Riley Construction Co. v. United States

65 Fed. Cl. 264, 2005 U.S. Claims LEXIS 119, 2005 WL 1023512
CourtUnited States Court of Federal Claims
DecidedApril 28, 2005
DocketNo. 02-953 C
StatusPublished
Cited by5 cases

This text of 65 Fed. Cl. 264 (Riley Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Riley Construction Co. v. United States, 65 Fed. Cl. 264, 2005 U.S. Claims LEXIS 119, 2005 WL 1023512 (uscfc 2005).

Opinion

ORDER AND OPINION

HODGES, Judge.

Riley Construction Company filed this suit after completing a construction contract with the Navy. Plaintiff alleged in the Complaint that the Navy required a larger building than disclosed in the Request for Proposal. The claim for added costs of constructing the larger building included additional fees for the architecture firm that Riley employed, Knight Architects/Engineers. The parties filed cross-motions for summary judgment on Riley’s claim, and we scheduled an evidentia-ry hearing because of confusion over certain terms used in the construction contract.

[266]*266Mr. Riley is president of Riley Construction. The Government deposed Mr. Riley for the first time less than a month before the hearing. He testified during his deposition that Knight, the A/E company, had not billed Riley Construction for the additional fees that plaintiff seeks in its claim. The Government then filed a motion for leave to amend its Answer to add an affirmative defense and counterclaims for fraud and false claims. We granted defendant’s motion and canceled the evidentiary hearing because of the potentially dispositive nature of defendant’s supplemental Answer.

We conducted a two-day hearing on the Government’s counterclaims and affirmative defense. Mr. Riley and employees of the Knight A/E firm testified at the hearing. We did not find that plaintiff acted with the intent that is a necessary element of the fraud and the forfeiture statutes. We cannot rule now on Riley's alleged deliberate ignorance or reckless disregard in claiming architecture and engineering fees on Knight’s behalf. Such findings depend on factual and legal issues related to the Navy’s contract with Riley and Riley’s contract with Knight.

BACKGROUND

Riley Construction Company contracted with the Navy to design and construct a Navy Exchange Fleet Store at the Great Lakes Naval Training Center in Illinois. Soon after contract award, confusion arose over the size of the building. The Request for Proposal called for a building of approximately 56,000 square feet. Riley's interpretation of the specifications and definitions in the RFP created issues regarding two disputed areas of the building. These were a “mezzanine and storage system,” and part of an area outside the building that was covered by a canopy. The result was that Riley thought the building’s footprint could be no larger than 49,000 square feet. Riley claims that it prepared and priced its bid accordingly-

The difference between the Navy’s interpretation of the contract and Riley’s is the size of the “mezzanine and storage system” and the disputed canopy area, approximately 7,000 square feet. Defendant discounted Riley’s interpretation. It directed plaintiff to build a Fleet Store with approximately 56,000 square feet on the ground floor, and to also to build the mezzanine and the area under the canopy.

Riley proceeded as directed and completed the Fleet Store in September 2000, then filed a $948,963 claim for additional costs in April 2001. Plaintiff attributed the additional costs to the larger building required by the Navy. The claim included $73,176 for additional architecture and engineering fees for Knight to design the larger building. The contracting officer asserted that the Request for Proposal called for a building of 56,000 square feet, and denied the claim.

DISCUSSION

Riley Construction first learned of the Fleet Store project from Knight Architects/Engineers. The Request for Proposals called for a building of approximately 56,000 square feet. Confusion arose from the Navy’s having included a “mezzanine and storage system” in the RFP, along with an unenclosed area under a canopy. The parties disagree on how to account for the disputed areas. The additional design fees in Riley’s claim are the focus of this Opinion. This is so because Knight had not billed the additional design fees that Riley claimed. Mr. Riley explained that Riley and Knight had a relationship that permitted such a result.

Plaintiff attempted to distinguish its relationship with Knight from that typical of a prime contractor and its subcontractor. Riley and Knight were a “design-build team” that should be treated as a single entity, according to plaintiff. Mr. Riley did not include Knight among its subcontractors in the bid proposal “[bjecause they’re not a subcontractor ____ They are our partner.” Riley and Knight had worked together on another Navy construction project, but they had no legal or ongoing business relationship. Mr. Riley points to provisions of its design contract that place the responsibility for all [267]*267legal services and cost estimation on Riley.1 Mr. Riley testified that he thought such services included assembling and submitting claims for Knight. He also highlighted the unusual nature of the Fleet Store project.

Mr. Riley described the Fleet Store project as a “bid-design-build” contract. This requires contractors to submit bids without the benefit of an existing design, but only descriptive specifications such as square footage, types of facilities, capacities, and fixtures. The Fleet Store was the first bid-design-build project that Riley Construction had undertaken. Mr. Riley testified that this type of contract entails greater risk than the more common design-bid-build sequence in which the Government provides a design upon which contractors base their bids. In the latter situation, “a contractor can take the drawings and take the information ... [and] collect pricing, analyze it, and basically know this is the amount of work we’re going to provide, and this is the amount of money it’s going to cost.”

The Fleet Store contract required contractors to submit bids with only part of the information needed to price construction of the building, Mr. Riley explained. He testified that one consequence of the Fleet Store project’s bid-design-build contract was the lack of baselines against which to assess additional costs of the larger building. For example, Riley did not know precisely how much concrete the Fleet Store would require before submitting its bid because the building had not yet been designed. Riley suggested that similar problems applied with regard to the design fee.

The contract between Riley and Knight called for a design fee of $353,939. Mr. Riley testified that he understood the architecture and engineering fee to be a percentage of total construction costs — approximately six percent. Mr. Jorge Sirgo, who was Knight’s project manager for the Fleet Store, corroborated Mr. Riley’s understanding in a limited sense. He stated that Knight proposed its design fee based on the original construction cost of $5,997,000. He did not testify that the fee was a percentage of the total, however. Knight’s fee in fact was slightly less than six percent of the total.

Mr. Riley testified that such percentage fee arrangements are standard in the industry. Mr. Sirgo concurred, stating that architecture and engineering fees are “usually [calculated as] a percentage of the overall construction cost.” Mr. Riley testified repeatedly that Knight’s fee was six percent of Riley’s construction cost, but he also acknowledged that the design contract compensated Knight with a fixed fee of $353,939.

Mr. Sirgo commented, “[w]e were competing against other firms. So sometimes in the field we call it sharpening the pencil to have a fee that is very tight, trying to present a very attractive offer to the Government.” Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Horn & Associates, Inc. v. United States
123 Fed. Cl. 728 (Federal Claims, 2015)
Ulysses, Inc. v. United States
117 Fed. Cl. 772 (Federal Claims, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
65 Fed. Cl. 264, 2005 U.S. Claims LEXIS 119, 2005 WL 1023512, Counsel Stack Legal Research, https://law.counselstack.com/opinion/riley-construction-co-v-united-states-uscfc-2005.