United Construction Co. v. United States

32 Cont. Cas. Fed. 73,130, 7 Cl. Ct. 47, 1984 U.S. Claims LEXIS 1233
CourtUnited States Court of Claims
DecidedDecember 12, 1984
DocketNo. 325-84C
StatusPublished
Cited by14 cases

This text of 32 Cont. Cas. Fed. 73,130 (United Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Construction Co. v. United States, 32 Cont. Cas. Fed. 73,130, 7 Cl. Ct. 47, 1984 U.S. Claims LEXIS 1233 (cc 1984).

Opinion

ORDER

NETTESHEIM, Judge.

This case is before the court on defendant’s motion for summary judgment, as opposed by plaintiff, after oral argument.

FACTS

The following facts are undisputed. On July 26, 1978, plaintiff United Construction Company, Inc. (“plaintiff”), entered into a construction contract with the Department of the Army Corps of Engineers, Kansas City District (the “Corps”). By letter dated June 25, 1979, plaintiff notified the Corps that additional work was required because construction site conditions were not as the parties had anticipated. The letter also expressed plaintiff’s expectations of an adjustment of the contract price and an extension on the contract completion date. Defendant directed plaintiff to perform the additional work.

On January 14, 1980, plaintiff submitted an uncertified notice of claim for the cost, approximating $550,000, that it allegedly would incur in performing the additional work. The letter stated in part, “If it is not possible to solve these problems through a claim procedure or change order, we request that you resolve these disputes in accordance with contract General Provision 6-a.”

Plaintiff attempted to negotiate its claim from January 14, 1980, to May 26, 1982. After negotiations failed to prove fruitful, plaintiff, by letter dated May 26, 1982, requested that the contracting officer issue a final decision on its claim. On August 26, 1982, the contracting officer issued a “final decision” denying plaintiff’s claim on the merits. The decision letter, received on August 27, contained the language applicable to a “transition case” involving a claim emanating from a contract entered into before March 1, 1979, the date on which the Contracts Disputes Act of 1978, 41 U.S.C. §§ 601-613 (1982) (the “CDA”), became effective. The letter advised the contractor of its right to elect to proceed under the contract Disputes clause or the CDA, pursuant to 41 U.S.C. § 601 note:

This is the final decision of the Contracting Officer. This decision may be appealed to the Corps of Engineers Board of Contract Appeals. As a result of the enactment of the Contract Disputes Act of 1978, you may elect to proceed under the Contract Disputes Clause or under the Act. If you decide to make an appeal under the Contract Disputes Clause, you must mail or otherwise furnish written notice thereof to the Contracting Officer ... within thirty (30) days from the date you receive this decision. If you decide to appeal under the Act, you must mail or otherwise furnish written notice thereof to the Corps of Engineers Board of Contract Appeals within ninety (90) days from the date you receive this decision.... Further, for appeals under the Act, in lieu of appealing to the Corps of Engineers Board of Contract Appeals, you may bring an action directly in the United States Court of Claims within 12 months of the date you received this decision.

In a letter dated August 31, 1982, plaintiff’s counsel advised Corps counsel for the Kansas City District that it “is my present inclination that we will proceed under the Contract Disputes Act.” Counsel for plaintiff also requested forms for the certification of costs pursuant to the CDA: “If we intend to appeal this decision under the Contract Disputes Act we must have this certification.” On September 2, 1982, the Corps District Counsel informed plaintiff’s counsel in writing of the proper certification language. By two letters dated March 24, 1983, plaintiff informed both the Corps and the Corps’ District Counsel of plaintiff’s “intention” to proceed under the CDA by filing suit in this court.

According to the unchallenged affidavit of plaintiff’s counsel, plaintiff reiterated this intention in a telephone conversation on April 1, 1983, with James Dyer, Assistant District Counsel for Kansas. Plain[50]*50tiffs counsel said that plaintiff was going to proceed under the CDA by filing an action in this court. In that conversation, Mr. Dyer informed plaintiff that Skelly & Loy v. United States, 231 Ct.Cl. 370, 685 F.2d 414 (1982), had issued, holding that a certified claim is a prerequisite to suit in this court. Mr. Dyer further informed plaintiff that the August 26, 1982 decision on an uncertified claim “was a nullity and of no legal effect” and advised plaintiff to prepare an accurate breakdown of costs and then submit a certified claim on the basis of which the contracting officer could issue a new final decision. Plaintiff requested a copy of the Skelly & Loy decision from Mr. Dyer and agreed to submit a certified claim. Affidavit of Charles R. Svoboda ¶¶ 1-2.

