Parsons Evergreene, LLC v. Secretary of the Air Force

968 F.3d 1359
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 7, 2020
Docket19-1931
StatusPublished
Cited by10 cases

This text of 968 F.3d 1359 (Parsons Evergreene, LLC v. Secretary of the Air Force) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parsons Evergreene, LLC v. Secretary of the Air Force, 968 F.3d 1359 (Fed. Cir. 2020).

Opinion

Case: 19-1931 Document: 58 Page: 1 Filed: 08/07/2020

United States Court of Appeals for the Federal Circuit ______________________

PARSONS EVERGREENE, LLC, Appellant

v.

SECRETARY OF THE AIR FORCE, Cross-Appellant ______________________

2019-1931, 2019-1975 ______________________

Appeals from the Armed Services Board of Contract Appeals in Nos. 58634, 61784, Administrative Judge J. Reid Prouty, Administrative Judge Craig S. Clarke, Ad- ministrative Judge Richard Shackleford. ______________________

Decided: August 7, 2020 ______________________

CAMERON HAMRICK, Miles & Stockbridge PC, Washing- ton, DC, argued for appellant. Also represented by RAYMOND MONROE.

ROBERT R. KIEPURA, Commercial Litigation Branch, Civil Division, United States Department of Justice, Wash- ington, DC, argued for cross-appellant. Also represented by ETHAN P. DAVIS, STEVEN JOHN GILLINGHAM, ROBERT EDWARD KIRSCHMAN, JR.; LORI R. SHAPIRO, Office of Gen- eral Counsel, United States General Services Administra- tion, Washington, DC. Case: 19-1931 Document: 58 Page: 2 Filed: 08/07/2020

______________________

Before DYK, CLEVENGER, and HUGHES, Circuit Judges. DYK, Circuit Judge. Parsons Evergreene, LLC (“Parsons”) appeals from two decisions by the Armed Services Board of Contract Appeals (“Board”). The Board granted in part and denied in part Parsons’ claims for equitable adjustment on a contract for the design and construction of two buildings at McGuire Air Force Base. The government cross-appeals, contending that the Board lacked jurisdiction; that we lack jurisdiction in part; and, on the merits, that the Board erroneously re- quired it to disprove the reasonableness of Parsons’ claimed costs. We affirm in part, reverse in part, dismiss in part, and remand. BACKGROUND On December 12, 2003, the government awarded Par- sons a $2.1 billion indefinite-delivery, indefinite-quantity contract (“Contract”) for planning and construction work. 1 The work was to be described in subsequent task orders. On July 13, 2005, the government issued a $34 million task order (“Task Order”) under the Contract to complete an ex- isting, concept-level design and construct two facilities, known as the Temporary Lodging Facility and the Visiting Quarters, at the McGuire Air Force Base in New Jersey. The Temporary Lodging Facility was to be a 50-unit tran- sitional housing facility for use by military and civilian per- sonnel. The Visiting Quarters was to be a 175-unit facility similar to a hotel with individual rooms and private bath- rooms. Design and construction were completed, and the

1 The contract was originally awarded to Parsons In- frastructure and Technology Group Inc. The contract was transferred to Parsons via novation on September 7, 2004. Case: 19-1931 Document: 58 Page: 3 Filed: 08/07/2020

