Commercial Contractors, Inc. v. United States

154 F.3d 1357, 1998 WL 559977
Court of Appeals for the Federal Circuit·Decided November 5, 1998·No. 97-5005·Published·Cited by 72 cases

Opinion

BRYSON, Circuit Judge.

Following a trial, the United States Court of Federal Claims held that Commercial Contractors, Inc., (CCI) knowingly submitted false or fraudulent claims with respect to a government construction project. See Commercial Contractors, Inc. v. United States, No. 612-89C (Fed.Cl. Aug. 29, 1995). The court entered judgment against CCI for more than $14 million. See Commercial Contractors, Inc. v. United States, No. 612-89C (Fed.Cl. Aug. 6, 1996). We affirm in part, reverse in part, and remand.

I

In October of 1987, the Army Corps of Engineers awarded a contract to CCI to construct several segments of the Telegraph Canyon Channel in Chula Vista, California, as part of a flood control project. The contract required CCI to excavate the areas in which the channel segments were to be built, to build the channel segments by setting up forms and pouring concrete into the forms, and to backfill the excavated areas surrounding the channel segments. The contract contained detailed specifications that governed all aspects of the work to be performed, including drawings indicating the lines to which CCI was required to excavate, quality control standards specifying the hardness that the poured concrete was required to achieve before the supporting forms could be removed, and miscellaneous other provisions specifying such factors as the proper composition and required compaction density of the backfill materials.

Joseph Augustine, CCI’s president and owner, and William Zondorak, CCI’s project manager, supervised the project for CCI. Mr. Augustine oversaw the field work, while Mr. Zondorak was primarily responsible for handling the paperwork, including the billing. The contract required CCI to hire a licensed surveyor to perform the specified surveying work, including the quantity surveys upon which payments were to be based. Michael Pallamary was the principal of Precision Survey & Mapping (PSM), the subcontractor CCI hired to perform that work.

CCI completed the contract on July 24, 1989. Shortly before that date, Mr. Palla-mary wrote to the Corps’ headquarters expressing concerns with CCI’s performance under the contract. Mr. Pallamary wrote a second letter following the completion of the contract, again noting deficiencies in CCI’s performance. That letter was forwarded to the Army’s Criminal Investigation Division *1362 (CID), which conducted an investigation of the charges.

On November 13, 1989, CCI filed suit in the Court of Federal Claims asserting a number of claims for additional payment under the contract. The suit was twice suspended pending resolution of the CID investigation into the allegations of criminal fraud by CCI. Instead of pursuing the criminal investigation, however, the government decided to assert counterclaims in CCI’s suit based on the anti-fraud provision of the Contract Disputes Act (CDA), 41 U.S.C. § 604, the False Claims Act (FCA), 31 U.S.C. §§ 3729-3731, and the Forfeiture of Fraudulent Claims Act (FFCA), 28 U.S.C. § 2514.

The Court of Federal Claims granted the government’s motion to bifurcate the trial so as to resolve the government’s counterclaims before addressing CCI’s affirmative claims. The counterclaims were tried between October 18 and October 30, 1993. After several rounds of post-trial briefing, the court entered a final judgment against CCI in the amount of $14,190,161.85 under the FCA and the CDA, and it ordered CCI’s affirmative claims to be forfeited pursuant to the FFCA. The court’s judgment rested on its finding that CCI submitted claims for payment that it knew to be false or fraudulent with respect to six categories of contract work: (1) excavation quantities; (2) backfill quantities; (3) backfill composition; (4) shoring; (5) channel length; and (6) concrete testing. CCI appeals from the judgment with respect to each of the six categories.

II

The False Claims Act provides, in pertinent part, that anyone who “knowingly presents ... a false or fraudulent claim for payment” to the government shall be liable “for a civil penalty of not less than $5,000 and not more than $10,000, plus 3 times the amount of damages which the Government sustains because of the act of that person.” 31 U.S.C. § 3729(a). The government must prove the elements of the cause of action by a preponderance of the evidence. See 31 U.S.C. § 3731(c). For purposes of the FCA, a contractor is deemed to have known that a claim it submitted was false if it had actual knowledge of the falsity of the claim or if it acted in deliberate ignorance or reckless disregard of the truth or falsity of the claim. See 31 U.S.C. § 3729(b).

