Lodge Construction, Inc. v. United States

CourtUnited States Court of Federal Claims
DecidedJanuary 10, 2022
Docket13-499
StatusPublished

This text of Lodge Construction, Inc. v. United States (Lodge Construction, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lodge Construction, Inc. v. United States, (uscfc 2022).

Opinion

In the Cited States Court of Federal Claims

No. 13-499; 13-800 Filed: January 10, 2022

LODGE CONSTRUCTION, INC., Plaintiff,

v.

THE UNITED STATES,

Defendant.

Michael H. Payne, Cohen Seglias Pallas Greenhall & Furman, Philadelphia, PA, and Edward Parrott, Watt, Tieder, Hoffar & Fitzgerald, L.L.P., McLean, VA, for Plaintiff.

John H. Roberson, Senior Trial Counsel, with whom were Steven Hough, Trial Attorney, Joana Cristei, Trial Attorney, Deborah A. Bynum, Assistant Director, Martin F. Hockey, Jr., Acting Director, Commercial Litigation Branch, and Brian M. Boynton, Acting Assistant Attorney General, Civil Division, U.S. Department of Justice, Washington, D.C., for Defendant.

POST-TRIAL OPINION AND ORDER

TAPP, Judge.

“Men must turn square corners when they deal with the Government.” Rock Island A. & L.R. Co. v. United States, 254 U.S. 141, 143 (1920) (Holmes, J.). In this case, the Court is presented with whether Lodge Construction, Inc. (“Lodge”) fraudulently submitted cost claims to the United States. At trial, the United States showed that Lodge misrepresented the value of certain equipment, billing the United States for operating four off-road dump trucks collectively valued at over $3,500,000 when the trucks were actually worth less than $100,000 combined. The United States also demonstrated that Lodge designed a ratio to inflate its total equipment, labor, and overhead costs—a ratio through which Lodge, at times, billed taxpayers at rates between $2,000 and $22,000 per hour for work performed by a single laborer or piece of equipment. Lodge also manipulated that already-dubious ratio by seeking compensation for work performed on days outside of the claim period, often with nominal expenditures of manpower, effort, and resources. Those examples and others support the Court’s conclusion that Lodge committed two violations of the False Claims Act when it certified and submitted two false claims to the U.S. Army Corps of Engineers (“the Army Corps”).

This case should serve as a cautionary tale to government contractors. For those who seek to recoup sums of money from the Federal Government, and thus burden taxpayers, rudimentary recordkeeping and approximated claims are likely insufficient. When job cost data and recordkeeping are inaccurate, the claim will inevitably contain errors and the line between negligence and reckless disregard for the truth becomes vanishingly thin. Cross it, and the government contractor’s claim becomes fraudulent as a matter of law, a designation that carries financial, practical, and stigmatic consequences. Here, while some elements of Lodge’s claims may reflect nothing more than slapdash formulae, overwhelming evidence establishes that substantial portions of those claims are patently deceitful.

It is now apparent that Lodge failed to earnestly undertake the obligations of claim certification: to ensure a claim submitted for payment is accurate and truthful. Lodge failed to accurately identify the equipment it used and support the valuation of that equipment with proper documentation in an act of deceit to increase its claim. Lodge used a dubious metric, riddled with errors, to measure its inefficiencies and dishonestly inflate Lodge’s claims. Lodge employed an artifice through which it sought to inflate costs of its equipment by reporting operation hours to the Army Corps differently than it recorded them internally. And finally, Lodge sought double recovery of costs for which Lodge assumed the risk of increased operation.

Despite originally admitting its claims contained errors, Lodge later reversed course and doubled down on its claims. Perhaps as a feature of the latter strategy, Lodge made clear that its claims were not the product of a mistake but were intentional. However, Lodge’s claims were also false. Lodge knew or should have known them to be false. And when a contractor acts intentionally or with reckless disregard for accuracy, submitting a false claim for payment is fraud.

I. Background and Procedural History

This case is procedurally complex. A brief overview will provide context to the findings of fact and conclusions of law. The dispute stems from a construction project to rehabilitate a levee in South Florida. The project was known as “Site 1 Impoundment Phase I” or simply “Site 1.” Although Lodge’s performance on that project is not directly at issue here, the Court reiterates the overview it provided in its recent opinion, Lodge Constr., Inc. v. United States, 153 Fed. Cl. 430 (2021).

