OPINION
NETTESHEIM, Judge.
This case is before the court on two motions by defendant to dismiss the complaint for lack of jurisdiction. Two issues are presented for consideration. The first is whether a contractor submitted to the contracting officer a claim, such that the contractor’s filing in the Claims Court over a year after the issuance of a final decision on the purported claim renders its suit untimely. The second issue, raised orally during argument on the first, is whether a contractor’s claim that the Government caused delay, although a time extension is not sought, transforms government assessment of liquidated damages into a contractor claim, so that due to the amount of the total claim, certification is a jurisdictional prerequisite.
FACTS
The following facts are undisputed. On April 21, 1988, the Army Directorate of Contracting (the “Army”), under authority delegated to it by the Small Business Administration (the “SBA”), issued Solicitation No. DAEA18-88-R-0037 (the “solicitation”) for paint, labor, material, and equipment to construct a helicopter hangar at Libby Army Airfield, Fort Huachuca, Arizona. After negotiations Sun Eagle Corporation (“plaintiff”) submitted a revised proposal price of $153,808.34 on May 18, 1988, which contemplated that the hangar would be a Butler steel building. The parties entered into Contract No. DAEA18-88-C-0019 on June 7, 1988. Plaintiff submitted drawings for the Butler building and for its foundation on June 24, 1988. Three days later plaintiff acknowledged receipt of the notice to proceed, which allowed plaintiff 120 days to construct the building.
In a memorandum for record dated July 18, 1988, Contract Specialist Lida Panaga-kos memorialized the steps by which the Directorate of Engineering and Housing (the “DEH”) reviewed and rejected plaintiff’s initial building and foundation submit-tal. Specifically, Ms. Panagakos noted that DEH found deficiencies regarding the proposed Butler building’s resistance to wind velocity, as well as problems with the compressive strength and seismic zone design of the concrete. Martin Alvarez, plaintiff’s President,1 disagreed with the assessment of DEH and stated that the building proposed by plaintiff already had been accept[467] ed. DEH contacted Butler directly in an attempt to rectify the problem.
On July 25,1988, plaintiff sent a letter to Contracting Officer Georgia A. Lawrence complaining about, among other things, the Army’s reluctance to approve promptly the Butler building submittal. In non-specific terms plaintiff requested compensation for increased overhead and demanded an extension of time.
By letter of July 28, 1988, due to the alleged necessity to install a quantity of concrete for the foundation's footings and stems beyond the requirements of the contract, plaintiff specifically requested additional overhead costs of $6,295.70 and a contract extension of five days.
The record at this point has a time gap. Defendant explained at argument that the DEH returned plaintiff’s first footing sub-mittals. On August 2, 1988, Contracting Officer Lawrence approved plaintiff’s sub-mittal for the foundation, paint, and building.2 In a letter dated August 8, 1988, responding to plaintiff’s July 25, 1988 letter, Ms. Lawrence stated her position that the Army’s approval on August 2 of plaintiff’s proposal was within the contract’s 20-day time limit for approval or disapproval by the Army of submittals. Ms. Lawrence stated that once a submittal is rejected, the 20-day period begins to run anew.
By letter of August 19,1988, Contracting Officer Lawrence questioned the escalated cost asserted for footings and stems. She requested negotiations and a “re-proposal” on this point, but did allow plaintiff’s request for increased costs associated with profit, overhead, bonds, and taxes. On September 14, 1988, plaintiff submitted its revised cost proposal in which it reduced its requested amount to $3,842.04.
On November 9,1988, the Army made its final inspection of the project. In a letter to plaintiff dated November 17, 1988, Contracting Officer Lawrence concluded that the building was not acceptable for government occupancy or use. She stated that the project did not pass inspection due to below-standard workmanship and numerous deficiencies in the alarm system, sliding doors, lock sets, weather seals, and other items. Ms. Lawrence assessed liquidated damages at $200.00 per day beginning on October 25, 1988, and at $300.00 per day from November 25 forward until completion and acceptance of all work.
In a letter dated November 28, 1988, plaintiff: 1) disputed the Army’s assessment of liquidated damages; 2) asserted that the Army modified the contract to allow plaintiff to supply a Butler building only; 3) claimed that several items listed in the November 17 letter referenced work outside the scope of the contract; 4) demanded payment for work that it performed outside of the contract; and 5) requested a meeting with Contracting Officer Lawrence and her superiors to “finalize” contract performance and payment. Ms. Lawrence responded by letter of the same date and requested that plaintiff specify which items were inapplicable to the contract. She stated that, after review of the information, her office would arrange a meeting, if required.
