A.T.I. TACOSE S.C.a R.L.

CourtArmed Services Board of Contract Appeals
DecidedJanuary 4, 2017
DocketASBCA No. 59157, 59200
StatusPublished

This text of A.T.I. TACOSE S.C.a R.L. (A.T.I. TACOSE S.C.a R.L.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A.T.I. TACOSE S.C.a R.L., (asbca 2017).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) A.T.I. TACOSE S.C.a R.L. ) ASBCA Nos. 59157, 59200 ) Under Contract No. N33191-l 1-C-0413 )

APPEARANCE FOR THE APPELLANT: Antonio Marcello Boschetti, Esq. Studio Legale Avv. Antonio M. Boschetti San Salvo, Italy

APPEARANCES FOR THE GOVERNMENT: Ronald J. Borro, Esq. Navy Chief Trial Attorney David L. Koman, Esq. Senior Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE NEWSOM ON CROSS-MOTIONS FOR SUMMARY JUDGMENT

Appellant, A.T.I. TACOSE S.C.a R.L. (TACOSE), was awarded a contract to design and build a dormitory for the Navy at Aviano Air Base in Italy. It appeals from final decisions denying two claims for additional compensation for work that it contends the government added to its contract. The government contends that the contract as originally awarded required this work and no additional compensation was warranted. Our jurisdiction to entertain these appeals arises from the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 7101-7109.

Both appeals involve disputes over the interpretation of requirements in a design/build contract. For the reasons explained below, we agree with the government's interpretations. We grant the government's motion for summary judgment and deny TACOSE's motion for summary judgment with respect to both appeals.

STATEMENT OFF ACTS (SOF) FOR PURPOSES OF THE MOTIONS

The following facts are not in dispute.

1. On 10 February 2011, the Naval Facilities Engineering Command, Europe, Africa, Southwest Asia, issued a solicitation for a competitive procurement seeking to award a design/build contract for a dormitory at Aviano Air Base in Aviano, Italy (R4, tab 7 at 1367). Proposals were due 43 days later on 25 March 2011 (id. at 1368). 2. The request for proposals (RFP) did not include a finished design. The RFP included a package setting forth minimum requirements, including specifications and drawings (R4, tab 1 at 143). After award, the selected contractor was required to design and construct the dormitory in accordance with these requirements (R4, tab 40 at 1991 ). Bidders were encouraged to develop unique solutions that exceeded the minimum requirements, provided that the design satisfied applicable building codes (R4, tab 1 at 143).

3. Because both appeals tum on the interpretation of the minimum requirements, we describe those requirements in some detail. The RFP and later the contract set forth requirements in six Parts, as follows:

Part I - Proposal Forms and Documents Part 2 - General Requirements Part 3 - Project Program Part 4 - Performance Technical Specifications Part 5 - Prescriptive Technical Specifications Part 6 -Attachments, including project drawings

(R4, tab 1 at 2, 688)

4. The contract required that the dormitory "be designed and constructed according to the latest version of all applicable design guides ... US Government Standards and Italian Laws and Norms." It expressly identified certain Italian, European and other building codes applicable to the dormitory design and construction. (R4, tab 1 at 143) It also incorporated by reference other building codes, laws, and other building standards (e.g., R4, tab 1 at 47-48, 369). Most contract Parts listed multiple codes and standards that were incorporated by reference (e.g., R4, tab I at 47, 143, 222, 369, 480, 711).

5. The contract required compliance with applicable building codes even if those codes were not expressly listed in the contract, stating "All applicable norms and standards, including those incorporated by reference, shall be met, whether or not a specific Italian or European norm or standard is indicated for a product or installation" (R4, tab 1 at 479-80, 489-500).

