LaCoste v. United States

33 Cont. Cas. Fed. 74,201, 9 Cl. Ct. 313, 1986 U.S. Claims LEXIS 921
CourtUnited States Court of Claims
DecidedJanuary 8, 1986
DocketNo. 233-85C
StatusPublished
Cited by16 cases

This text of 33 Cont. Cas. Fed. 74,201 (LaCoste v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LaCoste v. United States, 33 Cont. Cas. Fed. 74,201, 9 Cl. Ct. 313, 1986 U.S. Claims LEXIS 921 (cc 1986).

Opinion

OPINION

NETTESHEIM, Judge.

This case comes before the court on defendant’s motion for summary judgment. Plaintiff has opposed.1

FACTS

The parties do not dispute the following facts. Plaintiff Jack LaCoste (“plaintiff”) seeks pursuant to the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (1982) (the “CDA”), additional compensation in the amount of $30,000 for extra costs incurred under a contract with the United States Army Corps of Engineers (the “Corps”). The contract entered into on June 25, 1974, for the amount of $68,400, obligated plaintiff to build a sewer-holding tank system at the Thomas J. O’Brien Lock and Dam in Chicago, Illinois. The work was substantially completed as of September 17, 1975, and a letter of final acceptance was issued on April 12, 1976.

On April 7,1976, plaintiff sent a payment estimate letter to the contracting officer reserving a balance of $50.00 until the pos[314]*314sibility of any extra claims had been examined. During the same week, the contracting officer issued a response inviting plaintiff to address and document all disputed items under the contract. No claims were raised.

The contracting officer made second and third inquiries requesting information on any possible claims in letters dated May 17, 1976, and June 18,1976. The latter specifically advised plaintiff that if a claim were not submitted before July 15, 1976, a final contract payment would be administered by forwarding a check for the retained balance of $50.00. These inquiries elicited no response from plaintiff. Final payment was rendered to plaintiff on September 2, 1976. The check was never cashed.

Over five years passed without any communication from plaintiff. The Corps then received a mailgram, dated October 13, 1981, advising that plaintiff was submitting a claim. Another letter received on October 16, 1981, contained various claims couched in broad terms without assigned monetary value or supporting documentation. On November 30, 1981, the contracting officer responded noting the numerous previous requests for information before the issuance of final payment. This letter also emphasized the need for information to support each claim and an explanation of the allocation of costs relative to each item.

Again plaintiff remained silent. Another invitation for additional information sent on July 2, 1982, also failed to stir plaintiff to clarify his claim. In August 1982 plaintiff telephoned the Corps on another matter, and agency counsel took the opportunity to remind plaintiff to supply the requested information on his claim. Plaintiff was also advised that the Corps’ files were available to him. Another year passed without a response.

A sixth and final letter was sent on June 30, 1983, stating that, if no response was received within 30 days, the contracting officer would assume that plaintiff did not intend to submit further information concerning his claim. Plaintiff did not respond. The contracting officer ultimately considered the claim based on plaintiff’s letter of October 13, 1981, and his own investigation. A decision denying plaintiff’s claim sent on January 31, 1984, by certified mail, was not acknowledged by plaintiff. The decision was reissued on April 23, 1984, and receipt was acknowledged by plaintiff on April 25, 1984.

After plaintiff commenced suit in this court on April 25, 1985, within 12 months of the date on which the decision was received, defendant moved for summary judgment contending that the claim is barred by the general six-year statute of limitations. Defendant also relies on the CDA provision that deems a claim denied as a matter of law if the contracting officer fails to act on it within 60 days as a predicate for its argument that such a denial starts the running of the DCA’s 12-month limitations period and that plaintiff is barred from suit because he did not file within 12 months of the date the claim was deemed denied. Finally, defendant raises the defense of laches.