Plaintiff answered on November 29, 1988. Initially, this letter set out the following “facts” regarding negotiations between the Army and plaintiff on the project:
The first claim made by Sun Eagle Corporation is for the additional time required by Sun Eagle Corporation to verify color, structural integrity including redesigned footings and other items which were already approved at the time of the negotiations and reaffirmed by the modification in writing. Sun Eagle Corporation requests an additional 30 days of delays on the part of the Government for these extraneous approvals. Sun Eagle Corporation will make a further claim later for the additional labor, materials and equipment for the re-designed footings and stems.
[468] We have included our original claim to the Government dated July 28, 1988, in the amount of $6,295.70 for this additional work. The Government did not have a specification for this stem wall and later forced Sun Eagle Corporation to invest an additional $2,000.00+ in labor and materials cost in order that the stem wall be repaired to the satisfaction of the Government.
Next, plaintiffs November 29 letter discussed the history of the problems with horizontal sliding doors referred to in the contracting officer’s letter of November 17. Plaintiff also disputed a requirement to provide and install gutters. Plaintiff continued:
Our last claim to the Government is for extended overhead. Sun Eagle Corporation has incurred extended overhead costs for the duration of this contract due to the Government’s failure to address the original negotiations and convey the negotiations, the contract, the modification and Sun Eagle Corporation’s original proposal. With this in mind Sun Eagle Corporation hereby requests extended overhead costs of $275.00 per day for an additional 45 days. The total amount of our claim for extended overhead is $12,275.00.
If the Government had approved all of the items as per the negotiations, the modification and Sun Eagle Corporation’s proposal, then the project would have been completed more than 45 days prior to this date. Our total claim including additional concrete footings and stems, repair work on stems for un-prescribed stems and for additional overhead is $20,670.70. We also request and should be granted an extension to the contract of a minimum of 60 days. Please call me in order that we may discuss this situation and arrange for a meeting with all parties included.[3]
By letter of December 28, 1988, Ms. Lawrence denied all of plaintiff’s requests. Contracting Officer Lawrence labelled this letter a “final decision” pursuant to the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (1988) (the “CDA”).
On January 4, 1989, according to an internal memorandum authored by Contract Specialist Panagakos, a “meeting/telephone conversation” took place in which the parties attempted to resolve the dispute. According to Ms. Panagakos, plaintiff and the Army vigorously disputed whether the contract called for the Butler building to meet precise factory specifications or whether the Army waived those specifications. As the meeting progressed, as recorded by Ms. Panagakos, the Army stated that it still intended to assess liquidated damages, and plaintiff admitted its mistake concerning its proposed amount of concrete. In the words of Contract Specialist Panagakos, the “[mjeeting was terminated with ... [plaintiff] reluctantly agreeing to our statements. It was assumed that no further claim will be forthcoming and as soon [as] all deficiencies are corrected, modification will be issued for liquidated damages.”
On February 9, 1989, plaintiff wrote Ms. Lawrence, asserting that it complied with the extra work requirements in her December 28, 1988 letter. Plaintiff claimed that it delivered a final voucher on December 14, 1988, and requested full payment in the amount of $44,439.40. Additionally, based on plaintiff’s compliance with the contract and on the Army’s acceptance of the building on January 18,1989, plaintiff asked Ms. Lawrence to waive all damages.
No record of any further contact between the parties themselves exists, save for Contract Modification No. P00002 issued on April 17, 1989, signed by Contracting Officer Frank Abernathy, Mr. Alvarez for plaintiff, and a contracting officer of the SBA. This modification provided reimbursement to plaintiff in the amount of $3,852.02, principally for the concrete error noted above.
[469] On October 23,1989, counsel for plaintiff wrote to Contracting Officer Abernathy disputing the liquidated damages, charging the Army with delay in approving submit-tals, and identifying the Army’s requested additional work as the cause for delay. The letter stated:
Because of the conduct of the Government, in causing Sun Eagle’s work on the project to continue past the contract completion date, Sun Eagle is entitled to payment for any resulting extended overhead costs. On November 29, 1988, Sun Eagle requested payment for extended overhead in the total amount of $12,-275.00, for extended overhead costs of $275.00 per day for 45 days. In addition to extended overhead associated with the 45 days, Sun Eagle is entitled to payment for extended overhead for the remaining days of delay by the Government, which amounts to at least 81 days of delay at a cost of $22,275.00. Sun Eagle has yet to receive any payment for extended overhead.
