Blake Construction Co. v. United States

597 F.2d 1357, 26 Cont. Cas. Fed. 83,219, 220 Ct. Cl. 56, 1979 U.S. Ct. Cl. LEXIS 128
CourtUnited States Court of Claims
DecidedApril 18, 1979
DocketNo. 475-76
StatusPublished
Cited by13 cases

This text of 597 F.2d 1357 (Blake Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blake Construction Co. v. United States, 597 F.2d 1357, 26 Cont. Cas. Fed. 83,219, 220 Ct. Cl. 56, 1979 U.S. Ct. Cl. LEXIS 128 (cc 1979).

Opinion

SMITH, Judge,

delivered the opinion of the court:

This case is before the court on the parties’ cross-motions for summary judgment, the trial judge having determined, under Rule 166(b), that the issues are limited to issues of law within the purview of section 2 of the Wunderlich Act, 41 U.S.C. § 322 (1976). After carefully reviewing the briefs and oral arguments presented by the parties, as well as the decision of the General Services Administration Board of Contract Appeals (board), we hold in favor of plaintiff.

I.

Blake Construction Company, Inc. (plaintiff), was the successful bidder on contract No. GS-03B-16644 for construction of the superstructure (Phase II) of the J. Edgar [58]*58Hoover (FBI) Building, Washington, D.C. Under this contract, awarded by the General Services Administration (GSA) on June 14, 1971, plaintiff was to supply the finish hardware for the structure, including the locksets which were to be installed on the doors of the FBI Building.

In March 1972, plaintiff, on behalf of its supplier,1 submitted a physical sample, the Falcon Lock Set No. 2520 HG 32D (Type 86E), to GSA for approval. However, defendant’s contracting officer determined that the Falcon lockset did not meet contract specifications as to fabrication; specifically, that the rose and knob of the lockset were of wrought fabrication instead of cast fabrication, as specified in paragraph 6.22 of the contract specifications.3 These objections were detailed in the contracting officer’s final decision letter of May 22, 1972.

Plaintiff thereupon submitted another lockset, the 763 Milan by Corbin, one of the samples listed in the contract specifications for trim design.4 This lockset, more expensive than the rejected Falcon lockset, was accepted by the contracting officer as meeting contract requirements, although it was ultimately discovered that the Corbin was also of wrought, not cast, fabrication.

Plaintiff filed a timely notice of appeal from the contracting officer’s decision letter and a complaint with the board, seeking payment to plaintiff and its supplier of an amount sufficient as an equitable adjustment to compensate them for the allegedly wrongful rejection of the Falcon lockset. Following a hearing, the board, on August 29, 1973, held that while the Falcon lockset met contract requirements with regard to appearance, it did not meet contract specifications with regard to fabrication.5 On November 19, 1976, plaintiff filed a petition in this court [59]*59seeking a reversal of the board’s decision and an order remanding the case to the board for determination of the appropriate equitable adjustment.

II.

The only issue in the case involves the interpretation6 of contract specification section 0870, "Finish Hardware.”7 Plaintiff contends that Interim Federal Specification FFH-00106b,8 incorporated by reference into the contract through paragraph 1.8 of section 0870 of the specifications and paragraph 17.1.1 of the General Conditions,9 allows the supplier the option of furnishing trims of wrought fabrication whenever cast fabrication is specified; that paragraph 6.2 of the contract specifications provides that, "[t]rim material shall be * * * of cast fabrication”; that nowhere in the contract has the Government amended, modified, or eliminated the option; and that, therefore, the board was wrong in holding that the trim material had to be of cast fabrication alone.

Defendant contends that the option, otherwise available under paragraph 3.2.3 of the interim federal specifications, could, under paragraph 17.1.1 of the General Conditions, be "modified or * * * otherwise provided in the specifications”;10 that paragraph 1.8 of the contract specifications11 referred to "modified requirements specified herein”; that paragraphs 6.2, 6.5, and 6.6 of the contract specifications12 called for cast fabrication; and that by specifying "cast fabrication,” the Government had effectively specified its option as to the selection of type of fabrication and had rendered the supplier’s option inoperative. Defendant’s position is that there is a "hierarchy” of specifications and that, in the event of a conflict, contract specifications "control” over federal specifications.13

[60]*60To accept defendant’s argument would be to assume that the act of "specifying” cast fabrication both triggers and eliminates the supplier’s option, for the option is not available except "[w]hen cast trims are specified”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Holland v. United States
74 Fed. Cl. 225 (Federal Claims, 2006)
Navcom Defense Electronics, Inc. v. England
53 F. App'x 897 (Federal Circuit, 2002)
Larry D. Barnes, Inc. v. United States
45 F. App'x 907 (Federal Circuit, 2002)
Apollo Sheet Metal, Inc. v. United States
44 Fed. Cl. 210 (Federal Claims, 1999)
Yankee Atomic Electric Co. v. United States
42 Cont. Cas. Fed. 77,396 (Federal Claims, 1998)
C. Sanchez and Son, Incorporated v. United States
6 F.3d 1539 (Federal Circuit, 1993)
Global Associates v. The United States
914 F.2d 271 (Federal Circuit, 1990)
Randallstown Plaza Associates v. United States
13 Cl. Ct. 703 (Court of Claims, 1987)
Cherry Hill Sand & Gravel Co. v. United States
33 Cont. Cas. Fed. 74,030 (Court of Claims, 1985)
Tennessee Valley Authority v. Exxon Nuclear Co.
570 F. Supp. 462 (E.D. Tennessee, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
597 F.2d 1357, 26 Cont. Cas. Fed. 83,219, 220 Ct. Cl. 56, 1979 U.S. Ct. Cl. LEXIS 128, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blake-construction-co-v-united-states-cc-1979.