Al Munford, Inc. v. United States

39 Cont. Cas. Fed. 76,594, 30 Fed. Cl. 185, 1993 U.S. Claims LEXIS 323, 1993 WL 513465
CourtUnited States Court of Federal Claims
DecidedDecember 6, 1993
DocketNo. 93-177 C
StatusPublished
Cited by7 cases

This text of 39 Cont. Cas. Fed. 76,594 (Al Munford, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Al Munford, Inc. v. United States, 39 Cont. Cas. Fed. 76,594, 30 Fed. Cl. 185, 1993 U.S. Claims LEXIS 323, 1993 WL 513465 (uscfc 1993).

Opinion

ORDER

MOODY R. TIDWELL, III, Judge.

This case is before the court on defendant’s motion to dismiss for lack of subject [188]*188matter jurisdiction under RCFC 12(b)(1) and (4). For the reasons set forth below, the court denies defendant’s motion.

FACTS

The United States awarded contract DABT02-91-C-0022 to Munford Construction Company on August 21, 1991 for building and repairing washracks at Fort McClellan, Alabama. Differences arose early in the contract performance period and months of disagreement followed. During this period, the contracting officer and Munford exchanged a series of letters detailing their grievances; the contracting officer persistently complained about Munford’s performance delays and Munford responded by reciting events it alleged excused the delays. In essence, plaintiff contended that the government added cost and time to the project by failing to timely direct plaintiff on problems caused by adverse soil and weather conditions and by insisting on a particular tank supplier, which unduly delayed materials procurement. The government, on the other hand, cited a number of performance deficiencies, including: (1) failure to commence work on time, (2) failure to make timely progress, (3) failure to provide a Master Progress Schedule, and (4) nonconforming performance.

The government terminated the contract for default on April 17, 1992. Plaintiff asserted that the termination was unjustified and discriminatory and on June 1, 1992 filed suit in Federal District Court in the Northern District of Alabama, Eastern Division, seeking to reinstate the contract and money damages. However, after plaintiffs surety undertook completion of the contract, the parties filed a joint motion for dismissal, which the district court granted on September 8, 1992. The joint agreement stipulated that plaintiff would pursue its monetary claims under the Contracts Disputes Act of 1978, 41 U.S.C. §§ 601-613 (1988) (CDA).

As part of its case in the district court, Munford issued a subpoena for defendant’s contract administrator, to which it attached an itemized list of expenses that contained the certification language specified by the CDA. Subsequently, on August 12, 1992, plaintiff sent the contracting officer a letter stating:

If there is any confusion on the part of the contracting officer about whether the claim was intended by Munford to be processed, then it is hoped and expected that this letter will satisfy any such confusion because the document is certainly a monetary claim presented to the contracting officer for payment.

On March 29, 1993, plaintiff filed an action in this court, seeking sums owed under the contract and other money damages, a finding of wrongful termination, and other relief arising from the contracting officer’s denial of plaintiff’s claim under the disputes clause. Plaintiff alleged jurisdiction under the CDA. Defendant responded with a motion to dismiss, alleging that plaintiff never submitted a “claim” to the contracting officer, a prerequisite to this court’s jurisdiction under the CDA

DISCUSSION

In considering defendant’s motion to dismiss for lack of subject matter jurisdiction, the court must accept as true any undisputed allegations of fact made by the non-moving party. Reynolds v. Army and Air Force Exch. Serv., 846 F.2d 746, 747 (Fed.Cir.1988). When disputed facts relevant to the issue of jurisdiction exist, the court may decide those questions of fact. Id.; Hedman v. United States, 15 Cl.Ct. 304, 306 (1988). When subject matter jurisdiction is questioned, the non-moving party bears the burden of establishing the court’s jurisdiction. Reynolds, 846 F.2d at 748.

I. The Jurisdictional Prerequisites of the Contracts Disputes Act

This Court’s jurisdiction is defined by the Tucker Act. 28 U.S.C. § 1491 (Supp. 1992). The Tucker Act alone does not create a substantive right to recover money, but instead waives sovereign immunity under specific conditions. United States v. Mitchell, 445 U.S. 535, 538, 100 S.Ct. 1349, 1351, 63 L.Ed.2d 607 (1980). In order for this court to exercise jurisdiction over plaintiffs claims, the claims must be predicated on a constitu[189]*189tional provision, statute, executive department regulation, or an express or implied contract with the United States. 28 U.S.C. § 1491(a)(1) (Supp.1992); Nussinow v. United States, 23 Cl.Ct. 556, 559 (1991). In this case, plaintiff asserted jurisdiction under the CDA, which applies to “any express or implied contract ... entered into by an executive agency for ... the disposal of property.” 41 U.S.C. § 602(a)(4). Under the CDA, jurisdiction over a claim vests in this court only after a contractor has submitted a valid claim to the contracting officer and the contracting officer has denied the claim or failed to deny it within sixty days. 41 U.S.C. §§ 605, 609; Paragon Energy Corp. v. United States, 645 F.2d 966, 227 Ct.Cl. 176, 184 (1981).

Under the CDA, “[a]ll claims by a contractor against the government relating to a contract shall be in writing and shall be submitted to the contracting officer for a decision.” 41 U.S.C. § 605(a). To satisfy the CDA, a claim need not contain any particular language or conform to any specific format. See Contract Cleaning Maintenance, Inc. v. United States, 811 F.2d 586, 592 (Fed.Cir.1987). The CDA merely requires the contractor to “submit in writing to the contracting officer a clear and unequivocal statement that gives the contracting officer adequate notice of the basis and amount of the claim.” Id., at 592 (citing Tecom, Inc. v. United States, 732 F.2d 935, 936-37 (Fed.Cir.1984)); Metric Constr. Co. v. United States, 1 Cl.Ct. 383, 392 (1983). Such a statement may be in the form of one or several documents. Contract Cleaning, 811 F.2d at 592.

Moreover, the request for payment must be “in dispute” at the time of the claim. 48 C.F.R. § 33.201 (1992); Dawco Constr., Inc. v. United States, 930 F.2d 872 (Fed.Cir.1991). As defendant noted, “a claim only exists when the parties clearly have abandoned negotiations and the amount claimed is definitely in dispute.” Sun Eagle Corp. v. United States, 23 Cl.Ct. 465, 473 (1991).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

K-Con Building Systems, Inc. v. United States
107 Fed. Cl. 571 (Federal Claims, 2012)
North Star Alaska Housing Corp. v. United States
76 Fed. Cl. 158 (Federal Claims, 2007)
Witherington Construction Corp. v. United States
45 Fed. Cl. 208 (Federal Claims, 1999)
Hamilton Securities Advisory Services, Inc. v. United States
43 Cont. Cas. Fed. 77,462 (Federal Claims, 1999)
Medina Construction, Ltd. v. United States
43 Cont. Cas. Fed. 77,458 (Federal Claims, 1999)
Orbas & Associates v. United States
40 Cont. Cas. Fed. 76,831 (Federal Claims, 1995)
Al Munford, Inc. v. United States
40 Cont. Cas. Fed. 76,830 (Federal Claims, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
39 Cont. Cas. Fed. 76,594, 30 Fed. Cl. 185, 1993 U.S. Claims LEXIS 323, 1993 WL 513465, Counsel Stack Legal Research, https://law.counselstack.com/opinion/al-munford-inc-v-united-states-uscfc-1993.