Sun Eagle also requested reimbursement of costs for additional work in connection with the redesign of footings and stems in the amount of $6,295.70, and additional cost and repair of the stems in the amount of $2,000.00, for which Sun Eagle has not been paid. As a further added expense, Sun Eagle incurred $2,046.00 in connection with the furnishing and installation of gutters and downspouts, which were not part of the original contract. Sun Eagle also has not been reimbursed for this addition to the contract. A copy of the invoice sent to Sun Eagle for the gutters and downspouts is attached hereto. Thus, in addition to the $18,400.00 wrongfully deducted, Sun Eagle is entitled to reimbursement for all extra costs resulting from the conduct of the Government. Sun Eagle therefore demands payment of $44,891.70 plus interest for extended overhead and changes to the contract.
By this letter we are putting the Contracting Officer on notice of Sun Eagle’s claim for payment in the amount of $63,-291.90 [4] plus interest, for the amount remaining on invoice No. 6, and for extended overhead and extra costs associated with the additional work demanded by the Government, which was not required by the contract specifications.
We request your immediate review of this claim, and ask that the Contracting Officer render a prompt, final decision in writing if this claim is not paid in full.
Contracting Officer Abernathy responded in a letter dated November 20, 1989, in which he reiterated the Army’s position that plaintiff received a final decision dated December 28, 1988, foreclosing future disputes regarding all issues covered therein. Mr. Abernathy also explained how his office arrived at its computation of liquidated damages; he did not discuss any other specifics raised in plaintiff’s October 23 correspondence.
On April 6, 1990, plaintiff filed its complaint in this court seeking: 1) extended overhead of $275.00 per day for 94 days of delay; 2) modifications and extras to the contract of $2,046.00 for materials and an unspecified amount for labor; 3) liquidated damages in the amount of $18,400.00 wrongfully withheld by the Army; 4) costs, attorneys’ fees, and interest; and 5) a declaratory judgment that plaintiff complied with the one-year time limit for filing its action.
DISCUSSION
Defendant requests dismissal for lack of subject matter jurisdiction. When evaluating a RUSCC 12(b)(1) motion, the court must accept as true any allegations of fact made by the non-movant. Scheuer v. Rhodes, 416 U.S. 232, 236, 94 S.Ct. 1683, 16, 40 L.Ed.2d 90 (1974); Reynolds v. Army & Air Force Exch. Serv., 846 F.2d 746, 747 (Fed.Cir.1988). However, the burden is on plaintiff to establish jurisdiction. Reynolds, 846 F.2d at 748 (citing cases).
Defendant’s original motion requires the court to decide whether the November 29, 1988 letter from plaintiff to Contracting Officer Lawrence constituted a claim under [470] the CDA and applicable case law. If answered in the affirmative, the court must determine whether Ms. Lawrence’s December 28, 1988 letter constitutes a final decision as to the claims presented in plaintiff’s complaint.5
I. Whether the November 29, 1988 letter constitutes a claim
The CDA requires that “[a]ll claims by a contractor against the government relating to a contract shall be in writing and shall be submitted to the contracting officer for a decision.” 41 U.S.C. § 605(a).6 A claim need not be submitted in any particular form or use any particular wording. Contract Cleaning Maintenance, Inc. v. United States, 811 F.2d 586, 592 (Fed.Cir.1987). Nonetheless, a claim must be “a clear and unequivocal statement that gives the contracting officer adequate notice of the basis and amount of the claim.” Id. Moreover, a claim must request a decision from the contracting officer. Mingus Constructors, Inc. v. United States, 812 F.2d 1387, 1395 (Fed.Cir.1987). A claim, however, does not constitute such for purposes of the CDA merely by virtue of its being referred to by a party as a claim. See Mingus, 812 F.2d at 1394. In Cubic Corp. v. United States, 20 Cl.Ct. 610, 616 (1990), the Claims Court summarized the criteria for proper submission of a claim: The purported claim must be 1) an actual claim; 2) in writing; 3) sent to the contracting officer; and 4) a request for a final decision. Judge Robinson explained: “The relevant factors in this analysis are whether the contractor asserted specific rights, requested specific relief, and requested the ... [contracting officer] to render a final decision.” Id. at 616 (citing cases).