PARSONS EVERGREENE, LLC v. SECRETARY OF THE AIR FORCE 3

U.S. Department of the Air Force (“Air Force”) accepted the completed facilities for “beneficial use” on September 11, 2008. J.A. 96. On June 29, 2012, Parsons submitted a claim to the Air Force seeking approximately $34 million in additional costs that Parsons allegedly incurred in the design and con- struction process. The contracting officer issued a final de- cision on March 27, 2013 almost entirely denying Parsons’ claim, which Parsons appealed to the Board under the Con- tract Disputes Act (“CDA”). In separate decisions in ASBCA Nos. 58634 and 61784, the Board denied in part and sustained in part Parsons’ claim, awarding Parsons about $10.5 million plus interest. Parsons appeals. The government cross-appeals, con- tending that the Board lacked jurisdiction; that we lack ju- risdiction in ASBCA No. 61784; and that on the merits the Board erroneously required it to disprove the reasonable- ness of Parsons’ claimed costs. We review the Board’s legal conclusions de novo and its factfinding for substantial evi- dence. 41 U.S.C. § 7107(b). DISCUSSION I At the outset, we must resolve a jurisdictional chal- lenge. The government contends that the Board lacked CDA jurisdiction over this case. We disagree. The CDA provides a process for dispute resolution of certain contract claims against the government. As rele- vant here, the CDA applies to contracts “made by an exec- utive agency” for “the procurement of services” or “the procurement of construction . . . of real property.” 41 U.S.C. § 7102(a)(1), (3). Claims by contractors are first submitted to a contracting officer, who issues a decision on the claim. 41 U.S.C. § 7103(a)(1), (d). The contractor may appeal the contracting officer’s decision to a Board of Case: 19-1931 Document: 58 Page: 4 Filed: 08/07/2020

Contract Appeals. Id. § 7104(a). The Board’s decision may, in turn, be appealed to this court. Id. § 7107(a)(1). A The government first contends that the Board lacked jurisdiction under the so-called “NAFI doctrine.” The Board concluded that it had jurisdiction because the NAFI doctrine had been abrogated by this court’s decision in Slattery v. United States, 635 F.3d 1298 (Fed. Cir. 2011) (en banc). Beginning in the late 1960s, our predecessor court held in a line of cases that neither the Court of Federal Claims (“Claims Court”) nor the Boards of Contract Appeals had jurisdiction over contract disputes with nonappropriated fund instrumentalities (“NAFIs”). Kyer v. United States, 369 F.2d 714 (Ct. Cl. 1966). “A ‘nonappropriated fund in- strumentality’ is one which does not receive its monies by congressional appropriation.” United States v. Hopkins, 427 U.S. 123, 125 n.2 (1976). As relevant to Board juris- diction, these cases construed the phrase “executive agency” in the CDA to exclude contracts made by NAFIs. See, e.g., Furash & Co. v. United States, 252 F.3d 1336, 1343 (Fed. Cir. 2001); Strand Hunt Const., Inc. v. West, 111 F.3d 142 (Fed. Cir. 1997) (unpublished table decision). As to Claims Court jurisdiction, these cases construe the Tucker Act’s authorization of suits against “the United States” to exclude NAFIs. See 28 U.S.C. § 1491(a)(1); Kyer, 369 F.2d at 719 . In 2011, in our en banc decision in Slattery, we held that the Claims Court had Tucker Act jurisdiction over a dispute between a contractor and the Federal Deposit In- surance Corporation (“FIDC”), even though the FDIC was a NAFI. 635 F.3d at 1310, 1314. In so holding, we abro- gated the NAFI doctrine for Tucker Act claims. Id. at 1321. We have not yet decided whether Slattery also abrogated the NAFI doctrine for CDA disputes appealed to a Board of Case: 19-1931 Document: 58 Page: 5 Filed: 08/07/2020

PARSONS EVERGREENE, LLC v. SECRETARY OF THE AIR FORCE 5

Contract Appeals. We expressly reserved that the question in one later case. See Minesen Co. v. McHugh, 671 F.3d 1332, 1337 (Fed. Cir. 2012). The government asserts that the Board lacked CDA ju- risdiction under the NAFI doctrine. It points out that the Board found that the Task Order was made by the Air Force Services Agency (“AFSVA”), a NAFI.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ECC International Constructors, LLC
Armed Services Board of Contract Appeals, 2025
AICI-Archirodon JV
Armed Services Board of Contract Appeals, 2025
Lockheed Martin Aeronautics Company
Armed Services Board of Contract Appeals, 2024
Amatea/Grimberg JV
Armed Services Board of Contract Appeals, 2023
GSC Construction, Inc.
Armed Services Board of Contract Appeals, 2020

Cite This Page — Counsel Stack

Bluebook (online)
968 F.3d 1359, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parsons-evergreene-llc-v-secretary-of-the-air-force-cafc-2020.