DISCUSSION

Although defendant urges that the Claims Court’s general six-year statute of limitations, 28 U.S.C. § 2501 (1982), applies to a suit filed pursuant to the CDA, this court recently held that the CDA’s 12-month limitations period governs all suits that are based on the CDA. Kasler/Continental Heller/Fruin Colnon v. United States, 9 Cl.Ct. 187, 189-91 (1985); see also Union Manufacturing Co. v. USITC, 781 F.2d 186, 189 (Fed.Cir.1985) (Congress can pass statutes of limitations shorter than prior statutes, if reasonable).2 Plaintiff commenced this action within 12 months after receipt of the contracting officer’s decision, although he had delayed for years in submitting his claim to the contracting officer. However, a contrac[315]*315tor’s failure to act administratively within a reasonable time on his claim does not render the six-year statute applicable simply because the CDA’s one limitations period speaks only to the deadline for initiating the court process. To the contrary, the CDA explicitly states that all actions under the CDA shall be governed by the CDA’s provisions. See Kasler/Continental Heller/Fruin Colnon, 9 Cl.Ct. at 189-91.

Allowing the contractor to proceed in court under the circumstances present could have been avoided had the CDA limited the time within which the contractor is required to present his claim to a contracting officer. It did not. Even if defendant’s argument is consistent with the CDA’s legislative goal of arriving at prompt resolution of contract claims, see Kasler/Continental Heller/Fruin Colnon, 9 Cl.Ct. at 190, the court’s function is not to fashion a judicial bandage for an unfortunate gap in legislation. See In re Thorpe, 777 F.2d 695, 698 (Fed.Cir.1985) (court’s decision should not anticipate change in the law even if legislature may be considering amendment).

Defendant’s second argument is that plaintiff’s claim is barred because he failed to sue within 12 months after his claim was deemed denied. The CDA obligates a contracting officer to render a decision within 60 days of a written request from a contractor. 41 U.S.C. § 605(c)(1). Section 605(c)(2) provides that within 60 days of receipt of a submitted certified claim over $50,000 the contracting officer must either “issue a decision” or “notify the contractor of the time within which a decision will be issued.” Subsection (c)(5) further provides:

Any failure by the contracting officer to issue a decision on a contract claim within the period required will be deemed to be a decision by the contracting officer denying the claim and will authorize the commencement of the appeal or suit on the claim as otherwise provided in this Chapter____

The CDA’s legislative history illuminates that these provisions were intended “to insure that a contracting officer will act promptly on all claims and if he should arbitrarily delay, the contractor has recourse to obtaining a decision....”. S.Rep. No. 1118, 95th Cong., 2d Sess. 21, reprinted in 1978 U.S.Code Cong.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

System Planning Corp. v. United States
95 Fed. Cl. 1 (Federal Claims, 2010)
Land Grantors in Henderson, Union v. United States
86 Fed. Cl. 35 (Federal Claims, 2009)
Farmers Grain Co. v. United States
39 Cont. Cas. Fed. 76,585 (Federal Claims, 1993)
Maryland State Police v. Warwick Supply & Equipment Co.
624 A.2d 1238 (Court of Appeals of Maryland, 1993)
Spalding & Son, Inc. v. United States
37 Cont. Cas. Fed. 76,174 (Court of Claims, 1991)
Barrow Utilities & Electric Cooperative, Inc. v. United States
36 Cont. Cas. Fed. 75,840 (Court of Claims, 1990)
Travelers Indemnity Co. v. United States
35 Cont. Cas. Fed. 75,607 (Court of Claims, 1988)
W & J Construction Corp. v. United States
34 Cont. Cas. Fed. 75,318 (Court of Claims, 1987)
Pathman Construction Company, Inc. v. The United States
817 F.2d 1573 (Federal Circuit, 1987)
Kunz Construction Co. v. United States
34 Cont. Cas. Fed. 75,243 (Court of Claims, 1987)
Malissa Co. v. United States
33 Cont. Cas. Fed. 74,927 (Court of Claims, 1986)
Tsosie v. United States
11 Cl. Ct. 62 (Court of Claims, 1986)
United Construction Co. v. United States
33 Cont. Cas. Fed. 74,497 (Court of Claims, 1986)
Pathman Construction Co. v. United States
33 Cont. Cas. Fed. 74,394 (Court of Claims, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
33 Cont. Cas. Fed. 74,201, 9 Cl. Ct. 313, 1986 U.S. Claims LEXIS 921, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lacoste-v-united-states-cc-1986.