Parsons Evergreene, LLC v. Secretary of the Air Force

968 F.3d 1359
Court of Appeals for the Federal Circuit·Decided August 7, 2020·No. 19-1931·Published·Cited by 10 cases

Opinion

United States Court of Appeals for the Federal Circuit

PARSONS EVERGREENE, LLC, Appellant

v.

SECRETARY OF THE AIR FORCE, Cross-Appellant

2019-1931, 2019-1975

Appeals from the Armed Services Board of Contract Appeals in Nos. 58634, 61784, Administrative Judge J. Reid Prouty, Administrative Judge Craig S. Clarke, Administrative Judge Richard Shackleford.

Decided: August 7, 2020

CAMERON HAMRICK, Miles & Stockbridge PC, Washington , DC, argued for appellant. Also represented by RAYMOND MONROE.

ROBERT R. KIEPURA, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington , DC, argued for cross-appellant. Also represented by ETHAN P. DAVIS, STEVEN JOHN GILLINGHAM, ROBERT EDWARD KIRSCHMAN, JR.; LORI R. SHAPIRO, Office of General Counsel, United States General Services Administration , Washington, DC.

2 PARSONS EVERGREENE, LLC v. SECRETARY OF THE AIR FORCE

Before DYK, CLEVENGER, and HUGHES, Circuit Judges.

DYK, Circuit Judge.

Parsons Evergreene, LLC (“Parsons”) appeals from two decisions by the Armed Services Board of Contract Appeals (“Board”). The Board granted in part and denied in part Parsons’ claims for equitable adjustment on a contract for the design and construction of two buildings at McGuire Air Force Base. The government cross-appeals, contending that the Board lacked jurisdiction; that we lack jurisdiction in part; and, on the merits, that the Board erroneously required it to disprove the reasonableness of Parsons’ claimed costs. We affirm in part, reverse in part, dismiss in part, and remand.

BACKGROUND On December 12, 2003, the government awarded Parsons a $2.1 billion indefinite-delivery, indefinite-quantity contract (“Contract”) for planning and construction work. 1 The work was to be described in subsequent task orders. On July 13, 2005, the government issued a $34 million task order (“Task Order”) under the Contract to complete an existing , concept-level design and construct two facilities, known as the Temporary Lodging Facility and the Visiting Quarters, at the McGuire Air Force Base in New Jersey. The Temporary Lodging Facility was to be a 50-unit transitional housing facility for use by military and civilian personnel . The Visiting Quarters was to be a 175-unit facility similar to a hotel with individual rooms and private bathrooms . Design and construction were completed, and the

1 The contract was originally awarded to Parsons Infrastructure and Technology Group Inc. The contract was transferred to Parsons via novation on September 7, 2004.

PARSONS EVERGREENE, LLC v. SECRETARY OF THE AIR FORCE 3

U.S. Department of the Air Force (“Air Force”) accepted the completed facilities for “beneficial use” on September 11, 2008. J.A. 96.

On June 29, 2012, Parsons submitted a claim to the Air Force seeking approximately $34 million in additional costs that Parsons allegedly incurred in the design and construction process. The contracting officer issued a final decision on March 27, 2013 almost entirely denying Parsons’ claim, which Parsons appealed to the Board under the Contract Disputes Act (“CDA”). In separate decisions in ASBCA Nos. 58634 and 61784, the Board denied in part and sustained in part Parsons’ claim, awarding Parsons about $10.5 million plus interest.

Parsons appeals. The government cross-appeals, contending that the Board lacked jurisdiction; that we lack jurisdiction in ASBCA No. 61784; and that on the merits the Board erroneously required it to disprove the reasonableness of Parsons’ claimed costs. We review the Board’s legal conclusions de novo and its factfinding for substantial evidence . 41 U.S.C. § 7107(b).

DISCUSSION

I

At the outset, we must resolve a jurisdictional challenge . The government contends that the Board lacked CDA jurisdiction over this case. We disagree.

The CDA provides a process for dispute resolution of certain contract claims against the government. As relevant here, the CDA applies to contracts “made by an executive agency” for “the procurement of services” or “the procurement of construction . . . of real property.” 41 U.S.C. § 7102(a)(1), (3). Claims by contractors are first submitted to a contracting officer, who issues a decision on the claim. 41 U.S.C. § 7103(a)(1), (d). The contractor may appeal the contracting officer’s decision to a Board of 4 PARSONS EVERGREENE, LLC v. SECRETARY OF THE AIR FORCE

Contract Appeals. Id. § 7104(a). The Board’s decision may, in turn, be appealed to this court. Id. § 7107(a)(1).

