McCarthy v. United States

670 F.2d 996, 229 Ct. Cl. 361, 1982 U.S. Ct. Cl. LEXIS 29
CourtUnited States Court of Claims
DecidedJanuary 27, 1982
DocketNo. 235-76
StatusPublished
Cited by33 cases

This text of 670 F.2d 996 (McCarthy v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCarthy v. United States, 670 F.2d 996, 229 Ct. Cl. 361, 1982 U.S. Ct. Cl. LEXIS 29 (cc 1982).

Opinions

PER CURIAM:

This case comes before the court on defendant’s exceptions to the opinion, findings, and conclusion of law of Trial Judge Hogenson, submitted by him after trial in accordance with Rule 134(h). The exceptions to the fact findings and proposed substitute findings are all overruled as either irrelevant or contrary to the evidence. [363]*363Upon consideration of the briefs and oral argument, the court agrees with the trial judge that the court has jurisdiction and the defense and counterclaim of fraud were not sustained by the evidence. Defendant’s fraud case was that certain evidence offered by plaintiff to the arbitrators was false and fraudulent. Contrary to defendant’s present argument, the trial judge understood this and did not suppose the fraud was in any other context. Therefore, we adopt the opinion, findings, and conclusion of law as our own, with some modifications in the opinion as the basis for our judgment. Plaintiff is entitled to recover and judgment is entered for plaintiff in the amount of $495,898.45 plus 75 percent of the costs of arbitration. Defendant’s counterclaim is dismissed. The findings are not printed as they have been furnished to the parties. The opinion of Trial Judge Hogenson, as modified follows:

HOGENSON, Trial Judge:

Plaintiff, a corporation organized under the laws of the Republic of Senegal, brought this suit to recover on an arbitration award, thereafter amending its petition for a money judgment pursuant to an order of the court. The arbitration proceedings had been instituted according to the terms of a contract between plaintiff and the defendant’s Agency for International Development in an attempt to resolve a dispute arising under that contract.

In March 1965 two American businessmen, Robert F. Lusher and Ezra Cornell IV, traveled to Senegal with an official of the Agency for International Development (AID) for the purpose of determining whether it would be feasible to construct a large housing project there under an investment guaranty program administered by AID. After deciding that the project could be constructed in Dakar, Lusher organized a Delaware corporation, Builders International, Inc. (Builders Delaware), as the vehicle for conducting the initial preparations.1

In 1967 Lusher and Cornell organized a Senegalese corporation, Builders International (Senegal) S.A., (Build[364]*364ers), with nominal capital to carry on the actual construction of the project.

The housing project, know as "Patte d’Oie,” was planned to include approximately 800 units as well as a sewage treatment plant, roads, and electrical and water distribution systems. The project was planned, financed, and constructed according to the conditions of a program administered by AID pursuant to the Foreign Assistance Act of 1961. Under this program AID would guaranty loans made by private investors who agreed to provide permanent financing to Senegalese citizens who purchased the houses Builders constructed. Builders in turn would give AID the right of approval over the plans and specifications of the project. Builders would secure its own construction loans.

As part of the application for the program, Builders submitted detailed cost estimates for the project in 1967 and 1968. These estimates contained a breakdown of the items used in constructing the several types of houses and indicated the quantity of items needed, the unit price, and the total price. After AID approved the project, Builders entered into contracts with AID and with third parties to provide for the financing and construction of the project. In this case two insurance companies, the investors, agreed to provide Builders with up to $5 million in guaranteed loans to finance the project. In return, AID entered into a "Contract of Guaranty” with the investors under which AID obligated itself to repay any losses incurred by the investors on their loans to Builders. In addition, on June 1, 1968, Builders Senegal and the Government of Senegal entered into a separate contract with AID known as the "Company Agreement,” which gave AID control over certain of the financial and planning decisions pertaining to the project. Pursuant to this agreement, Builders could not increase the sales prices without AID’s prior approval and AID reserved the right to approve the plans and specifications of the houses, as well as the time at which Builders could commence construction. The agreement further provided that AID would be obliged to consider requests to increase the sale prices of the houses only in certain circumstances. If AID were to require changes in [365]*365the construction plans, however, Builders would be entitled to reflect any consequent cost increases in the selling prices. In the event that any dispute relating to the agreement were to arise, the parties agreed to resolve it through arbitration.

