Robins Maintenance, Inc. v. United States

265 F.3d 1254, 2001 U.S. App. LEXIS 20639, 2001 WL 1105133
CourtCourt of Appeals for the Federal Circuit
DecidedSeptember 20, 2001
Docket01-5010
StatusPublished
Cited by24 cases

This text of 265 F.3d 1254 (Robins Maintenance, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Robins Maintenance, Inc. v. United States, 265 F.3d 1254, 2001 U.S. App. LEXIS 20639, 2001 WL 1105133 (Fed. Cir. 2001).

Opinion

DYK, Circuit Judge.

This case involves a claim by Robins Maintenance, Inc. (“RMI”) for an equitable adjustment to a grounds maintenance contract with the Robins Air Force Base (“Robins AFB”) based on a theory of defective specifications. We conclude that the Court of Federal Claims properly granted the government’s motion for summary judgment because RMI’s knowledge of the errors in the specifications precluded recovery, and RMI abandoned all other claims not based on the defective specifications.

BACKGROUND

On April 30, 1992, the United States Air Force (“Air Force”) issued a request for proposals for a grounds maintenance contract at the Warner Robins Air Logistics Center at Robins AFB, Georgia. Initial bids were due on June 18, 1992; negotiations were to occur in early September 1992; and final offers were due on Novem *1256 ber 27, 1992. The contract was for a one-year base period with four annual option periods. RMI was the current contractor, and had performed grounds maintenance at Robins AFB since 1982.

The contract required that the successful bidder, RMI, “provide all personnel, equipment, tools, materials, supervision, and other items and services necessary to perform Grounds Maintenance ... at Robins AFB.” The bid document at the heart of the controversy was Technical Exhibit 2, which described the acreage and square footage of the base grounds, so that bidders could estimate the number of labor hours and costs associated with bidding on the contract. Technical Exhibit 2 identified 500 acres of “improved” grounds 1 and 13 acres of “enhanced” grounds 2 , instead of the correct acreage of 1152.06 and 29.51, respectively. The Exhibit specifically identified the figures as “estimates.” After Mr. Everett Dykes, Jr., RMI’s then-president, and Mr. William Dykes, RMI’s then-vice president and current president, attended a pre-proposal conference in late May 1992, they concluded that the previous maintenance contract and the new maintenance contract covered approximately the same area. At this point, appellant contends that Mr. Everett Dykes, Jr., informed the Air Force’s contracting officer, Ms. Betty Holley, that there were errors in Technical Exhibit 2. Allegedly, Ms. Holley told Mr. Dykes not to “start any trouble” and to proceed to bid on the solicitation as it was written.

RMI acknowledges that it was fully aware of the inaccurately low estimates in Technical Exhibit 2 at the time it bid on the contract. Furthermore, RMI knew the correct acreage based on the prior maintenance contract.

Despite the errors, RMI bid on and subsequently won the maintenance contract. From July 1,1993, until October 19, 1995, RMI performed the contract without seeking any adjustment for the inaccurate specifications. On October 19, 1995, RMI filed an uncertified equitable adjustment claim, which was later supplemented in December 1995. Five months later, on May 6, 1996, the Air Force and RMI agreed to modify the contract to indicate the correct acreage. The modification involved updating Technical Exhibit 2 and the corresponding maps included in Technical Exhibit 3, but did not change the amount that RMI was to receive for the work. On August 29, 1996, RMI filed a certified claim seeking an equitable adjustment of $5,239,130 for its additional work prior to the modification. The Air Force denied RMI’s certified claim on April 17, 1997.

In August 2000 the Court of Federal Claims granted the government’s motion for summary judgment, holding that an incumbent contractor, such as RMI, may not recover based on a defective specifications theory when it knew that the specifications were inaccurate. Robins Maintenance, Inc. v. United States, No. 97-488C, slip op. at 5 (Fed.Cl. Aug. 23, 2000). Furthermore, the court found that all of RMI’s claims were based on the defects in the specifications, and that any other claims had been abandoned. Id. RMI appealed. We have jurisdiction over this appeal pursuant to 28 U.S.C. § 1295(a)(3).