A

The government first contends that the Board lacked jurisdiction under the so-called “NAFI doctrine.” The Board concluded that it had jurisdiction because the NAFI doctrine had been abrogated by this court’s decision in Slattery v. United States, 635 F.3d 1298 (Fed. Cir. 2011) (en banc).

Beginning in the late 1960s, our predecessor court held in a line of cases that neither the Court of Federal Claims (“Claims Court”) nor the Boards of Contract Appeals had jurisdiction over contract disputes with nonappropriated fund instrumentalities (“NAFIs”). Kyer v. United States, 369 F.2d 714 (Ct. Cl. 1966). “A ‘nonappropriated fund instrumentality ’ is one which does not receive its monies by congressional appropriation.” United States v. Hopkins, 427 U.S. 123, 125 n.2 (1976). As relevant to Board jurisdiction , these cases construed the phrase “executive agency” in the CDA to exclude contracts made by NAFIs. See, e.g., Furash & Co. v. United States, 252 F.3d 1336, 1343 (Fed. Cir. 2001); Strand Hunt Const., Inc. v. West, 111 F.3d 142 (Fed. Cir. 1997) (unpublished table decision). As to Claims Court jurisdiction, these cases construe the Tucker Act’s authorization of suits against “the United States” to exclude NAFIs. See 28 U.S.C. § 1491(a)(1); Kyer, 369 F.2d at 719 .

In 2011, in our en banc decision in Slattery, we held that the Claims Court had Tucker Act jurisdiction over a dispute between a contractor and the Federal Deposit Insurance Corporation (“FIDC”), even though the FDIC was a NAFI. 635 F.3d at 1310, 1314. In so holding, we abrogated the NAFI doctrine for Tucker Act claims. Id. at 1321. We have not yet decided whether Slattery also abrogated the NAFI doctrine for CDA disputes appealed to a Board of

PARSONS EVERGREENE, LLC v. SECRETARY OF THE AIR FORCE 5

Contract Appeals. We expressly reserved that the question in one later case. See Minesen Co. v. McHugh, 671 F.3d 1332, 1337 (Fed. Cir. 2012).

The government asserts that the Board lacked CDA jurisdiction under the NAFI doctrine. It points out that the Board found that the Task Order was made by the Air Force Services Agency (“AFSVA”), a NAFI. We need not decide the current status of the NAFI doctrine as applied to the Boards of Contract Appeals because, even under pre- Slattery precedent, the dispute here would not be barred. Contrary to the Board’s finding, the contract is not a NAFI contract.

The contracting documents show that the Task Order was made by the Air Force and not by the AFSVA. The Contract on which the Task Order is based was “Issued By” the “Air Force Materiel Command” (“AFMC”), a part of the Air Force that the government admits is not a NAFI, and was to be “Administered By” the “Department of the Air Force.” J.A. 733. The request for proposal (“RFP”) that led to the Task Order uses “Department of the Air Force” letterhead and states that “[t]he USAF intends to issue a competitive [Task Order].” J.A. 4823 (emphasis added). The Task Order, like the Contract, was “Issued By” the “Air Force Materiel Command” and “Administered By” the “Department of The Air Force.” J.A. 798. The contracting officer who signed the Task Order was from the AFMC. The government has not identified any mention of the AFSVA or any other NAFI in either the Contract or the Task Order.

Free access — add to your briefcase to read the full text and ask questions with AI

Parsons Evergreene, LLC v. Secretary of the Air Force, 968 F.3d 1359 (Fed. Cir. 2020).

968 F.3d 1359 (Parsons Evergreene, LLC v. Secretary of the Air Force) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Al Ghanim Combined Group W.L.L.
Armed Services Board of Contract Appeals, 2026
ECC International Constructors, LLC
Armed Services Board of Contract Appeals, 2025
AICI-Archirodon JV
Armed Services Board of Contract Appeals, 2025
Lockheed Martin Aeronautics Company
Armed Services Board of Contract Appeals, 2024
Amatea/Grimberg JV
Armed Services Board of Contract Appeals, 2023
GSC Construction, Inc.
Armed Services Board of Contract Appeals, 2020