6. Among the publications incorporated by reference were certain U.S. Department of Defense (DoD) Unified Facilities Criteria (UFC) (R4, tab 1 at 47, 370). The UFC comprise a system of criteria for the planning, design, construction, sustainment, restoration, and modernization of DoD facilities (R4, tab 5 at 1236). Each UFC covers a different discipline or subsystem, e.g., electrical engineering, fire protection engineering, interior design, and design procedures, among others (R4, tab 1 at 4 7).

2 7. On 28 July 2011, the government awarded Contract No. N33191-l 1-C-0413 (contract) to TACOSE for a firm-fixed-price of €9,860,000 (R4, tab 14 at 1411-14).

8. After award, TA COSE was required to prepare designs of increasing maturity for government review and approval, including a Design Development submittal of 50-60% completion; a Prefinal Design of 100% completion; and a Final Design (R4, tab 1 at 72). TACOSE was also required to designate a Designer of Record (DOR) who had overall responsibility for the design (R4, tab 1 at 27, 49-50). TACOSE designated the OK Design Group of Rome, Italy (OK Design) as its DOR. OK Design was a subcontractor to TACOSE. (Tr. 15-17, 27; R4, tab 32 at 1560)

9. During performance, disagreements over the requirements arose between the government and TACOSE, some of which are the subject of these appeals. In ASBCA No. 59157, TACOSE contends that the government directed it to install 144 more mass notification speakers than the contract required. In ASBCA No. 59200, TACOSE contends that the government constructively changed the contract to add requirements for a perimeter waterproofing membrane and insulation for the ground floor slab. (R4, tabs 19, 34)

Mass Notification System Speaker Dispute

10. In Part 3 of the contract, entitled Project Program, Paragraph D4010 governed the dormitory's Life Safety Notification Systems. It required that the contractor "[p]rovide a complete, electrically supervised mass notification system (MNS) with paging function throughout the facility." (R4, tab 1 at 201)

11. The purpose of an MNS is to "protect life by indicating the existence of an emergency situation and instructing people of the necessary and appropriate response and action." In an emergency, the MNS provides "real-time information and instructions" to people in the building, using voice communications along with visible signals, text, graphics, or other methods of communication. (R4, tab 5 at 1243)

12. Paragraph D4010 specified further that the MNS was to include, in finished spaces, flush-mounted speakers to provide audible notifications (R4, tab 1 at 201 ). The dispute in this appeal concerns the number and placement of these speakers.

· 13. The contract called for 144 sleeping rooms arranged in 36 groupings, each consisting of 4 bedrooms and a common area. Each grouping was known as a "Quad Module." (R4, tab 14 at 1411) TACOSE contends that the contract required it to install one MNS speaker in each Quad Module, to be installed in the common room (app. br. at 11). The government contends the contract required TACOSE to install at least four speakers in each Quad Module, one in each sleeping room (gov't br. at 16-17).

3 14. Various contractual elements bear upon the location of MNS speakers. The contract required compliance with UFC 3-600-:l ON, entitled "Fire Protection 1 Requirements" (R4, tab 1 at 370, tab 6 at 1331). This requirement appears in many

'sections, including Part 2 General Requirements; Part 4 Performance Technical Specifications; and Part 6 Attachments, Project Description, and Life Safety Analysis (e.g., R4, tab 1 at 48, 62 (Part 2), at 370-71, 3 76-77, 482, 487 (Part 4), at 711, 720 (Part 6)).

15.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Hol-Gar Manufacturing Corp. v. The United States
351 F.2d 972 (Court of Claims, 1965)
Hensel Phelps Construction Co. v. The United States
886 F.2d 1296 (Federal Circuit, 1989)
Robins Maintenance, Inc. v. United States
265 F.3d 1254 (Federal Circuit, 2001)
bell/heery v. United States
739 F.3d 1324 (Federal Circuit, 2014)
William F. Klingensmith, Inc. v. United States
505 F.2d 1257 (Court of Claims, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
A.T.I. TACOSE S.C.a R.L., Counsel Stack Legal Research, https://law.counselstack.com/opinion/ati-tacose-sca-rl-asbca-2017.