Jemison & Partners, Inc. v. Secretary of the Army

CourtCourt of Appeals for the Federal Circuit
DecidedApril 16, 2024
Docket23-1773
StatusUnpublished

This text of Jemison & Partners, Inc. v. Secretary of the Army (Jemison & Partners, Inc. v. Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jemison & Partners, Inc. v. Secretary of the Army, (Fed. Cir. 2024).

Opinion

Case: 23-1773 Document: 37 Page: 1 Filed: 04/16/2024

NOTE: This disposition is nonprecedential.

United States Court of Appeals for the Federal Circuit ______________________

JEMISON & PARTNERS, INC., Appellant

v.

SECRETARY OF THE ARMY, Appellee ______________________

2023-1773 ______________________

Appeal from the Armed Services Board of Contract Ap- peals in No. 62928, Administrative Judge Michael N. O’Connell, Administrative Judge Owen C. Wilson, Admin- istrative Judge Richard Shackleford. ______________________

Decided: April 16, 2024 ______________________

WILLIAM LEE KOHLER, Kohler Construction Law, New Orleans, LA, for appellant.

ANNE DELMARE, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washing- ton, DC, for appellee. Also represented by BRIAN M. BOYNTON, WILLIAM JAMES GRIMALDI, PATRICIA M. MCCARTHY. ______________________ Case: 23-1773 Document: 37 Page: 2 Filed: 04/16/2024

2 JEMISON & PARTNERS, INC. v. SECRETARY OF THE ARMY

Before PROST, CHEN, and HUGHES, Circuit Judges. PER CURIAM. Appellant Jemison & Partners, Inc. (Jemison) and the Army Corps of Engineers (Corps) entered into a contract for greenspace restoration in 2019. That restoration in- cluded placing topsoil along a portion of Jefferson Avenue’s median in Orleans Parish, Louisiana. For the topsoil placement, the parties dispute whether their contract re- quires a unit-price or lump-sum payment. That is, does the contract require the Corps to pay Jemison for the actual quantity of topsoil placed or a lump sum based on the quan- tity of topsoil the parties estimated would be placed? Jemison appealed to the Armed Services Board of Con- tract Appeals (Board), insisting that it had been underpaid by $53,104.80 because the contract required a lump-sum payment for topsoil placement. The Board disagreed and found that the contract required per-unit payment for the topsoil placement. See In re Jemison & Partners, Inc., ASBCA No. 62928, 23-1 B.C.A. ¶ 38,249, 2022 WL 17970459 (Dec. 5, 2022) (Decision). 1 Jemison appeals the Board’s determination. Appellee Secretary of the Army (Secretary) counters that we lack jurisdiction to hear this appeal and, in the alternative, argues that the Board cor- rectly interpreted the contract. For the following reasons, we conclude that we have jurisdiction, and we affirm the Board’s decision.

1 Because the reported version of the Board’s deci- sion is not paginated, citations in this opinion are to the version of the Board’s decision included in the Joint Appen- dix (J.A. 1–9). For example, Decision at 1 is found on J.A. 1. Case: 23-1773 Document: 37 Page: 3 Filed: 04/16/2024

JEMISON & PARTNERS, INC. v. SECRETARY OF THE ARMY 3

BACKGROUND A. On November 16, 2018, the Corps issued Solicitation W912P8-19-R-0005 for the planting of trees along a stretch of Jefferson Avenue’s median in Orleans Parish, Louisiana. J.A. 32–143. The project included, among other things, controlling traffic, excavating and filling, planting trees and other plants, and placing topsoil, mulch, and sod. J.A. 261–96. For the topsoil portion, the solicitation listed an “Estimated Quantity” of 2,355 cubic yards. J.A. 39. Following the issuance of the solicitation, Jemison and the Corps began negotiating a contract. Jemison submit- ted multiple bids, met with the Corps, and asked questions, which the Corps answered. They ultimately agreed to a contract. See J.A. 199–313 (the contract). That contract listed nine item numbers, and each item number included a description of the supplies and/or ser- vices, a quantity, a unit, a unit price, an amount, and a net amount. The first two item numbers are reproduced below: Case: 23-1773 Document: 37 Page: 4 Filed: 04/16/2024