In addition to the above factors and requirements, the Federal Circuit recently added an analytical element to the analysis of whether a particular writing constitutes a claim. In Dawco Construction, Inc. v. United States, 930 F.2d 872 (Fed.Cir.1991), the successful contractor, Dawco, and the United States Navy (the “Navy”) entered into a contract involving, in part, landscaping for the grounds of six individual housing areas. Dawco subcontracted the landscaping work to J.C. Landscape (“JCL”). After award, the Navy decided to landscape only two of the six areas. In performing the work, JCL encountered differing site conditions.
Dawco and the Navy subsequently exchanged numerous pieces of correspondence. One of the issues before the Federal Circuit was whether Dawco, in any of its correspondence, properly submitted a “claim” under the CDA. As the fulcrum of its decision, the Federal Circuit stated that to constitute a claim, “[a] contractor and the government agency must already be in dispute over the amount requested____ Unilateral cost proposals or correspondence suggesting disagreement during negotiations, while they may ultimately lead to a dispute, do not, for purposes of the Act, satisfy the clear requirement that the request be in dispute.” Dawco, 930 F.2d at 878 (emphasis in original) (citing Mayfair Constr. Co. v. United States, 841 F.2d 1576, 1577 (Fed.Cir.), cert. denied, 488 U.S. 980, 109 S.Ct. 528, 102 L.Ed.2d 560 (1988)). Worded differently, if a dispute over the payment request does not exist at the time of communication to the contracting officer, then no claim emanates from that communication. The Federal Circuit stated that the early letters from Dawco did not constitute a claim because they were merely attempts to “spur negotiations.” Dawco, 930 F.2d at 879. For example, one letter explained “that Dawco ‘would like to start settlement negotiations as soon as possible’____” Id. at 875. However, the last letter from Dawco did amount to a claim because it indicated “that negotia[471] tions had clearly been abandoned____ at 879.7 Id.
In the instant case, plaintiff contends that its letter of November 29, 1988, does not constitute a claim under 41 U.S.C. § 605(a). Relying primarily on Metric Construction Co. v. United States, 14 Cl.Ct. 177, 179 (1988), and Hoffman Construction Co. v. United States, 7 Cl.Ct. 518, 525 (1985), plaintiff argues that its failure to request specifically a final decision by the contracting officer forestalls any claim arising from the November 29 letter. It asserts that the demands in the letter were merely indicia of an intent to negotiate. Further, plaintiff contends that it “did not clearly identify the entire amount of monetary compensation or time extension requested____”, Plf’s Br. filed Feb. 8, 1991, at 11, and therefore did not state a sum certain, a requirement for a legally effective claim.
Defendant rejoins that plaintiff’s November 29, 1988 letter was a claim. Relying on Mendenhall v. United States, 20 Cl.Ct. 78 (1990), and Contract Cleaning, defendant contends that the court must look to the “totality of the circumstances,” viz., even if plaintiff did not specifically request a final decision, one can characterize the November 29 letter as the “straw that broke the camel’s back,” Def's Br. filed Mar. 11, 1991, at 2, thereby converting arguments and demands in previous letters into a claim. According to defendant, insofar as plaintiff stated a specific dollar amount in the November 29 letter, along with a specific number of days that plaintiff sought as an extension of time, plaintiff was requesting a sum certain and, as a result, presented a claim to the contracting officer.
Looking first to the language of the November 29,1988 letter, the court notes that plaintiff referred at least four times to “our claim.” Indeed, plaintiff characterized the $20,670.70 payment request as “our total claim.” As defendant correctly notes, Contract Cleaning counsels that the CDA does not require a contractor to use any particular wording. 811 F.2d at 592. Thus, plaintiff’s use of the term “claim” does not, in the absence of other factors, render the November 29 letter a claim. However, plaintiff also referred to the payment and time extension demands in writing and sent them to the contracting officer, thereby satisfying three out of four elements of the test formulated in Cubic.
