Uniglobe General Trading & Contracting Co. v. United States

107 Fed. Cl. 423, 2012 U.S. Claims LEXIS 1181, 2012 WL 4467230
CourtUnited States Court of Federal Claims
DecidedSeptember 27, 2012
DocketNo. 10-204C
StatusPublished
Cited by3 cases

This text of 107 Fed. Cl. 423 (Uniglobe General Trading & Contracting Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Uniglobe General Trading & Contracting Co. v. United States, 107 Fed. Cl. 423, 2012 U.S. Claims LEXIS 1181, 2012 WL 4467230 (uscfc 2012).

Opinion

OPINION

BUSH, Judge.

Now pending before the court is defendant’s motion for partial dismissal, which has been fully briefed and is ripe for a decision by the court. Because the court concludes that it does not have subject matter jurisdiction over one of the three claims set forth in the complaint, defendant’s motion to dismiss that claim pursuant to Rule 12(b)(1) of the Rules of the United States Court of Federal Claims (RCFC) is granted.

BACKGROUND1

In this case, plaintiff seeks damages stemming from the government’s alleged breach [425]*425of three separate contracts for the lease of vehicles in Kuwait. Defendant has moved to dismiss one count of the complaint on the grounds that the claim was not submitted to the contracting officer within six years of the date on which it first accrued, and that the instant suit was not filed in this court within twelve months of the contracting officer’s final decision on the claim. For those reasons, defendant asserts that the claim is untimely and must therefore be dismissed pursuant to RCFC 12(b)(1) for lack of subject matter jurisdiction.

1. Factual History

Uniglobe General Trading and Contracting Company, W.L.L. (Uniglobe) is a Kuwaiti corporation with its principal place of business in Kuwait. In 2003, Uniglobe entered into three contracts with the United States Department of the Army (Army), under which Uniglobe agreed to lease various types of vehicles to the Army to be used in support of Operation Iraqi Freedom. Under those contracts, the Army leased from Uniglobe: (1) a number of Chevy Suburbans under Contract DABM06-03-P-0363 (the 363 contract); (2) several trucks under Contract DABM06-03-P-0432 (the 432 contract); and (3) five Caterpillar construction vehicles (Caterpillars) under Contract DABM06-03-P-0442 (the 442 contract). Because only the 442 contract is at issue in defendant’s pending motion to dismiss, the court will limit its discussion of the facts in this opinion to those relevant to that contract.

The 442 contract provided that the Army would lease five Caterpillars from Uniglobe for a period of six months. Under the contract, the leasing fees for the vehicles were determined in accordance with monthly rates, which were to accrue from the beginning of the contract or the delivery of the vehicles, and would continue until the expiration of the contract term or the termination of the contract. The contract further provided that it would be subject to the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (2006) (CDA), and that the parties’ failure to reach an agreement with respect to any claim under the contract was to be resolved in accordance with section 52.233-1 of the Federal Acquisition Regulation (FAR), 48 C.F.R. § 52.233-1 (2011).2

In accordance with the 442 contract, Uni-globe delivered five Caterpillars to an Army encampment in Kuwait on April 1, 2003. On April 10, 2003, the Army contacted Uniglobe to discuss the condition of.four of those vehicles. In response to the Army’s concerns, Uniglobe delivered four replacement Caterpillars to the encampment the same day and removed two of the original vehicles for maintenance, leaving the Army with a total of seven Caterpillars at the encampment. The next day, Uniglobe personnel attempted to retrieve the two Caterpillars still in need of repairs, but they were denied entry to the site. Uniglobe made repeated attempts to remove those vehicles, but the Army would not allow Uniglobe’s employees to enter the installation.

In May 2003, the Army informed Uniglobe that it was cancelling the 442 contract. Uni-globe sent field drivers to the Army encampment on May 25, 2003 to recover the seven Caterpillars still in the Army’s possession, but two of those vehicles could not be located at that time. The two missing vehicles were subsequently recovered from Camp Arifjan and Camp Virginia in Kuwait on September 9, 2003 and October 29, 2003, respectively. The Caterpillar discovered at Camp Virginia was severely damaged, and its removal from that location required the use of salvage equipment.3

[426]*426On March 21, 2004, Uniglobe submitted a claim to the contracting officer regarding the 442 contract. See PL’s Resp. Ex. A at 2. In its claim, Uniglobe requested payment in the amount of KWD 24,282.590, which represented the cost of repairing the disabled vehicle recovered from Camp Virginia.4 Id. It does not appear that the March 21, 2004 claim sought damages for the unpaid leasing fees for the two Caterpillars retained by the Army outside the contractual period of performance.5

Eighteen months later, on September 26, 2005, Major Rosiher Sibaja of the Army’s contracting command e-mailed his final decision on the March 2004 claim to a Uniglobe employee named Dina.6 Id. Ex. A at 1. The final determination, which was dated August 30, 2005, stated that the amount requested in Uniglobe’s claim was unreasonable, and that Uniglobe was entitled to a payment of no more than KWD 2880 because the Army had overpaid Uniglobe for the lease of the Caterpillars. Id. Ex. A at 2-3. Major Sibaja’s transmittal e-mail identified the document as the contracting officer’s final decision and asked that if Uniglobe was “satisfied with the determination, let me know by email, or by writing so on the document and faxing/emailing it back to me.” Id. Ex. A at 1. In the event that Uniglobe was dissatisfied with the Army’s determination, the final decision stated that Uniglobe could challenge that decision in this court within twelve months of its receipt of the final determination. Id. Ex. A at 3.

On October 3, 2005, Dr. lesa M. Jasem, Uniglobe’s chief executive officer, provided Major Sibaja with several invoices and other documents concerning the 442 contract. See id. Ex. B. A few weeks later, on October 23, 2005, Major Sibaja e-mailed a revised version of the final determination to Dina at Uni-globe. Id. Ex. C at 1. In his revised determination, which was also dated August 30, 2005, Major Sibaja increased the reasonable cost of the damaged Caterpillar from KWD 11,200 to KWD 14,000. Id. Ex. C at 2. As a result of that change, the revised determination concluded that Uniglobe was entitled to a total payment in the amount of KWD 5680. Id. Like the first version, the revised determination stated that it was the final decision of the contracting officer, and noted that any suit challenging that decision in this court had to be filed within twelve months of Uni-globe’s receipt of the decision. Id. Ex. C at 3. In his transmittal e-mail, Major Sibaja asked Dina to confirm her receipt of the decision and to indicate via e-mail or facsimile whether Uniglobe concurred with the decision. Id. Ex. C at 1.

On November 10, 2005, Uniglobe e-mailed a signed copy of the October 23, 2005 revised determination to Lieutenant Colonel (LTC) Raymond Strother, Major Sibaja’s replacement at the Army contracting command. See Pl.’s Resp. Ex. F at 1. In her e-mail to LTC Strother, Dina stated that she had already made a number of unsuccessful attempts to transmit the signed final determination via facsimile. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Al-Juthoor Contracting Co. v. United States
129 Fed. Cl. 599 (Federal Claims, 2016)
Diversified Maintenance Systems, Inc. v. United States
110 Fed. Cl. 612 (Federal Claims, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
107 Fed. Cl. 423, 2012 U.S. Claims LEXIS 1181, 2012 WL 4467230, Counsel Stack Legal Research, https://law.counselstack.com/opinion/uniglobe-general-trading-contracting-co-v-united-states-uscfc-2012.