting officer render a decision.

To date, however, no decision has been rendered on Pathman’s claim.

B. On March 11, 1985, Pathman filed suit in the Claims Court seeking de novo determination of the claim pursuant to section 10(a) of the Disputes Act. See Pub.L. No. 95-563, § 10(a), 92 Stat. 2383, 2388 (1978) (codified at 41 U.S.C. § 609). That section requires that such an action be filed “within twelve months from the date of the receipt by the contractor of the decision of the contracting officer concerning the claim____” The Act further provides that the failure of the contracting officer “to issue a decision on a contract claim within the period required [under the Act] will be deemed to be a decision by the contracting officer denying the claim and will authorize the commencement of the appeal or suit on the claim as otherwise provided in this Act.” Pub.L. No. 95-563, § 6(c)(5), 92 Stat. 2383, 2385 (1978) (codified at 41 U.S.C. § 605).

On the government’s motion, the Claims Court dismissed the suit as untimely. The court noted that Pathman had submitted its certified claim with request for final decision to the contracting officer on May 6, 1983. The court held that Pathman’s claim had been “deemed denied” sixty days thereafter because at that time the contracting officer had neither (1) rendered a decision on the claim, nor (2) set a definite future date when such decision would be rendered, as the Disputes Act required the contracting officer to do. According to the court, this “deemed denied” decision triggered the running of the twelve-month limitations period for filing suit in the Claims Court. Since Pathman filed suit on March 11,1985, more than twelve months after its claim was deemed denied on July 5, 1983, the court concluded that Pathman’s suit was untimely. Pathman Constr. Co., Inc. v. United States, 10 Cl.Ct. 142 (1986).

II

The decision of the Claims Court that the twelve-month limitation period in the Disputes Act for filing suit in that court begins to run when the contract claim is “deemed denied” stands in juristic solitude. Five other decisions of that court, both before and after the decision in this case, have reached a contrary result. Malissa Co., Inc. v. United States, 11 Cl.Ct. 389, 391 (1986); LaCoste v. United States, 9 Cl.Ct. 313, 315 (1986); Turner Constr. Co. *1576 v. United States, 9 Cl.Ct. 214, 215-16 (1985); Vemo Co. v. United States, 9 Cl.Ct. 217, 220-22 (1985); G & H Mach. Co. v. United States, 7 Cl.Ct. 199, 203 (1985). Three different boards of contract appeals also have come out the other way. Guy F. Atkinson Co., No. 4693 (ENG. BCA Feb. 19,1987); Roebbelen Eng’g, Inc., 47 F.C.R. 108 (DOT BCA 1986); Blake Constr. Co., Inc., 87-1 BCA ¶ 19523 (VABCA 1986).

We conclude that the language of the Disputes Act, its legislative history, and its basic purpose demonstrate that, contrary to the conclusion of the Claims Court in this case, the twelve-month limitations period for bringing suit in the Claims Court does not begin to run until the contracting officer has issued his decision on the contractor’s claim. Accordingly, Path-man’s suit was timely filed, and the Claims Court erred in dismissing it.

A. The pertinent provisions of the Disputes Act are sections 6(c) and 10(a)(1), (3). The former provides:

(c)(1) A contracting officer shall issue a decision on any submitted claim of $50,-000 or less within sixty days from his receipt of a written request from the contractor that a decision be rendered within that period.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Racer Machinery International
Armed Services Board of Contract Appeals, 2026
W. J. v. Hhs
Federal Circuit, 2024
JAAAT Technical Services, LLC
Armed Services Board of Contract Appeals, 2021
Access Personnel Services, Inc.
Armed Services Board of Contract Appeals, 2016
FRASSON LODOVICO S.r.l.
Armed Services Board of Contract Appeals, 2014
Diversified Maintenance Systems, Inc. v. United States
110 Fed. Cl. 612 (Federal Claims, 2013)
The Minesen Co. v. McHugh
671 F.3d 1332 (Federal Circuit, 2012)
Newtech Research Systems LLC v. United States
99 Fed. Cl. 193 (Federal Claims, 2011)
Environmental Safety Consultants, Inc. v. United States
95 Fed. Cl. 77 (Federal Claims, 2010)
System Planning Corp. v. United States
95 Fed. Cl. 1 (Federal Claims, 2010)
Nwogu v. United States
94 Fed. Cl. 637 (Federal Claims, 2010)
Paradigm Learning, Inc. v. United States
93 Fed. Cl. 465 (Federal Claims, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
817 F.2d 1573, 34 Cont. Cas. Fed. 75,250, 1987 U.S. App. LEXIS 262, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pathman-construction-company-inc-v-the-united-states-cafc-1987.