UMC Electronics Co. v. United States

43 Fed. Cl. 776, 1999 U.S. Claims LEXIS 149, 1999 WL 428039
CourtUnited States Court of Federal Claims
DecidedJune 23, 1999
DocketNos. 93-709C, 95-450C
StatusPublished
Cited by34 cases

This text of 43 Fed. Cl. 776 (UMC Electronics Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
UMC Electronics Co. v. United States, 43 Fed. Cl. 776, 1999 U.S. Claims LEXIS 149, 1999 WL 428039 (uscfc 1999).

Opinion

OPINION

HORN, Judge.

The case comes before the court following a contracting officer’s final decision, denying plaintiffs claim for an equitable adjustment under a contract for the production of floodlight sets for the United States Department of the Air Force. The plaintiff also asserted an adversary claim against the United States [778]*778in the United States Bankruptcy Court for the District of Connecticut. The Bankruptcy Court dismissed the adversary proceeding without prejudice and ordered the plaintiff and the United States to refile their pleadings in the United States Court of Federal Claims.

The plaintiff, therefore, filed a first complaint in this court, Case No. 93-709C, appealing the contracting officer’s final decision and seeking an additional claim for labor costs. The court dismissed the plaintiffs labor cost claims based upon a failure to submit the claim to the contracting officer. Following a contracting officer’s denial of the labor cost claims, plaintiff filed an additional complaint in this court, Case No. 95-450C. These two complaints were subsequently consolidated.

On August 28, 1995, the United States moved for leave to file counterclaims under the Special Plea in Fraud, 28 U.S.C. § 2514 (1994), the False Claims Act, 31 U.S.C. § 3729 (1994), and the antifraud provision of the Contract Disputes Act, 41 U.S.C. § 604 (1994). This motion was granted at a status conference on October 26, 1995. A trial on the government’s fraud counterclaims was conducted prior to action on the plaintiffs claim because, if the government were to be successful, the plaintiffs claim would be foreclosed. Closing arguments were conducted on March 2, 1999, after which the parties sought leave to file additional pleadings.

FACTS

Prior to September 1986, the Air Force had prepared an “Acquisition Plan” to procure portable floodlight sets, termed the “NF-2D,” to replace its fleet of “NF-2” Floodlight Sets, which are used throughout the world to provide lighting for nighttime maintenance, loading and unloading, security, and emergency lighting of Air Force aircraft. The Acquisition Plan recommended the procurement of the NF-2D Floodlight Sets because the Air Force considered this to be the best alternative to replace the aging NF-2 Floodlight Sets which had exceeded their normal service life. In September 1986, the Air Force issued Request for Proposals to obtain a fixed price contract from a small business concern for the acquisition of “a best estimated quantity” of 7,350 NF-2D Floodlight Sets.

On April 29, 1988, the Air Force awarded Contract No. F41608-88-D-16801 to UMC Electronics Company (UMC), a small business concern which was engaged in the manufacture and supply of equipment for a variety of customers including the United States. UMC is a debtor in possession under the supervision of the United States Bankruptcy Court, District of Connecticut, Case No. 92-53869, and the plaintiff and counterclaim defendant in this proceeding. UMC’s primary place of business is North Haven, Connecticut.

Under the terms of the contract, the ordering period commenced on the effective date of the contract, April 29, 1988, and expired five years after award date, on April 28, 1993. The contract required UMC to build NF-2D Floodlight Sets in accordance with the Scope of the Purchase Description, as amended, which “covers a basic NF-2 modified to include 3 KW Diesel Engine Driven (DED) generator set, modified version of the DOD generator set, MEP-016B, and two 1,000 watt high pressure sodium lights.” In addition, the contract required that UMC initially produce a first article floodlight unit that would be subject to design review and testing.

The contract contains, in Part II, Contract Clauses, the standard “Disputes” clause from the Federal Acquisition Regulations (FAR), 48 C.F.R. § 52.233-1 (APR 1984), which prescribes the procedure for a contractor seeking an equitable adjustment. This clause, FAR 52.233-1, states:

(a) This contract is subject to the Contract Disputes Act of 1978 (41 U.S.C. [§§ ] 601-613) (the Act).
[779]*779(b) Except as provided in the Act, all disputes arising under or relating to this contract shall be resolved under this clause.
(c) “Claim,” as used in this clause, means a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to this contract. A claim arising under a contract, unlike a claim relating to that contract, is a claim that can be resolved under a contract clause that provides for the relief sought by the claimant. However, a written demand or written assertion by the Contractor seeking the payment of money exceeding $50,000 is not a claim under the Act until certified as required by subpara-graph (d)(2) below. A voucher, invoice, or other routine request for payment that is not in dispute when submitted is not a claim under the Act. The submission may be converted to a claim under the Act, by complying with the submission and certification requirements of this clause, if it is disputed either as to liability or amount or is not acted upon in a reasonable time.
(d) (1) A claim by the Contractor shall be made in writing and submitted to the Contracting Officer for a written decision. A claim by the Government against the Contractor shall be subject to a written decision by the Contracting Officer.
(2) For Contractor claims exceeding $50,000, the Contractor shall submit with the claim a certification that—
(i) The claim is made in good faith;
(ii) Supporting data are accurate and complete to the best of the Contractor’s knowledge and belief; and
(iii) The amount requested accurately reflects the contract adjustment for which the Contractor believes the Government is liable.
(3)(i) If the Contractor is an individual, the certification shall be executed by that individual.
(ii) If the Contractor is not an individual, the certification shall be executed by—
(A) A senior company official in charge at the Contractor’s plant or location involved; or
(B) An officer or general partner of the Contractor having overall responsibility for the conduct of the Contractor’s affairs.
* * * * * *
(h) The Contractor shall proceed diligently with performance of this contract, pending final resolution of any request for relief, claim, appeal, or action arising under the contract, and comply with any decision of the Contracting Officer.

48 C.F.R. § 52.233-1 (1987).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mw Builders, Inc. v. United States
134 Fed. Cl. 469 (Federal Claims, 2017)
Horn & Associates, Inc. v. United States
123 Fed. Cl. 728 (Federal Claims, 2015)
United States ex rel. Wuestenhoefer v. Jefferson
105 F. Supp. 3d 641 (N.D. Mississippi, 2015)
Ulysses, Inc. v. United States
117 Fed. Cl. 772 (Federal Claims, 2014)
Aey, Inc. v. United States
114 Fed. Cl. 619 (Federal Claims, 2014)
Kellogg Brown & Root Services, Inc. v. United States
99 Fed. Cl. 488 (Federal Claims, 2011)
United States Ex Rel. Farmer v. City of Houston
523 F.3d 333 (Fifth Circuit, 2008)
Trafalgar House Construction, Inc. v. United States
77 Fed. Cl. 48 (Federal Claims, 2007)
Daewoo Engineering & Construction Co. v. United States
73 Fed. Cl. 547 (Federal Claims, 2006)
Riley Construction Co. v. United States
65 Fed. Cl. 264 (Federal Claims, 2005)
US Ex Rel. Ervin and Assoc. v. Hamilton SEC.
370 F. Supp. 2d 18 (District of Columbia, 2005)
Visiting Nurse Ass'n of Brooklyn v. Thompson
378 F. Supp. 2d 75 (E.D. New York, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
43 Fed. Cl. 776, 1999 U.S. Claims LEXIS 149, 1999 WL 428039, Counsel Stack Legal Research, https://law.counselstack.com/opinion/umc-electronics-co-v-united-states-uscfc-1999.