Under cover of an April 5, 1983 letter from F.H. Moore, Corps District Counsel, plaintiff received a copy of the Skelly & Loy decision. Plaintiffs counsel states in his affidavit that he contacted Mr. Dyer on “at least one and perhaps two occasions” after April 1, 1983, as suggested in Mr. Moore’s letter, and that, in these communications, he informed Mr. Dyer that he was preparing cost breakdowns to submit along with a certified claim, as Mr. Dyer had suggested. Svoboda Affidavit ¶ 3.

On March 8, 1984, approximately eleven months after being advised to do so, plaintiff submitted a certified claim to the contracting officer requesting an equitable adjustment in the amount of $324,297.57 or, in the alternative, a final decision from which an appeal could be perfected. The contracting officer responded to plaintiff by letter dated April 5, 1984, that he did not “intend to issue another ... final decision on this matter....” because the August 26, 1982 decision on the same claim submitted on January 14, 1980, was final and because plaintiff had failed timely to appeal.

Because the contracting officer refused to issue a final decision, plaintiff filed its complaint in this court on June 25, 1984, relying upon 41 U.S.C. § 605(c)(5) for the proposition that a failure to issue a final decision within 60 days of the receipt of a certified claim, pursuant to section 605(c)(1), is deemed a decision denying the claim, thereby authorizing the commencement of suit.

DISCUSSION

1. Timeliness of Court Action

Whether this court lacks jurisdiction to entertain plaintiff’s suit depends on whether the contracting officer issued a final decision. The court is guided by the principle that the scope of the sovereign’s waiver of sovereign immunity under the CDA must be strictly construed. See, e.g., Lehman v. Nakshian, 453 U.S. 156, 161, 101 S.Ct. 2698, 2702, 69 L.Ed.2d 548 (1981); United States v. Mitchell, 445 U.S. 535, 538, 100 S.Ct. 1349, 1351, 63 L.Ed.2d 607 (1980); Fidelity Construction Co. v. United States, 700 F.2d 1379, 1383-84 (Fed.Cir.1983); Cosmic Construction Co. v. United States, 697 F.2d 1389, 1390 (Fed.Cir.1982).

41 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Renda Marine, Inc. v. United States
71 Fed. Cl. 782 (Federal Claims, 2006)
Witherington Construction Corp. v. United States
45 Fed. Cl. 208 (Federal Claims, 1999)
Buchan v. United States
27 Fed. Cl. 222 (Federal Claims, 1992)
George W. Kane, Inc. v. United States
38 Cont. Cas. Fed. 76,385 (Court of Claims, 1992)
Triax Co. v. United States
35 Cont. Cas. Fed. 75,697 (Court of Claims, 1989)
Donald M. Drake Co. v. United States
34 Cont. Cas. Fed. 75,330 (Court of Claims, 1987)
H.H.O. Co. v. United States
34 Cont. Cas. Fed. 75,256 (Court of Claims, 1987)
White Mountain Apache Tribe v. United States
11 Cl. Ct. 614 (Court of Claims, 1987)
Hickman v. United States
10 Cl. Ct. 550 (Court of Claims, 1986)
United Construction Co. v. United States
33 Cont. Cas. Fed. 74,497 (Court of Claims, 1986)
LaCoste v. United States
33 Cont. Cas. Fed. 74,201 (Court of Claims, 1986)
Kasler/Continental Heller/Fruin Colnon v. United States
33 Cont. Cas. Fed. 74,096 (Court of Claims, 1985)
Saunooke v. United States
8 Cl. Ct. 327 (Court of Claims, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
32 Cont. Cas. Fed. 73,130, 7 Cl. Ct. 47, 1984 U.S. Claims LEXIS 1233, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-construction-co-v-united-states-cc-1984.