Lockheed Martin Aeronautics Company

Armed Services Board of Contract Appeals·Decided April 22, 2024·No. 62209·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - )

)

Lockheed Martin Aeronautics Company ) ASBCA No. 62209 )

Under Contract No. FA8625-07-C-6471 )

APPEARANCES FOR THE APPELLANT: Stephen J. McBrady, Esq.

J. Chris Haile, Esq. Skye Mathieson, Esq. Michelle D. Coleman, Esq. John Nakoneczny, Esq. Crowell & Moring LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Caryl A. Potter, III, Esq.

Air Force Deputy Chief Trial Attorney Lawrence M. Anderson, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE PAGE

This appeal involves a contract for Lockheed Martin Aeronautics Company (Lockheed Martin) to modernize and install new engines for 49 C-5 Galaxy aircraft owned by the United States Air Force. Lockheed Martin alleges that the Air Force and the Defense Contract Management Agency (DCMA) directed it to perform excessive and disruptive “over and above” (O&A) work to repair pre-existing (or “legacy”) defects on the aircraft and seeks to recover $131,888,860 for the additional work. The Air Force asserts Lockheed Martin failed to prove its entitlement to this amount and its calculation of damages is unreasonable. Additionally, the Air Force contends Lockheed Martin’s claim is barred by the Contract Disputes Act’s statute of limitations and releases contained in bilateral modifications to the contract. We sustain the appeal.

FINDINGS OF FACT

The Contract

1. On April 30, 2007, the Air Force awarded Contract No. FA8625-07-C-6471, the Reliability Enhancement and Re-engining Program” (RERP), 1 to Lockheed Martin for the modernization of C-5 Galaxy aircraft. The undefinitized contract required Lockheed Martin to provide a set of upgrades to each of 49 government-owned aircraft. This included the installation of new CF6-80C2 commercial engines and other enhancements to subsystems and major components. (Gov’t br. at 2) The work was primarily conducted under fixed-price contract line item numbers (CLINs) (R4, tab 3 at 3-13). The original total amount of the contract was not to exceed (NTE) $23,000,000 (id. at 4). The C-5 Galaxy aircraft were produced from the mid-1960s through the 1980s (tr. 3/42, 4/30-31).

2. Lockheed Martin modified the 49 C-5 aircraft under the RERP contract, as well as three aircraft under a related, previously awarded Systems Development & Demonstration (SDD) contract (tr. 1/47). 2 The 49 aircraft to be reworked were informally designated by the parties as P-1 through P-49 (gov’t br. at 2). These aircraft were grouped into seven lots comprised of varying numbers of planes for the RERP work. The 21 aircraft at issue in this appeal are aircraft P-7 through P-27, which were part of Lots 3, 4, and 5. (Id.)

3. The contract incorporated by reference Federal Acquisition Regulation (FAR) 52.233-1, DISPUTES (JUL 2002) – ALTERNATE I (DEC 1991) (R4, tab 3 at 35). The contract also incorporated by reference FAR 52.243-1, CHANGES – FIXED-PRICE (AUG 1987) (the Changes Clause), which applied to “Firm-Fixed-Price Incentive (Firm Target) CLIN(s) only,” and FAR 52.243-3, CHANGES – TIME-AND- MATERIALS OR LABOR-HOURS (SEP 2000), which applied to “Time-and- Materials [T&M] CLIN(s) only” (id. at 36). The Changes Clause provided that “[t]he Contracting Officer may at any time, by written order, and without notice to the sureties, if any, make changes within the general scope of this contract . . . .” FAR 52.243-1(a). The Changes Clause also provided that “[i]f any such change causes an increase in the cost of, or the time required for, performance of any part of the work under this contract, whether or not changed by the order, the Contracting Officer [CO] shall make an equitable adjustment in the contract price . . . .” FAR 52.243-1(b).

1 This is the definition for the acronym “RERP” provided in the contract (see R4, tab 3 at 86).

2 See contract clause H101 SDD AND PRODUCTION CONCURRENCY (MAR 2007)

(R4, tab 3 at 22-23).