DISCUSSION

1. Standard of Review

Summary judgment is appropriate when “there is no genuine issue as to any mate *1257 rial fact and ... the moving party is entitled to a judgment as a matter of law.” Fed R. Civ. P. 56(c). We review a trial court’s grant of a motion for summary judgment without deference. Metric Con structors, Inc. v. Nat’l Aeronautics & Space Admin., 169 F.3d 747, 751 (Fed.Cir. 1999).

II. Contractor Knotvledge of Eirors in the Specifications

We conclude that the Court of Federal Claims properly granted the government’s motion for summary judgment because, even though RMI knew about the defects in the specifications, it nonetheless chose to submit a bid and agreed to the contract.

Whenever the government uses specifications in a contract, there is an accompanying implied warranty that these specifications are free from errors. See United States v. Spearin, 248 U.S. 132, 137, 54 Ct.Cl. 187, 39 S.Ct. 59, 63 L.Ed. 166 (1918) (permitting a contractor to rely on an implied warranty by the government). The test for recovery based on inaccurate specifications is whether the contractor was misled by these errors in the specifications. Beginning at least with the Supreme Court’s decision in Spearin, the cases have made clear that there can be no recovery unless the contractor has been “misled.” See, e.g., Spearin, 248 U.S. at 136, 39 S.Ct. 59 (“[T]he contractor should be relieved, if he was misled by erroneous statements in the specifications.”); Ragonese v. United States, 128 Ct.Cl. 156, 120 F.Supp. 768, 771 (1954) (Contract did not mention that contractor was likely to encounter large quantities of subsurface water, thereby misleading the contractor; contractor entitled to an equitable adjustment.). Where the contractor is not misled, it cannot claim an equitable adjustment. For example, in Wickham Contracting Co., Inc. v. United States, 212 Ct.Cl. 318, 546 F.2d 395, 400 (1976), the contractor based its bid on an erroneous scale in a contract drawing. When the government asked for verification of plaintiffs bid, plaintiff became aware of the error in scale. “Since plaintiff was aware of the drawing error at the time it entered into the contract, refusing an opportunity to withdraw its bid based on the drawing error, it is not entitled to recover additional costs by way of a contract price adjustment based on said error.” Id. at 401.

The decision of our predecessor court in Helene Curtis Industries, Inc. v. United States, 160 Ct.Cl. 437, 312 F.2d 774 (1963), is closely in point.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sheffield Barbers, LLC
Armed Services Board of Contract Appeals, 2025
Hahnenkamm, LLC v. United States
104 F.4th 1333 (Federal Circuit, 2024)
Amatea/Grimberg JV
Armed Services Board of Contract Appeals, 2023
Dynamic Systems Technology, Inc.
Armed Services Board of Contract Appeals, 2023
MPG West, LLC
Armed Services Board of Contract Appeals, 2020
A.T.I. TACOSE S.C.a R.L.
Armed Services Board of Contract Appeals, 2017
Otis Elevator Company v. WG Yates & Sons Construction Company
589 F. App'x 953 (Eleventh Circuit, 2014)
Metric Construction Co. v. United States
80 Fed. Cl. 178 (Federal Claims, 2008)
AAB Joint Venture v. United States
75 Fed. Cl. 414 (Federal Claims, 2007)
M.A. DeAtley Construction, Inc. v. United States
71 Fed. Cl. 370 (Federal Claims, 2006)
Clearwater Constructors, Inc. v. United States
71 Fed. Cl. 25 (Federal Claims, 2006)
Southern Comfort Builders, Inc. v. United States
67 Fed. Cl. 124 (Federal Claims, 2005)
Conner Brothers Construction Co. v. United States
65 Fed. Cl. 657 (Federal Claims, 2005)
Nvt Technologies, Inc. v. United States
370 F.3d 1153 (Federal Circuit, 2004)
Turner Construction Co., Inc. v. United States
367 F.3d 1319 (Federal Circuit, 2004)
Kiewit Construction Co. v. United States
56 Fed. Cl. 414 (Federal Claims, 2003)
Roy Case Construction Co. v. White
51 F. App'x 313 (Federal Circuit, 2002)
Comtrol, Inc. v. United States
294 F.3d 1357 (Federal Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
265 F.3d 1254, 2001 U.S. App. LEXIS 20639, 2001 WL 1105133, Counsel Stack Legal Research, https://law.counselstack.com/opinion/robins-maintenance-inc-v-united-states-cafc-2001.