Amatea/Grimberg JV

CourtArmed Services Board of Contract Appeals
DecidedMay 30, 2023
Docket60426, 60427, 60428, 60689, 60690, 60691, 61252, 61402, 61715
StatusPublished

This text of Amatea/Grimberg JV (Amatea/Grimberg JV) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Amatea/Grimberg JV, (asbca 2023).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) Amatea/Grimberg JV ) ASBCA Nos. 60426, 60427, 60428 ) 60689, 60690, 60691 ) 61252, 61402, 61715 ) Under Contract No. N40080-09-C-0171 )

APPEARANCES FOR THE APPELLANT: Stephen H. Swart, Esq. Arnie B. Mason, Esq. Melisa A. Roy, Esq. Williams Mullen Tysons Corner, VA

APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq. Navy Chief Trial Attorney Joshua S. Kauke, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE PROUTY

These nine appeals, brought pursuant to Board Rule 11, stem from disputes over the performance of a design/build construction contract (the contract) to erect a laboratory building for the Engineering Directorate of the Naval Surface Warfare Center located at Indian Head, Maryland. Many things went wrong during the pendency of the project, beginning with poor site conditions that required remediation, and including disputes over the partial re-design of the fire sprinkler system and who was responsible for the installation of an electronic security system. Appellant, the Amatea/Grimberg Joint Venture (AGJV or the joint venture) maintains that respondent, the United States Navy (the Navy), only made things worse by the contentious manner in which it administered the contract: unreasonably refusing to allow AGJV to work on nights and weekends and wrongfully refusing to extend the project completion date, therefore requiring AGJV to incur the additional expenses that followed from accelerating its work. The joint venture also argues that the Navy’s imposition of liquidated damages for the late completion of the project was unjust, given the Navy’s supposed responsibility for the delays and the Navy’s use of an unreasonable beneficial occupancy date.

As will be explained below, the Navy largely—but not completely—prevails here. The conditions at the site, though an absolute mess after AGJV began working on it, were not inconsistent with what could have been anticipated from the information provided by the Navy with the solicitation and were somewhat AGJV’s fault. Moreover, the contracting officer’s (CO’s) decision not to afford AGJV the opportunity for night and weekend work was not a breach of the duty of good faith and fair dealing as the Navy had sufficient reasons to deny the request to make its exercise of discretion reasonable. On the other hand, the Navy does owe AGJV additional money for the fire sprinkler system (not as much as AGJV claims) and for the electronic security system which was required by the contract but was not completely paid for by the Navy. Additionally, the Navy should have found the building ready for beneficial occupancy at an earlier date than it did, which leads to lower liquidated damages due the government. Finally, we find the acceleration claims to be unsupported.

FINDINGS OF FACT

I. The Contract

The contract to erect the laboratory building that is the subject of this dispute (the lab building) was a design/build contract that was awarded as a competitive small business set-aside. The procurement was done in two phases: in the first phase, the Navy basically selected a small number of contractors that (based on the solicitation criteria) were suited to perform the work. In the second phase, those contractors selected in the first phase responded to the solicitation for the project and were judged upon that response. (See generally, R4, tab 1) AGJV was one of the three teams that were selected by the first phase of the procurement and were invited to participate in the second phase by responding to the solicitation (R4, tab 3 at GOV 35). 1

On July 10, 2009, the government issued the request for proposals (RFP) (R4, tab 3 at GOV 32) 2. The RFP included various contract line items, and provided that the work to be performed under each line item was delineated in the

1 The government has placed Bates numbers at the bottom of the pages of its Rule 4 file, beginning with the descriptor “GOV_ORIG_R4_” after which follows a seven-digit number, beginning with zeroes. For greater ease of use, we replace this with “GOV ___” in which the seven-digit number is replaced by only the digits actually used. Thus, for example, we replace GOV ORIG-R4 0000005 with GOV 5. We similarly curtail appellant’s Bates numbers to “APP __” followed by only the digits actually used. 2 The solicitation is at tab 3 of the Rule 4 file, while the executed contract, which incorporates some portions of the solicitation (as noted below), is at tab 24. Throughout the remainder of this opinion, we generally cite the solicitation document at tab 24, since that is associated with the executed contract.