4. The contract included the full text of Clause B036, CONTRACT TYPE:

TIME-AND-MATERIALS (FEB 1997) (TAILORED):

(a) The Contractor shall furnish at the hourly rates stated below, all necessary and qualified personnel, managing and directing the same to complete all T&M CLINS within the performance period specified in Section F. In performance of these CLIN(s), Contractor shall be reimbursed for direct labor (exclusive of any work performed in an unpaid overtime status) at the hourly rates listed in Section J as an attachment.

CATEGORIES HOURLY RATE

Rates will be established each year and incorporated into the contract as an attachment.

(b) For the purposes of the clause of this contract entitled “Payments Under Time-and-Material and Labor-Hour Contracts”, the total ceiling price of the CLIN(s) specified in paragraph (a) above is $0.00.

Applies to Time-and-Materials CLIN(s) only.

(R4, tab 3 at 14) (emphasis in original)

5. The contract incorporated by reference FAR 52.243-7, NOTIFICATION OF CHANGES (APR 1984) and stipulated that the “[n]umber of calendar days is (insert 30 for RDSS/C) ‘30 days.’” (R4, tab 3 at 36). Additionally, FAR 52.243-7 provided in relevant part:

(b) Notice. The primary purpose of this clause is to obtain prompt reporting of Government conduct that the Contractor considers to constitute a change to this contract. Except for changes identified as such in writing and signed by the [CO], the Contractor shall notify the Administrative Contracting Officer [ACO] in writing promptly, within [30] calendar days from the date that the Contractor identifies any Government conduct (including actions,

inactions, and written or oral communications) that the Contractor regards as a change to the contract terms and conditions.

(Id.)

6. Contract clause H100, C-5B AIRCRAFT BASELINE (MAR 2006) set forth criteria for aircraft being provided by the government for RERP modification. Paragraph 1(b) defined the “baseline” at delivery to include “all approved Time Compliance Technical Orders (TCTOs) approved for incorporation as of this contract’s effective date.” (R4, tab 3 at 21-22)

7. Paragraphs 6 and 7 of H100 respectively required the government to ensure the aircraft met the baseline requirements prior to delivery and to negotiate an equitable adjustment with the contractor where it failed to ensure the airplanes met this standard:

6. All scheduled and routine aircraft maintenance required to be accomplished prior to RERP modification will be accomplished prior to delivery of aircraft to the Contractor for RERP modification. If the required maintenance has not been accomplished prior to delivery of the aircraft for RERP modification, the Contractor shall, if tasked by the [Procurement Contracting Officer (PCO)/Administrative Contracting Officer (ACO)], accomplish the required maintenance on an “R3” basis in accordance with the ”R3” clause H106, or other mutually acceptable contractual agreement.

7. If any delay in achieving the baseline configuration impacts this contract, the Government and the Contractor shall negotiate an equitable adjustment to this contract in accordance with the procedures of the “Changes” clause. Notwithstanding any other references in the contract, specifications, or statement of work, or any other document, aircraft delivered to the Contractor for RERP modification shall conform to the aircraft baseline as defined in paragraph 1 above.

(R4, tab 3 at 22)

8. The SDD contract was performed on two C5-B model aircraft and one older C5-A model (see, e.g., tr. 3/41-43, 5/121, 10/54, 58-59; see also app. supp. R4, tabs 414 at 2, 415 at 26, 3474 at 9 n.34).

9. The 49 RERP aircraft were expected to be C5-B or C5-C models. The latter were essentially B-models with “minor” configuration “modifications to the cargo bay area.” (Tr. 10/47; see also app. supp. R4, tabs 800 at 6, 3474 at 9 n.34; tr. 5/107, 133)

10. Mr. Tom Baxter, Lockheed Martin’s senior manager of business ventures who served as the business lead for the RERP proposal (tr. 3/48), testified that TCTOs were time-sensitive orders:

Free access — add to your briefcase to read the full text and ask questions with AI

Lockheed Martin Aeronautics Company, (asbca 2024).

Lockheed Martin Aeronautics Company (Lockheed Martin Aeronautics Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Smithkline Beecham Corp. v. Apotex [Corrected Date]
439 F.3d 1312 (Federal Circuit, 2006)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
Dixon v. Shinseki
741 F.3d 1367 (Federal Circuit, 2014)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
Parsons Evergreene, LLC v. Secretary of the Air Force
968 F.3d 1359 (Federal Circuit, 2020)
Wunderlich Contracting Co. v. United States
351 F.2d 956 (Court of Claims, 1965)