Al Munford, Inc. v. United States

40 Cont. Cas. Fed. 76,830, 34 Fed. Cl. 62, 1995 U.S. Claims LEXIS 163, 1995 WL 495223
CourtUnited States Court of Federal Claims
DecidedAugust 15, 1995
DocketNo. 93-177 C
StatusPublished
Cited by4 cases

This text of 40 Cont. Cas. Fed. 76,830 (Al Munford, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Al Munford, Inc. v. United States, 40 Cont. Cas. Fed. 76,830, 34 Fed. Cl. 62, 1995 U.S. Claims LEXIS 163, 1995 WL 495223 (uscfc 1995).

Opinion

ORDER

MOODY R. TIDWELL, III, Judge:

This order addresses three outstanding motions before the court: (1) defendant’s motion for summary judgment, (2) plaintiff’s motion to reset hearing on defendant’s motion for summary judgment, and (3) plaintiffs motion to amend, alter, or vacate the court’s order dismissing plaintiffs complaint.

The summary judgment motion addressed both plaintiffs complaint and defendant’s counterclaims for fraud. However, on May 24,1995, in open court and on the record, the court dismissed plaintiffs complaint for failure to prosecute, pursuant to RCFC 41(b), after plaintiff failed to appear at a scheduled oral argument. The court later confirmed that dismissal by written order filed on May 31, 1995. Thereafter, plaintiff filed two motions. On June 2, 1995, plaintiff filed a motion requesting that the court reset the date for oral argument, and on June 12, 1995, plaintiff filed a motion to amend, alter, or vacate the order dismissing the ease. For the reasons that follow the court denies each of these motions.

Following the court’s dismissal, only defendant’s counterclaims remain at issue in defendant’s motion for summary judgment. As to those claims, the court grants summary judgment in part, and denies it in part.

FACTS

This case centered around a contract awarded to Munford Construction Company on August 21, 1991, for building and repairing washracks at Fort McClellan, Aabama. Differences arose early in the contract performance period, and months of disagreement followed. During this period, the contracting officer and Munford exchanged a series of letters detailing their grievances; the contracting officer persistently complained about Munford’s performance delays, and Munford responded by reciting events it alleged excused the delays. In essence, plaintiff contended that the government add[64]*64ed cost and time to the project by failing timely to direct plaintiff on problems caused by adverse soil and weather conditions and by insisting on a particular tank supplier, which delayed materials procurement. The government, on the other hand, cited a number of performance deficiencies, including: failure to commence work on time, failure to make timely progress, failure to provide a Master Progress Schedule, and nonconforming performance.

The government terminated the contract for default on April 17, 1992. Plaintiff asserted that the termination was unjustified and discriminatory and on June 1,1992, filed suit in Federal District Court for the Northern District of Alabama, Eastern Division, seeking to reinstate the contract and money damages. However, because plaintiffs surety undertook completion of the contract, the issue of reinstatement was rendered moot, and the parties filed a joint motion for dismissal, which the district court granted on September 8, 1992. The joint agreement stipulated that plaintiff would pursue its monetary claims in this court.

As part of its case in the district court, plaintiff subpoenaed the contracting officer, and attached to the subpoena a certified claim for alleged damages arising from termination of the contract. Appended to the claim was an itemized list of plaintiffs “costs incurred.” The contracting officer denied this claim on September 11, 1992.

On March 29,1993, plaintiff filed an action in this court, “appealing” the contracting officer’s decision and further alleging that the default termination was racially motivated. In its complaint, plaintiff sought (1) sums allegedly due under the contract and damages caused by the termination; (2) declaratory judgment that defendant breached and wrongfully terminated the contract; (3) reversal of the contracting officer’s actions; and (4) other relief the court deemed necessary to provide plaintiff a full remedy. Defendant responded with a motion to dismiss for lack of subject matter jurisdiction, alleging that plaintiffs claim to the contracting officer did not meet the requirements of the CDA. On December 6, 1993, this court denied defendant’s motion to dismiss, holding that plaintiffs submissions to the contracting officer satisfied the threshold statutory and regulatory requirements of the Contracts Disputes Act of 1978, 41 U.S.C. §§ 601-613 (1988) (CDA). Al Munford, Inc. v. United States, 30 Fed.Cl. 185 (1993).

Subsequently, the parties entered into discover In its first set of interrogatories, defendant inquired into plaintiffs claim for monetary relief in this court. Plaintiffs response set forth a detailed list of the damages it sought. The list included: (1) loss of income caused by termination of the contract, (2) loss of income from other jobs resulting from the damage to plaintiffs reputation caused by the default termination, (3) loss of income of future years, (4) reimbursement for work completed, and (5) claims of creditors resulting from the termination. Defendant’s subsequent requests for admissions, interrogatories, and requests for production of documents confirmed that these were indeed the damages sought by plaintiff in this court, and that these damages relate both to the contract at issue and other contracts to which plaintiff was a party. Defendant also discovered that the damages sought from the contracting officer included amounts previously paid and costs plaintiff had not yet incurred.

On June 24, 1994, defendant filed counterclaims for civil fraud, alleging that plaintiffs claim to the contracting officer was fraudulent under both the False Claims Act, 31 U.S.C. § 3729 (1988) (FCA), and the CDA, 41 U.S.C. § 604 (1988). Specifically, defendant alleged that plaintiff submitted claims that were fictitious, inflated, and duplicative.

On November 16, 1994, defendant filed a motion for summary judgment on plaintiffs claims and defendant’s counterclaims. The court scheduled oral argument on the motion for May 24,1995, at 3:00 p.m. EST. However, when the scheduled time arrived, plaintiff was not present, and the court dismissed plaintiffs complaint for failure to prosecute, pursuant to RCFC 41(b). The court confirmed the dismissal by written order filed May 31, 1995. Plaintiff responded to the court’s dismissal with two motions: (1) on June 2, 1995, plaintiff filed a motion requesting the court to reset the date for oral argu[65]*65ment; and (2) on June 12,1995, plaintiff filed a motion to amend, alter, or vacate the order dismissing the case.

DISCUSSION

I. Plaintiffs Motion to Reinstate Its Complaint and to Reset Hearing on Defendant’s Motion for Summary Judgment.

In two motions filed on June 2, 1995, and June 12, 1995, respectively, plaintiff requested that this court alter, amend, or vacate its order dismissing the case, and reset oral argument on defendant’s motion for summary judgment. These motions followed the court’s May 24, 1995 dismissal of plaintiff’s complaint for failure to prosecute, which the court ordered after plaintiff failed to appear for oral argument. As grounds for its requests, plaintiff stated that it mistakenly believed that oral argument would be over the telephone, and that counsel was in its office and prepared for oral argument at the scheduled time.

RCFC 41(b) empowers this court to dismiss any action for plaintiffs failure to prosecute or to comply with an order or the rules of the court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Crane Helicopter Services, Inc. v. United States
45 Fed. Cl. 410 (Federal Claims, 1999)
UMC Electronics Co. v. United States
43 Fed. Cl. 776 (Federal Claims, 1999)
Commercial Contractors, Inc. v. United States
154 F.3d 1357 (Federal Circuit, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
40 Cont. Cas. Fed. 76,830, 34 Fed. Cl. 62, 1995 U.S. Claims LEXIS 163, 1995 WL 495223, Counsel Stack Legal Research, https://law.counselstack.com/opinion/al-munford-inc-v-united-states-uscfc-1995.