In August 2010, the Army Corps awarded Lodge a competitively-bid fixed price contract to rehabilitate a levee in Palm Beach County—part of the Army Corps’ broader “Everglades Update” restoration mission. The levee rehabilitation work required removal of the top layers of the existing levee slopes and replacement of those layers with soil cement and other mechanical means of shoring up the levee. (Joint Stipulation of Facts (“JSOF”) 4 2, ECF No. 43). The levee was adjacent to the L-40 canal. L-40 CAMEL

io

CANTRECTOR STAGING 4REA PHASE 1 DEWATERING

EFFLUENT STORAGE AERA (S00 ACRES)

SITE 1 IMPOUNDMENT CONTRACTOR STAGING AREA

LIMITE: OF CONSSTPRLIC THD

HLL SEORS CANAL

Lodge Construction, Inc. v. United States, Case No. 13-499, Lodge’s MSJ on Liability Ex. C, ECF No. 19-2

Lodge divided the project area into six numbered sections, starting with Section 1 at the east end of the site. The project also required subsurface work, so Lodge constructed a temporary cofferdam so that it could perform that subsurface work “in the dry.”' Lodge performed work a few feet above the groundwater table, so the project required significant dewatering efforts.

Pursuant to the solicitation, Lodge was required to submit a design based on the Army Corps’ subsurface geotechnical site inspection and analysis. After revisions, the Army Corps accepted Lodge’s final cofferdam design proposal in July 2011, and Lodge began work soon thereafter. In mid-March 2012, water breached two sections of the cofferdam’s sheet pile wall in Section 2, flooding the project site.” After the failure, the Army Corps retroactively disapproved

' A cofferdam is “a watertight enclosure from which water is pumped to expose the bottom of a body of water and permit construction[.]” Cofferdam, Meriam Webster’s Online Dictionary, https://www.merriam-webster.com/dictionary/cofferdam (last visited Jan. 7, 2022). For an overview of the Army Corps’ cofferdam and wet construction techniques, see generally Patrick O’Bannon, Working in the Dry: Cofferdams, In-River Construction, and the United States Army Corps of Engineers (United States Army Corps of Engineers, Pittsburg District, 2009) available at https://usace.contentdm.oclc.org/digital/collection/p16021coll4/id/156/ (last visited Jan. 7, 2022).

* Lodge maintains that the breach was caused by a differing site condition. The Army Corps, however, maintains that Lodge’s cofferdam design was defective. Resolution of that issue is not ripe. Lodge’s cofferdam design. Lodge and the Army Corps corresponded over the next few months, and the Army Corps eventually sent Lodge a Cure Notice, demanding Lodge submit a revised cofferdam design by May 29, 2012 or be terminated for default.

Later in the summer of 2012, Lodge submitted three certified claims to the Contacting Officer. First, on June 21, 2012, Lodge certified and submitted its “Design Claim” related to the Army Corps’ retroactive disapproval of Lodge’s cofferdam design, stating:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sonnentheil v. Christian Moerlein Brewing Co.
172 U.S. 401 (Supreme Court, 1899)
United States v. Bornstein
423 U.S. 303 (Supreme Court, 1976)
Colorado v. New Mexico
467 U.S. 310 (Supreme Court, 1984)
United States v. Philip Morris USA Inc.
566 F.3d 1095 (D.C. Circuit, 2009)
Medichem, S.A. v. Rolabo, S.L.
437 F.3d 1157 (Federal Circuit, 2006)
Brunswick Bank & Trust Company v. The United States
707 F.2d 1355 (Federal Circuit, 1983)
United States v. Charles William Beard
761 F.2d 1477 (Eleventh Circuit, 1985)
Young-Montenay, Inc. v. United States
15 F.3d 1040 (Federal Circuit, 1994)
United States Ex Rel. Allen Lamers v. City of Green Bay
168 F.3d 1013 (Seventh Circuit, 1999)
Umc Electronics Co. v. United States
249 F.3d 1337 (Federal Circuit, 2001)
Kellogg Brown & Root Services, Inc. v. United States
728 F.3d 1348 (Federal Circuit, 2013)
Davies v. Owens-Illinois, Inc.
632 So. 2d 1065 (District Court of Appeal of Florida, 1994)
Lakeshore Engineering Services, Inc. v. United States
748 F.3d 1341 (Federal Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Lodge Construction, Inc. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lodge-construction-inc-v-united-states-uscfc-2022.