4 JEMISON & PARTNERS, INC. v. SECRETARY OF THE ARMY

J.A. 201. Notably, the unit for “Mobilization and Demobi- lization” is “Job” whereas the unit for “Topsoil” is “Cubic Yard.” Units for other item numbers include “Square Foot” for Sod and “Each” for Magnolia grandiflora, a type of flower. J.A. 201–02. The value in the Amount column is determined by mul- tiplying the quantity by the unit price. The sum of the Amount column for all nine entries is $747,298.57, which is the “Total Award Amount” listed on the front page of the contract. J.A. 199, 239. The contract also includes a “Measurement and Pay- ment” section that describes how the topsoil is to be meas- ured and what is included in the payment price: Measurement for work required under this section shall be an in place topsoil cubic yard measure- ment. The topsoil quantities are provided as an aid to bidders only. The contractor shall take measure- ments subtracting rootball volume at each area re- quiring excavation and soil replacement. Payment for all work specified in this section including ma- terial, equipment, labor and any other incidental work necessary for providing, installing and main- taining the topsoil will be considered completely covered under the contract price for topsoil as indi- cated in Section 00 41 00 Bid Schedule. J.A. 274. Case: 23-1773 Document: 37 Page: 5 Filed: 04/16/2024

JEMISON & PARTNERS, INC. v. SECRETARY OF THE ARMY 5

The referenced Bid Schedule provides a summary of the estimated contract price for each item number:

J.A. 239. The parties also incorporated Federal Acquisition Reg- ulation (FAR) 52.212-4 into the contract. J.A. 199. That regulation discusses, among other things, how the contrac- tor will submit invoices and how the Government will make payments. For invoices, “[t]he Contractor shall submit an original invoice,” which “must include . . . [d]escription, quantity, unit of measure, unit price and extended price of the items delivered.” 48 C.F.R. § 52.212-4(g)(1)(iv). For payment, the regulation provides that “[p]ayment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this con- tract.” 48 C.F.R. § 52.212-4(i)(1). Finally, the contract includes some of the questions and answers that were exchanged during negotiations. As an example, Jemison asked the following question, and the Corps provided the following answer: Case: 23-1773 Document: 37 Page: 6 Filed: 04/16/2024

6 JEMISON & PARTNERS, INC. v. SECRETARY OF THE ARMY

Q. “[C]an we retain the same estimated quantities for top soil and add a qualification in the revised proposal that the actual quantities utilized will be verified by the [Corps] in the field? It is our under- standing the [Corps] carefully confirms material quantities (such as top soil) in the field as work pro- gresses. We understand that the [Corps] will only pay for verified materials used in the project.” A. “Measurement for this work shall be an in place top soil cubic yard measurement verified by the government. The topsoil quantities are provided as an aid to the bidder. The actual topsoil quantities used cannot exceed the government’s estimated quantities without a contract modification.” J.A. 213. B. Once the contract was executed, Jemison began work- ing on the project. Decision at 4 ¶ 11. Jemison submitted two requests for payment for its work through April 30 and August 12, 2019, respectively. Id. at 4 ¶¶ 11–12. The first invoice requested payment for placing 452.78 cubic yards of topsoil at the $84 per cubic yard rate, and the second requested payment for placing an additional 1,206.61 cubic yards at the same rate. Id. The Corps approved these pay- ments. Id. The present dispute arose with the third payment re- quest, which Jemison submitted on October 19, 2019. Id. at 5 ¶ 15.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Placeway Construction Corporation v. The United States
713 F.2d 726 (Federal Circuit, 1983)
Nvt Technologies, Inc. v. United States
370 F.3d 1153 (Federal Circuit, 2004)
Parsons Evergreene, LLC v. Secretary of the Air Force
968 F.3d 1359 (Federal Circuit, 2020)
Blough v. United States
35 Cont. Cas. Fed. 75,675 (Court of Claims, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
Jemison & Partners, Inc. v. Secretary of the Army, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jemison-partners-inc-v-secretary-of-the-army-cafc-2024.