The Contract Disputes Act provides that a contractor who is unable to support any part of a claim because of a misrepresentation of fact or fraud on the part of the contractor shall be liable to the government for the unsupported part of the claim, as well as for the government’s costs expended in reviewing the claim. See 41 U.S.C. § 604. To recover under the CDA, the government is required to establish that the contractor made false or fraudulent statements in its submitted claim with an intent to deceive or mislead the government. See 41 U.S.C. § 601(7). ■ Although the statute does not prescribe a standard of proof, the “preponderance of the evidence” standard has been applied in the past, see Al Munford, Inc. v. United States, 34 Fed. Cl. 62, 67 (1995), vacated on other grounds, 86 F.3d 1178, 1996 WL 252834 (Fed.Cir.1996) (Table), and we agree that the traditional civil standard is appropriate here. See Grogan v. Garner, 498 U.S. 279, 286, 111 S.Ct. 654, 112 L.Ed.2d 755 (1991) (citing Herman & MacLean v. Huddleston, 459 U.S. 375, 389-90, 103 S.Ct. 683, 74 L.Ed.2d 548 (1983)).

The Forfeiture of Fraudulent Claims Act provides that “[a] claim against the United States shall be forfeited ... by any person who corruptly practices or attempts to practice any fraud against the United States in the proof, statement, establishment, or allowance thereof.” 28 U.S.C. § 2514. To prevail under the FFCA, the government is required to establish by clear and convincing evidence that the contractor knew that its submitted claims were false, and that it intended to defraud the government by submitting those claims. See Young-Montenay, Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Commercial Contractors, Inc. v. United States, 154 F.3d 1357, 1998 WL 559977 (Fed. Cir. 1998).

154 F.3d 1357 (Commercial Contractors, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

CSILO v. JC Remodeling, Inc.
First Circuit, 2020
Ingram v. Army
Federal Circuit, 2019
Mw Builders, Inc. v. United States
134 Fed. Cl. 469 (Federal Claims, 2017)
Hanover Insurance Company (The) v. United States
134 Fed. Cl. 51 (Federal Claims, 2017)
Lcm Energy Solutions v. United States
128 Fed. Cl. 728 (Federal Claims, 2016)
Alta Wind I Owner Lessor C v. United States
128 Fed. Cl. 702 (Federal Claims, 2016)
United States Ex Rel. Purcell v. MWI Corp.
807 F.3d 281 (D.C. Circuit, 2015)
Horn & Associates, Inc. v. United States
123 Fed. Cl. 728 (Federal Claims, 2015)
Ulysses, Inc. v. United States
117 Fed. Cl. 772 (Federal Claims, 2014)
Veridyne Corporation v. United States
758 F.3d 1371 (Federal Circuit, 2014)
Chapman Law Firm, LPA v. United States
113 Fed. Cl. 555 (Federal Claims, 2013)
Kellogg Brown & Root Services, Inc. v. United States
728 F.3d 1348 (Federal Circuit, 2013)
Hernandez, Kroone and Associates, Inc. v. United States
110 Fed. Cl. 496 (Federal Claims, 2013)
United States v. Anchor Mortgage Corp.
711 F.3d 745 (Seventh Circuit, 2013)
Grand Acadian, Inc. v. United States
105 Fed. Cl. 447 (Federal Claims, 2012)
Railway Logistics International v. United States
103 Fed. Cl. 252 (Federal Claims, 2012)
Alcatec, LLC v. United States
100 Fed. Cl. 502 (Federal Claims, 2011)
Kellogg Brown & Root Services, Inc. v. United States
99 Fed. Cl. 488 (Federal Claims, 2011)