As derived from the CDA and case law, the following four-part analysis will instruct whether plaintiff’s November 29, 1988 letter qualifies as a claim: whether the letter clearly and unequivocally 1) asserted specific rights; 2) requested specific relief of a sum certain; 3) requested a final decision; and 4) whether the letter, in conjunction with the totality of circumstances, was sent in the context of an ongoing dispute between the parties as to which they previously had abandoned negotiations.
1. Assertion of specific rights
Plaintiff’s November 29 letter stated the basis for its request for payment and time extension, as required by Contract Cleaning, 811 F.2d at 592. Mr. Alvarez, plaintiff’s President, characterized the first extension of time as necessary “to verify color, structural integrity including re-designed footings and other items ... already approved at the time of negotiations.” Mr. Alvarez also requested payment for additional work required to repair a stem wall to the Army’s satisfaction. Finally, Mr. Alvarez stated that the time and money required for this work necessitated additional overhead costs because of “the government’s failure to address the original negotiations and convey the negotiations, the contract, the modification and Sun Eagle’s original proposal.” While plaintiff’s assertion of its right to payment and an extension of time is perhaps not a model of clarity, the letter notified the contracting officer as to the basis of plaintiff’s request for additional money and time. As such, the letter asserted specific rights.
[472]*4722. Request for specific relief of a sum certain
The next issue is whether plaintiff requested specific relief. Tecom, Inc. v. United States, 732 F.2d 935, 936 (Fed.Cir. 1984). The Claims Court in Z.A.N. Co. v. United States, 6 Cl.Ct. 298, 304 (1984), required a claim to state the amount sought. As with the basis for a claim, the contracting officer must receive a “clear and unequivocal notice” of the amount of the claim. Metric, 14 Cl.Ct. at 179. In Metric the court recognized a claim where the amount in dispute could be determined by a simple mathematical calculation or otherwise derived from the contractor’s submission. Id. at 180. Little doubt exists that the November 29 letter quantified amounts of money and time. However, whether these amounts relate to the complaint at issue is another matter. To the extent that plaintiff’s complaint asks for payment for work not itemized in the November 29 letter, that work is not subject to any statutory limitations applicable to any claims set forth in that letter.
In the November 29 letter, plaintiff requested $20,670.008 and 45 days’ extension time.9 Significantly, plaintiff requested payment for additional concrete footings and stems as early as July 28, 1988. The November 29 letter also requested $2,000.00 for labor and materials required to repair the stem wall and $12,275.00 in extended overhead for the duration of the contract. The court regards these figures as sums certain. Plaintiff even totalled the claims for the contracting officer to facilitate mathematical calculation, although the total appears incorrect.
Plaintiff argues that Metric compels this court to regard the November 29 letter as not stating a sum certain. In Metric, however, the contractor only stated a request “exceeding” a certain amount; it gave no exact total. 14 Cl.Ct. at 178. Further, in Metric, the letter in question contained voluminous exhibits stating varying dollar amounts, one indistinguishable from the other. Id. at 179-80. The instant case involves a single letter with consistent dollar figures and no exhibits. Thus, the November 29 letter does state a sum certain as to any “claims” made in that letter.
3. Request for final decision
Third, this court must examine whether plaintiff requested a final decision. While Contract Cleaning counsels that no particular magic language is required to create a claim, 811 F.2d at 592, the Federal Circuit in Mingus Constructors elaborated that the claim must request a final decision. 812 F.2d at 1395. In the instant case, plaintiff did not expressly request a final decision in the November 29 letter, nor is there any implication that plaintiff desired a final decision. The letter sets forth a statement of rights and payment amounts and requests a meeting to discuss these issues. Indeed, it would be inconsistent to find that plaintiff impliedly requested a final decision when it expressly requested a meeting to discuss the situation. Further, this court observes that even an explicit request for a final decision combined with a sum certain and statement of specific rights does not necessarily constitute a claim. See Dawco, 930 F.2d at 877-78; see also Hoffman, 7 Cl.Ct. at 524-25 (letter requesting meeting to resolve issues did not request final decision and therefore did not constitute an “assertion of entitlement”).