2 RFP’s technical specifications and drawings, which were organized into “parts” (id. at GOV 37-38; R4, tabs 4-9).

On September 30, 2009, AGJV was awarded the contract to build the lab building along with several related line items from the solicitation. The contract was in the amount of $10,574,419, with a contract completion date of March 31, 2011. (R4, tab 24 at GOV 1153) Of relevance here, the contract incorporated the RFP’s Price Schedule and the specifications and drawings (R4, tab 24 at GOV 1155). 3

The contract included the standard liquidated damages clause found in the Federal Acquisition Regulation (FAR) at section 52.211-12 Liquidated Damages – Construction (SEP 2000), which, modified to insert a specific dollar figure, provided in part that: “[i]f the Contractor fails to complete the work within the time specified by the contract, the Contractor shall pay liquidated damages to the government in the amount of $5,250 for each calendar day of delay until the work is completed or accepted” (R4, tab 24 at GOV 1190).

II. Early Contract Extensions

On May 3, 2010, the parties agreed to add a number of enhancements to the building to increase its energy efficiency. By bilateral 4 contract Modification No. A00001 (Mod 1), AGJV agreed to make the various energy efficiency enhancements to the building for an additional $1,040,783 (raising the contract price to $11,615,202) and a 90-day extension to the contract completion date, which would now be June 29, 2011. (R4, tab 26 at GOV 1218) This modification was followed within a few days by Modification No. A00003 (Mod 3). Mod 3 was another bilateral 5 contract modification. This one, extending the time for performance by 224 days, until February 8, 2012, in recognition of delays in the FY09 Demolition and Footprint Reduction Program which would have affected the construction site. This was a

3 Although these portions of the RFP were incorporated into the contract, the parties, throughout performance and during this litigation, generally continued to refer to them as RFP provisions, not contract provisions. For consistency, we adopt the parties’ terminology. 4 The copy of Mod 1 in the government-provided Rule 4 file is signed by the government, but not by AGJV (see R4, tab 26). Since AGJV does not raise an argument over this, we will presume that it was, in fact, a bilateral modification and that the Navy was either sloppy in obtaining AGJV’s signature after forwarding the modification to AGJV or in its records-keeping. This is an all-too-common problem. See, e.g., Metro Machine d/b/a General Dynamics NASSCO-Norfolk, ASBCA No. 62221, 22-1 BCA ¶ 38,096 at 185,002 n.5. 5 Yet again, with only the government’s signature present (see R4, tab 28 at GOV 1225).

3 no-cost modification, with the contract price remaining at $11,617,761. 6 (R4, tab 28 at GOV 1225)

AGJV characterizes these as “significant delays” for which the Navy admitted responsibility (app. br. at 2-3). This is true to the extent that the extension of the contract completion date by more than 10 months was certainly significant and also a matter of the Navy’s responsibility.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Precision Pine & Timber, Inc. v. United States
596 F.3d 817 (Federal Circuit, 2010)
International Technology Corp. v. Winter
523 F.3d 1341 (Federal Circuit, 2008)
Teg-Paradigm Environmental, Inc. v. United States
465 F.3d 1329 (Federal Circuit, 2006)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
John McShain, Inc. v. United States
375 F.2d 829 (Court of Claims, 1967)
Olympus Corporation v. United States
98 F.3d 1314 (Federal Circuit, 1996)
H.B. Mac, Inc. v. United States
153 F.3d 1338 (Federal Circuit, 1998)
Robins Maintenance, Inc. v. United States
265 F.3d 1254 (Federal Circuit, 2001)
Comtrol, Inc. v. United States
294 F.3d 1357 (Federal Circuit, 2002)
Barron Bancshares, Inc. v. United States
366 F.3d 1360 (Federal Circuit, 2004)
United States v. Ford Motor Company
463 F.3d 1267 (Federal Circuit, 2006)
bell/heery v. United States
739 F.3d 1324 (Federal Circuit, 2014)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
Lakeshore Engineering Services, Inc. v. United States
748 F.3d 1341 (Federal Circuit, 2014)
K-Con Building Systems, Inc. v. United States
778 F.3d 1000 (Federal Circuit, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Amatea/Grimberg JV, Counsel Stack Legal Research, https://law.counselstack.com/opinion/amateagrimberg-jv-asbca-2023.