On June 20,1968, Builders engaged Enterprises Generale du Cap Vert de Travaux Publics et Particuliers Batiments (EGCAP) to be the general contractor for the Patte d’Oie Project. The contract documents included several "devis estimatifs” prepared by EGCAP, which were cost breakdowns of the total house price into items of construction. Each item listed in the devis estimatifs was accompanied by a stated unit of measurement, a unit price, quantity, and total price. The total cost of construction for a B-3 house in the 1968 devis estimatif was subsequently reduced in reaching the contract price.2

EGCAP commenced initial operations to clear the site that same month and began constructing the houses in late November or early December 1968. In constructing the individual houses, Builders employed a method known as a steel-frame system. This method involved the use of steel trusses and steel laths to form a frame to which cement or plaster could be applied. AID approved the use of this system in the project although the Federal Housing Authority (FHA) had informed AID earlier that it had some reservations about the system. Sometime before the actual construction began Builders received word from FHA that a contractor employing a method similar to the steel-frame system on a project in Puerto Rico had experienced some difficulties with it. On the basis of this report AID subsequently decided to review the use of the steel-frame system by Builders. In December 1968 two officials from FHA went to Dakar to evaluate the steel-frame system. These officials informed Builders that a number of changes would have to be made in the plans and specifications of the project and, in addition, recommended to AID that Builders be required to switch from the steel-frame system to a conventional method of construction.

[366]*366At this time Builders had made substantial progress on the construction of the 26 houses that comprised the first section of the project but had done only preliminary work on the other sections. On December 23, 1968, officials of AID met at their Washington office with Mr. Harrison Chapman, Builders’ construction consultant, and informed him that Builders could no longer use the steel-frame system on the Patte d’Oie Project. By letter dated January 8, 1969, Mr. George Hazel of AID ordered Builders to change to a conventional method of construction for all but the first 26 units in the project. As a result of this order, Builders was forced to halt construction after completing the first section of houses.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Parsons Evergreene, LLC v. Secretary of the Air Force
968 F.3d 1359 (Federal Circuit, 2020)
Horn & Associates, Inc. v. United States
123 Fed. Cl. 728 (Federal Claims, 2015)
Hernandez, Kroone and Associates, Inc. v. United States
110 Fed. Cl. 496 (Federal Claims, 2013)
Slattery v. United States
635 F.3d 1298 (Federal Circuit, 2011)
Daewoo Engineering & Construction Co. v. United States
73 Fed. Cl. 547 (Federal Claims, 2006)
American Heritage Bancorp v. United States
61 Fed. Cl. 376 (Federal Claims, 2004)
Long Island Savings Bank, FSB v. United States
54 Fed. Cl. 607 (Federal Claims, 2002)
Slattery v. United States
53 Fed. Cl. 258 (Federal Claims, 2002)
Larry D. Barnes, Inc. v. United States
45 F. App'x 907 (Federal Circuit, 2002)
Ains, Inc. v. United States
56 Fed. Cl. 522 (Federal Claims, 2002)
Furash & Company v. United States
252 F.3d 1336 (Federal Circuit, 2001)
Crane Helicopter Services, Inc. v. United States
45 Fed. Cl. 410 (Federal Claims, 1999)
UMC Electronics Co. v. United States
43 Fed. Cl. 776 (Federal Claims, 1999)
Commercial Contractors, Inc. v. United States
154 F.3d 1357 (Federal Circuit, 1998)
Supermex, Inc. v. United States
40 Cont. Cas. Fed. 76,897 (Federal Claims, 1996)
Young-Montenay, Inc. v. United States
15 F.3d 1040 (Federal Circuit, 1994)
Sterling Millwrights, Inc. v. United States
38 Cont. Cas. Fed. 76,316 (Court of Claims, 1992)
Colorado State Bank of Walsh v. United States
18 Cl. Ct. 611 (Court of Claims, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
670 F.2d 996, 229 Ct. Cl. 361, 1982 U.S. Ct. Cl. LEXIS 29, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccarthy-v-united-states-cc-1982.