Larry D. Barnes, Inc. v. United States

45 F. App'x 907, 45 Fed. Appx. 907, 2002 U.S. App. LEXIS 16595, 2002 WL 1890798
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 14, 2002
DocketNo. 01-5020
StatusPublished
Cited by5 cases

This text of 45 F. App'x 907 (Larry D. Barnes, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Larry D. Barnes, Inc. v. United States, 45 F. App'x 907, 45 Fed. Appx. 907, 2002 U.S. App. LEXIS 16595, 2002 WL 1890798 (Fed. Cir. 2002).

Opinion

LINN, Circuit Judge.

Larry D. Barnes, Inc., doing business as Tri-Ad Constructors (hereinafter “TriAd”), appeals the decision of the Court of Federal Claims denying Tri-Ad’s claim for equitable adjustment of a contract for the replacement of underground water lines. Tri-Ad further appeals the grant of the government’s counterclaims pursuant to the Contract Disputes Act (“CDA”) Anti-Fraud provision and the False Claims Act. Because Tri-Ad has demonstrated no errors of law or clearly erroneous factual findings, we affirm.

DISCUSSION

Tri-Ad argues that the Court of Federal Claims erroneously rejected Tri-Ad’s interpretation of the contract as unreasonable, erroneously credited the government’s affirmative defense under the Special Plea in Fraud, and erroneously awarded damages pursuant to the government’s counterclaims under the CDA Anti-Fraud provision and the False Claims Act. We address each of Tri-Ad’s contentions in turn.

A. Contract Interpretation

Tri-Ad argues that the Court of Federal Claims erred in its finding that Tri-Ad’s construction of the contract was unreasonable. Tri-Ad argues that the bid solicitation represented that the contractor would encounter only 100 underground utility obstructions. According to Tri-Ad, the solicitation included an estimated quantity of 100 for line items 36 and 37, the only line items mentioning use of a backhoe, which was required for use in excavating near the underground obstructions. Tri-Ad further argues that, based upon the number of obstructions and the government’s obligation to mark each obstruction, it reasonably assumed that it could use a trenching machine capable of excavating 800 linear feet per day.

The interpretation of a contract is a question of law to be decided by the court. B.D. Click Co. v. United, States, 222 Ct.Cl. 290, 614 F.2d 748, 752 (Ct.Cl.1980). It is a cardinal rule of contract construction that the joint intent of the [909]*909parties is dominant if it can be ascertained. See United States v. Bethlehem Steel Co., 205 U.S. 105, 119, 27 S.Ct. 450, 51 L.Ed. 731 (1907); J.W. Bateson Co. v. United States, 196 Ct.Cl. 531, 450 F.2d 896, 902 (Ct.Cl.1971). If some substantive provision of a government-drawn agreement is fairly susceptible of a certain construction and the contractor actually and reasonably so construes it, in the course of bidding or performance, that is the interpretation which will be adopted — unless the parties’ intention is otherwise affirmatively revealed. WPC Enters., Inc. v. United States, 163 Ct.Cl. 1, 323 F.2d 874, 876 (Ct.Cl.1963); Peter Kiewit Sons’ Co. v. United States, 109 Ct.Cl. 390, 418 (1947). It is well settled that where a contractor seeks recovery based on his interpretation of an ambiguous contract, he must show that he relied on this interpretation in submitting his bid. See Edward R. Marden Corp. v. United States, 803 F.2d 701, 705 (Fed.Cir.1986); Dale Ingram, Inc. v. United States, 201 Ct.Cl. 56, 475 F.2d 1177, 1185 (Ct.Cl.1973).

Tri-Ad contends that the parties’ contemporaneous understanding comported with its interpretation, because the government agreed to modifications of the contract under which Tri-Ad was compensated for several hundred underground obstructions under line item 36. Tri-Ad argues that these modifications did not fully compensate for the negative effect on TriAd’s overall productivity caused by the underground obstructions, including a so-called “ripple effect.” For example, TriAd argues that it intended to use a trencher on the project, but was forced to switch to a less-efficient baekhoe after running into significantly more obstructions than Tri-Ad expected to encounter. Tri-Ad claims the government owes it further compensation for loss of productivity under the theories of constructive change, differing site conditions, and variation of estimated quantities (“VEQ”).

The Court of Federal Claims found no support for Tri-Ad’s contentions that it bid this contract expecting to encounter only 100 underground, obstructions and expecting to excavate 800 linear feet per day. Larry D. Barnes, Inc. v. United States, No. 98-668C, slip op. at 3-4 (Fed.Cl. Aug. 31, 2000). The Court of Federal Claims noted evidence indicating that Tri-Ad was not surprised when it encountered fifty underground obstructions during the first two and a half months of a twelve-month contract. Id. at 4. Other evidence indicated that Tri-Ad’s estimate at bid time was 630 feet per day, using “3 2 men crews” averaging 210 feet per day (i.e., using backhoes rather than a trenching machine). Id. at 3.

The Court of Federal Claims found that, had Tri-Ad attended the pre-bid site inspection attended by other bidders, it would have known to expect much more than 100 underground obstructions. Id. at 4. The 1000 meter boxes estimated in the contract provided another indication that many more than 100 underground obstructions would be encountered. Id. at 5.

We agree with the Court of Federal Claims that Tri-Ad’s interpretation of the contract, including only 100 underground obstructions and permitting use of a trenching machine capable of excavating 800 feet per day, was unreasonable. Beyond the indications noted by the Court of Federal Claims that Tri-Ad did not in fact interpret the solicitation at bid time as they now contend, the contract documents and other information available to a reasonable bidder at bid time do not support Tri-Ad’s asserted interpretation.

Under the contract’s Site Investigation clause, Tri-Ad was charged with the knowledge available at the pre-bid site in[910]*910spection. The Site Investigation clause states,

The Contractor ... acknowledges that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site ... as well as from drawings and specifications made a part of this contract. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work ...

FAR § 52.236-3(a). Tri-Ad’s vice president stated at trial that he was familiar with this clause, but Tri-Ad chose not to attend the pre-bid site visit or conduct a separate site inspection because it would have been “useless.”

“It is well-settled that a contractor is charged with knowledge of the conditions that a pre-bid site visit would have revealed.” H.B. Mac, Inc. v. United States, 153 F.3d 1338, 1346 (Fed.Cir.1998). At the pre-bid site inspection, the bidders toured the project areas to be excavated, including residential areas likely to have many underground obstructions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Folliard v. Insight Enterprises, Inc.
District of Columbia, 2013
United States v. Govplace
930 F. Supp. 2d 123 (District of Columbia, 2013)
US Ex Rel. Ervin and Assoc. v. Hamilton SEC.
370 F. Supp. 2d 18 (District of Columbia, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
45 F. App'x 907, 45 Fed. Appx. 907, 2002 U.S. App. LEXIS 16595, 2002 WL 1890798, Counsel Stack Legal Research, https://law.counselstack.com/opinion/larry-d-barnes-inc-v-united-states-cafc-2002.