United Construction Co. v. United States

33 Cont. Cas. Fed. 74,497, 10 Cl. Ct. 257, 1986 U.S. Claims LEXIS 849
CourtUnited States Court of Claims
DecidedJune 30, 1986
DocketNo. 325-84C
StatusPublished
Cited by2 cases

This text of 33 Cont. Cas. Fed. 74,497 (United Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Construction Co. v. United States, 33 Cont. Cas. Fed. 74,497, 10 Cl. Ct. 257, 1986 U.S. Claims LEXIS 849 (cc 1986).

Opinion

OPINION

NETTESHEIM, Judge.

Having survived several motions for summary judgment that would have preter-mitted plaintiff’s day in court, see order entered on January 18, 1985 (motion for summary judgment; bench ruling); United Construction Co. v. United States, 7 Cl.Ct. 47 (1984) (motion for summary judgment), this case has been tried.1 The issue is whether the failure of an asphalt construction project was due to government specifications or lack of compaction and insufficient preparation of the subgrade. The parties have stipulated that recovery shall be in the amount of $250,887.83 if plaintiff prevails.

This case deserves to be put in a proper context by recognizing the significant and extensive efforts of counsel in achieving comprehensive factual stipulations. Counsel also showed a responsible approach to the evidence as it was developed, exemplified by defendant’s withdrawing its counterclaim during the course of trial. Nonetheless, defendant faced a formidable challenge when its expert witness candidly stated that he had no experience in asphalt design, other than in connection with Safeway markets 17 or 18 years ago; that he had not consulted before on a project involving the placement of asphalt for roadways or parking lots, such as the type of project involved in the litigation; and that this type of project is “definitely outside” his general line of work. This witness was [259]*259also confronted with his- preliminary report of 1985 that pointed to a lack of quantitative evidence to show that the subgrade was poorly compacted at the time of placement. The report also suggested that the Army Corps of Engineers would have difficulty in showing that the design of the pavement was sufficient. Not surprisingly, the credibility of witnesses has played no small part in shaping the findings of fact.

The operative events took place between 1978 and 1980, justifiably prompting defendant to try to dispose of the case by motion before trial. One key player, Doyle Shelton, the Government’s construction representative who served as a site inspector, in the long interval before trial became the victim of age and illness, as revealed by his deposition testimony. See Deposition of Doyle Shelton, June 15,1985, at 29. The delay between completion of the contract and filing suit was not attributable to actions of the Government, and the parties were advised that testimony reflecting poor memory would not be considered in plaintiff’s favor. The documentary evidence, buttressed by testimony of percipient witnesses, helped fill the voids of faded memories, and the record includes sufficient evidence to assess whether plaintiff has proved its case by a preponderance of the evidence.

FACTS

The parties agreed to 95 stipulations of fact which are incorporated herein by reference. The stipulations are affixed to the official copy of this opinion, but will not otherwise be reproduced.

In 1978 plaintiff United Construction Co., Inc. (“plaintiff”), was awarded a contract by the United States Army Corps of Engineers (the “Corps”) for the construction of bituminous surfaced (asphalt) and aggregate surfaced roads, eleven asphalt parking areas, concrete boat ramps, and a water distribution system at Harry S. Truman Dam and Reservoir in Missouri. The contract amount was $2,887,661.80, and performance originally was to be completed between August 1978 and April 1979. The three asphalt parking areas involved in this case are the Long Shoal boat ramp parking lot, the Long Shoal maneuver area (collectively referred to as “Long Shoal” unless otherwise indicated), and the Berry Bend boat ramp parking lot (“Berry Bend”).

Three types of contemporaneous records were maintained on plaintiff’s contract performance. Danny Locke, plaintiff’s on-site quality control officer, prepared performance Quality Control Reports (“QCR”s); the Corps maintained Daily Logs of Construction; and Bob Gene Johnson, a former superintendent for plaintiff, kept a daily diary. It was stipulated that plaintiff’s QCR’s and the Corps logs generally do not distinguish between the Long Shoal boat ramp parking lot and the Long Shoal maneuver area, nor do Mr. Johnson’s diary and most of the testimony. As a result the findings for the most part do not distinguish between the two sites.

The parties agree that “cut” refers to the excavation of material on a hillside to a specified grade, and “fill” refers to the placement of material from a cut area or a borrow area into compacted lifts of a specified height or grade. It was also stipulated that beginning in August 1978 the Government’s Daily Logs of Construction recorded the dates and nature of preliminary work in clearing and grubbing the sites, excavation (excavating fill from a cut or borrow area), and placement of the embankment (placing material to bring the ground surface to design grade requirements for placement of asphalt).

The Long Shoal parking lot was largely a fill area on the lower portion of the lot, and both the Long Shoal maneuver area and Berry Bend were entirely fill. For each site the Corps designated borrow areas, or areas from which fill was to be obtained. Some of the fill for the Long Shoal parking lot was obtained from the upper-cut portion. The remainder of the fill for the Long Shoal parking Jot, as well as the fill for the maneuver area and Berry Bend, was borrow from the area that ultimately became Truman Reservoir.

[260]*260Section 8 of the contract specifications entitled “Formation of Embankment” provides:

8.1 General: Embankments shall be placed and compacted in horizontal layers or lifts. Trees, logs, stumps, rubbish, standing or matted brush, matted roots, sod, unsuitable materials, frozen materials, or any other deleterious material or substances shall not be placed in embankments. Holes left from removal of existing structures, and grubbing operations, shall be backfilled and compacted, unless otherwise specified. Additional lifts shall not be placed on embankment where the previous lift, contains frozen materials. Equipment of such weight or so loaded that it might cause damage to culverts or other structures shall not be permitted to work over or immediately adjacent to such structures until reasonable possibility of damage thereto no longer exists. Where embankments, regardless of height are placed against hillsides or existing embankments, either of which have a slope steeper than one vertical to six horizontal, the existing slope shall be benched or stepped as the new fill is brought up. The depth of the benches or steps shall be approximately equal to the lift being placed. In the event rock is encountered when benching, the benching operation shall be omitted, and the overburden stripped to firm rock line to permit fill to be placed in direct contact with the exposed rock surfaces.
8.2 Earthfills: Each layer or lift or material shall not exceed 8 inches in thickness loose measurement and shall be compacted to not less than the required density before the next layer is placed thereon. Blade graders and bulldozers shall be used on each lift to remove mounds and ridges caused by dumping operations and to obtain uniform thickness prior to and during compacting.
8.3 Combination earth and rock-fills: Layers or lifts formed of rock, shale, or other hard materials and earth materials that cannot be satisfactorily compacted in layers of 8 inches, shall be placed in uniform layers not to exceed 24 inches in thickness (loose measurement).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Construction Co. v. United States
34 Cont. Cas. Fed. 75,324 (Court of Claims, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
33 Cont. Cas. Fed. 74,497, 10 Cl. Ct. 257, 1986 U.S. Claims LEXIS 849, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-construction-co-v-united-states-cc-1986.