Apollo Sheet Metal, Inc. v. United States

44 Fed. Cl. 210, 1999 U.S. Claims LEXIS 135, 1999 WL 398937
CourtUnited States Court of Federal Claims
DecidedJune 16, 1999
DocketNo. 98-719C
StatusPublished
Cited by4 cases

This text of 44 Fed. Cl. 210 (Apollo Sheet Metal, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Apollo Sheet Metal, Inc. v. United States, 44 Fed. Cl. 210, 1999 U.S. Claims LEXIS 135, 1999 WL 398937 (uscfc 1999).

Opinion

ORDER

MILLER, Judge.

This matter is before the court on defendant’s motion to dismiss. The issues under consideration are (1) whether certain maps drawn by the government and included within a permit application constitute design specifications, and (2) if so, whether an order of precedence clause negates the attendant implied warranty of suitability. Argument is deemed unnecessary.

FACTS

The following facts are not disputed. On June 26,1996, the U.S. Department of Interi- or’s Bureau of Reclamation (the “BOR”) awarded a contract to Apollo Sheet Metal, Inc. (“plaintiff’), for construction of the Stan-field Relift Pumping Plant. The purpose of the plant is to meet the irrigation needs of the Stanfield Irrigation District.

On July 15, 1996, the BOR directed plaintiff to proceed with construction of the facilities. The contract required plaintiff to remove and control water from the construction site and “handle all flows from natural drainage.” Although the BOR made no representation as to the precise amount of water that plaintiff might encounter, it did warn plaintiff about possible runoff due to precipitation, but specifically noted that the levels for both ground water and flows were usually lowest from November to February.

Once construction began, plaintiff laid a 24-inch diameter pipe to divert water from the construction site. On January 1, 1997, warm weather precipitated a snowmelt which, in turn, flooded the construction site causing significant damage. Plaintiff submitted a time * and material change order on January 2,1997, seeking to recoup the cost of repairs. After the BOR denied this request on January 21, 1997, plaintiff submitted a claim on May 16, 1997, to the contracting officer for $96,461.00, the cost to repair the damages from the January 1,1997 flood. On October 14, 1997, the contracting officer issued a final decision denying plaintiffs claim.

Plaintiff thereafter filed its complaint seeking to recover $96,461.00. Plaintiff alleges that it used the 24-inch pipe in accordance with the BOR’s design specifications. Plaintiff relied upon “drawings” produced by the BOR, which indicated that the pipes in question were to be 24 inches in diameter. As a result, plaintiff asserts that the BOR is liable [212]*212for damages due to its breach of an implied warranty of suitability.

Defendant agrees that if the drawings constituted design specifications, the BOR would be liable. However, because “conceptual drawing[s]” were involved, Defs Br. filed Jan. 26, 1999, at 4, 13, plaintiff was not required to perform in compliance with the information included in the drawings. According to defendant, a controlling performance specification gave plaintiff full discretion to select the pipe’s size; cpnsequently, the BOR bears no responsibility for the pipe’s inadequacy.

DISCUSSION

1. Standards for motion to dismiss

RCFC 12(b)(4) governing motions to dismiss for failure to state a claim upon which relief can be granted authorizes dismissal when, despite the truth of plaintiffs allegations, no claim for which relief may be granted remains as a matter of law. Accordingly, the Supreme Court has held that dismissal is appropriate whenever “it appears beyond doubt that the plaintiff can prove no set of facts in support of his claim which would entitle him to relief.” Scheuer v. Rhodes, 416 U.S. 232, 236, 94 S.Ct. 1683, 40 L.Ed.2d 90 (1974). The court shall make all reasonable inferences in favor 'of the nonmoving party. See Gould, Inc. v. United States, 935 F.2d 1271, 1274 (Fed.Cir.1991) (holding that with motions to dismiss, court “must ... indulge in all reasonable inferences in favor of the nonmovant”). Any favorable inferences made, however, are to be based solely upon allegations of fact and not conclusions or opinions of law. The movant thus bears a heavy burden in showing that plaintiffs claim lacks any merit.

2. The drawings as design specifications

The Clean Water Act, 33 U.S.C. § 403 (1994), provides that “[t]he creation of any obstruction ... to the navigable capacity of any of the waters of the United States is prohibited ... except on plans recommended by the Chief of Engineers and authorized by the Secretary of the Army ... prior to beginning the same.” The Secretary of the Army authorizes such projects by issuing a permit. See 33 U.S.C. § 404 (1994). The BOR assumed the responsibility of applying for and acquiring all necessary licenses and permits. Included in the BOR’s permit application were two drawings indicating that a 24-inch pipe was to be used to “dewater” the construction site. A permit subsequently was granted as a result of this application.

In constructing the dewatering system, plaintiff maintains that it relied upon the permit application drawings to install the 24-inch diameter pipe, because it believed the drawings to be design specifications. Design specifications “describe in precise detail the materials to be employed and the manner in which the work is to be performed. They afford no discretion to the contractor, which is required to follow them as one would a roadmap.” Blake Constr. Co., Inc. v. United States, 987 F.2d 743, 745 (Fed.Cir.1993) (quoting J.L. Simmons Co. v. United States, 188 Ct.Cl. 684, 689, 412 F.2d 1360, 1362 (1969)). In contrast, performance specifications “set forth an objective or standard to be achieved [by the contractor who is] expected to exercise his ingenuity in achieving that objective or standard of performance, selecting the means and assuming a corresponding responsibility for that selection.” Blake Constr., 987 F.2d at 745 (internal quotations and citations omitted). If the drawings are deemed to be design specifications, then liability for any inherent defect in design would rest with the BOR. See Stuyvesant Dredging Co. v. United States, 834 F.2d 1576, 1582 (Fed.Cir.1987) (citing United States v. Spearin, 248 U.S. 132, 54 Ct.Cl. 187, 39 S.Ct. 59, 63 L.Ed. 166 (1918)). If, however, the drawings were merely performance specifications, then plaintiff assumed the risk for the 24-inch pipe. See Blake Constr., 987 F.2d at 745 (citing J.L. Simmons, 188 Ct.Cl. at 689, 412 F.2d at 1362).

To determine whether a specification is a design specification or a performance specification, the court is to look to “the obligations imposed by the specification.” Dillingham Construction, N.A., Inc. v. United States, 33 Fed.Cl. 495, 501 (citing Blake Constr., 987 F.2d at 746), aff'd, 91 F.3d 167 (Fed.Cir.1996) (Table). In Dillingham the [213]*213Veterans Administration contracted for the design and construction of an outpatient clinic.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

West Bay Builders, Inc. v. United States
85 Fed. Cl. 1 (Federal Claims, 2008)
Manuel Bros. v. United States
55 Fed. Cl. 8 (Federal Claims, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
44 Fed. Cl. 210, 1999 U.S. Claims LEXIS 135, 1999 WL 398937, Counsel Stack Legal Research, https://law.counselstack.com/opinion/apollo-sheet-metal-inc-v-united-states-uscfc-1999.