Witherington Construction Corp. v. United States

45 Fed. Cl. 208, 1999 U.S. Claims LEXIS 252, 1999 WL 974843
CourtUnited States Court of Federal Claims
DecidedOctober 20, 1999
DocketNo. 97-124C
StatusPublished
Cited by11 cases

This text of 45 Fed. Cl. 208 (Witherington Construction Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Witherington Construction Corp. v. United States, 45 Fed. Cl. 208, 1999 U.S. Claims LEXIS 252, 1999 WL 974843 (uscfc 1999).

Opinion

OPINION

ALLEGRA, Judge.

This government contract suit is before the court on the defendant’s motion to dismiss the monetary portions of Count 1 of the plaintiffs amended complaint due to an alleged failure to comply with the Contract Disputes Act (CDA), 41 U.S.C. § 701 et seq. After carefully reviewing the submissions of the parties, and following oral argument, the court GRANTS defendant’s motion, dismissing, without prejudice, the monetary claims contained in Count 1 of the amended complaint.

I. Facts

This case arises out of a contract between the Witherington Construction Company (Witherington) of Mobile, Alabama and the General Services Administration (GSA). As amended, plaintiffs complaint sets forth three counts: (i) the first count alleges that, on August 19, 1996, the contracting officer wrongfully terminated plaintiffs contract for default, giving rise to a number of monetary claims; (ii) the second count alleges that, on July 5, 1996, the contracting officer wrongly determined that plaintiff was not entitled to recover the cost associated with the removal of a plaster ceiling in an elevator lobby; and (iii) the third count challenges the contracting officer’s decision of October 17, 1997, [210]*210asserting that the government is entitled to liquidated damages. The defendant’s motion seeks to dismiss only the monetary claims contained in the first of these three counts, the underlying facts with respect to which are as follows:

On August 18, 1995, GSA awarded a contract to Witherington to renovate and alter the U.S. Post Office and Courthouse in Fort Smith, Arkansas. A series of disputes ensued between GSA and Witherington, culminating in an August 19, 1996, letter from the GSA terminating the contract for default. The letter was the “final decision” of the contracting officer (CO) regarding Wither-ington’s failure to comply with the requirements of the contract. Without submitting a certified claim to the contracting officer for alleged monetary damages associated with the CO’s termination of the contract, Wither-ington filed suit in this court on February 27, 1997, appealing the CO’s termination for default and demanding monetary compensation for the government’s allegedly improper termination.

On August 4, 1997, the GSA issued yet another “final decision,” demanding $467,-041.13 in liquidated damages based on With-erington’s alleged repudiation of the contract; this amount was later reduced, in yet another “final decision,” to $437,041.13. On April 16, 1998, Witherington amended its complaint to appeal the CO’s demand for liquidated damages. Defendant filed its answer on June 1, 1998.

Prior to a July 22, 1998 status conference, counsel for the government first raised the question whether this court had jurisdiction to entertain the monetary claims associated with Count 1 of plaintiffs suit. According to counsel, because the plaintiff had failed to submit a certified demand for payment of these sums to the contracting officer pursuant to 41 U.S.C. § 605(a) (1994), none of the myriad “final decisions” issued by the CO during the course of the parties’ dispute were effective to satisfy the jurisdictional requirements of the CDA with respect to the monetary claims. The parties then entered into a series of discussions regarding the manner in which this jurisdictional defect might be corrected. A letter submitted to this court by plaintiff on July 29, 1998, indicated that the parties had agreed to ask the court for a stay to provide the plaintiff with the opportunity to rectify its failure to submit a certified claim regarding these claims to the CO. The court issued the requested stay on August 5, 1998. On August 26, 1998, the plaintiff submitted a certified request for a final decision on the monetary claims of Count 1, which was issued by the CO on December 1, 1998.

On January 22, 1999, the government, despite having agreed to allow the CO to consider Witherington’s claims, moved to dismiss the monetary portions of Count 1 of the amended complaint for lack of jurisdiction under RCFC 12(b)(1). The defendant alleges that the stay to which it assented was ineffective to cure the jurisdictional defect it identified. Rather, according to the defendant, once a lawsuit under the CDA is filed, a CO loses all authority to issue a final decision. As such, according to the defendant, this court does not have jurisdiction to entertain the monetary claims of Count 1.1

II. Discussion

The CDA provides that “[a]ll claims by a contractor against the government relating to a contract shall be in writing and shall be submitted to the contracting officer for a decision.” 41 U.S.C. § 605(a). A CDA action may be brought in the Court of Federal Claims only if (i) the contracting officer has issued a final decision on the contractor’s claim, 41 U.S.C. § 605(b); or (ii) the contracting officer has failed to issue a final decision on the contractor’s claim or to notify the contractor of the time within which a decision will be issued, and at least 60 days have passed since the date the claim was submitted, 41 U.S.C. § 605(c)(5). In the latter case, the claim is “deemed denied.” See Case Incorporated v. United States, 88 F.3d 1004, 1008 (Fed.Cir.1996); Sharman Co., Inc. [211]*211v. United, States, 2 F.3d 1564, 1569 (Fed.Cir.1993), overruled on other grounds, Reflectone, Inc. v. Dalton, 60 F.3d 1572, 1578-79 & n. 10 (Fed.Cir.1995); Ervin & Associates, Inc., et al. v. United States, 44 Fed.Cl. 646, 652-53 (1999). Moreover, under these provisions, it is axiomatic that a contracting officer’s decision that is invalid may not serve as a basis for a CDA action. See United States v. Grumman Aerospace Corp., 927 F.2d 575, 579 (Fed.Cir.1991), cert. denied, 502 U.S. 919, 112 S.Ct. 330, 116 L.Ed.2d 270 (1991); W.H. Moseley Co., Inc. v. United States, 230 Ct.Cl. 405, 677 F.2d 850, 851-52 (1982), cert. denied, 459 U.S. 836, 103 S.Ct. 81, 74 L.Ed.2d 77 (1982). Thus, to gain a jurisdictional foothold in this court, a plaintiff pursuing a contract claim must satisfy two fundamental jurisdictional requirements—it must submit a claim for money presently due and must obtain a “final decision” on the claim, either actual or deemed.

A. Has a “Final Decision” Been Rendered as to the Monetary Claims Contained in Count 1?

As to the claims for money damages contained in Count 1 of the plaintiffs complaint, the defendant argues that the December 1, 1998, determination made by the CO regarding the plaintiffs claims was not a “final decision” because it was rendered without authority and thus is ineffective.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seh Ahn Lee v. United States
127 Fed. Cl. 734 (Federal Claims, 2016)
System Planning Corp. v. United States
95 Fed. Cl. 1 (Federal Claims, 2010)
OK's Cascade Co. v. United States
87 Fed. Cl. 739 (Federal Claims, 2009)
Omega World Travel, Inc. v. United States
82 Fed. Cl. 452 (Federal Claims, 2008)
Renda Marine, Inc. v. United States
71 Fed. Cl. 782 (Federal Claims, 2006)
Lumbermens Mutual Casualty Co. v. United States
67 Fed. Cl. 253 (Federal Claims, 2005)
United Partition Systems, Inc. v. United States
12 A.L.R. Fed. 2d 867 (Federal Claims, 2004)
Vanalco, Inc. v. United States
48 Fed. Cl. 68 (Federal Claims, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
45 Fed. Cl. 208, 1999 U.S. Claims LEXIS 252, 1999 WL 974843, Counsel Stack Legal Research, https://law.counselstack.com/opinion/witherington-construction-corp-v-united-states-uscfc-1999.