Defendant argues that the regulation defining a claim under section 605(a) does not specify that the letter seek a final decision. The Federal Acquisition Regulations (“FAR”) define a “claim” as
a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, ... A voucher, invoice, or other routine request for payment [473] that is not in dispute when submitted is not a claim____
FAR § 33.201, 48 C.F.R. § 33.201 (1990) (quoted in Dawco, 930 F.2d at 877-78). By this argument defendant seems to suggest that the Federal Circuit’s requirement is superfluous or inconsistent with the regulation. Mingus and Dawco are neither, and they are binding precedent, whereas defendant commends the Claim Court’s decision in Mendenhall which appears to have glossed over the requirement.10 Claims Court decisions are not binding precedent. Defendant’s argument is rejected.
4. Abandonment of negotiations
Finally, this court must examine the circumstances in which plaintiff drafted the letter at issue. A claim only can arise when the parties are in dispute over a payment request. Dawco, 930 F.2d at 878. However, the converse is not necessarily true, to wit, that any time the parties are in a dispute, any payment request automatically becomes a claim. Indeed, the Federal Circuit in Dawco stated that a claim only exists when the parties clearly have abandoned negotiations and the amount claimed is definitely in dispute. Id. at 879.
Problems beset this contract almost from its inception. On July 28, 1988, four months prior to the letter in question, plaintiff already was complaining about delays, specifically requesting $6,295.70 and five additional days to install the concrete footings and stems. The contracting officer disputed some of the amount in her August 19 letter, but, significantly, allowed certain increased costs for overhead, profit, taxes, and bonds. The contracting officer requested further re-proposals and negotiations. On September 14, plaintiff accepted the contracting officer’s cost calculations.11 Thus, as of the November 29, 1988 letter, the concrete footing and stem issue seemed to have been resolved. At the very least, both parties were willing to negotiate about the request. As a result, the footing and stem payment requests could not constitute any part of a claim expressed in the November 29 letter.
Plaintiff’s claim for additional time to complete the project was also not clearly in dispute. The November 29 letter states that plaintiff required additional time in order “to verify color [and] structural integrity including re-designed footings----” No indication of any previous request for additional time other than that associated with the footing/stem issue is apparent. However, as noted above, those items were never clearly in dispute, nor does any evidence indicate that the contracting officer refused to grant additional time until after the November 29 letter. In any case, the November 29 request for 45 days’ additional time was the first such request, and nothing in the record indicates that the parties viewed this item as nonnegotiable.
Plaintiff’s final request in the November 29 letter for an additional overhead payment of $20,670.70 was likewise not clearly in dispute. Significantly, the Army accepted the only previous overhead request by plaintiff. Again, nothing in the record reflects either the contracting officer's or plaintiff’s unwillingness to discuss this issue.
The circumstances surrounding plaintiff’s November 29, 1988 letter are illuminating. Prior to the contracting officer’s November 17 letter to plaintiff communicating various deficiencies in the Butler building, the last contact between the parties was an amicable September 14 letter from plaintiff accepting the contracting officer’s revised costs for footings and stems. Further, plaintiff’s letters of November 28 and 29 requested a meeting to discuss alleged contractual deficiencies. While a desire to meet is not dispositive on the claim issue, Contract Cleaning, 811 F.2d at 592, [474] such requests are evidence of a desire to continue negotiations, rather than an effort to resolve the dispute formally.
Lastly, because the request to meet and discuss the disagreement is considered along with the fact that plaintiff did not request a final decision, see Mingus, 812 F.2d at 1395; Hoffman, 7 Cl.Ct. at 525-26, this court cannot say that negotiations clearly were abandoned. According to a government memorandum to file, a meeting was held on January 4, 1989, in which both parties discussed payments and responsibilities under the contract. The occurrence of such a meeting undercuts the contention that the. parties had reached an impasse by November 29, 1988.
It is instructive to analyze plaintiffs letters, assuming, arguendo, that all amounts requested were in dispute. Even in such a situation, plaintiffs November 29 letter does not constitute a claim. A disagreement alone, without an intent to discontinue negotiations, is insufficient to transform a request into a dispute, hence a claim. Dawco, 930 F.2d at 878.
The court concludes that plaintiffs November 29, 1988 letter did not constitute a claim. Consequently, Ms. Lawrence’s December 28, 1988 letter is inoperative and need not be evaluated.
II. Whether plaintiff’s claim that the Government caused delay as a defense against liquidated damages constitutes a contractor claim
At argument defendant raised the issue of certification. In its oral motion to dismiss, defendant contended that plaintiff’s request for a release of $18,400.00, withheld by the Army as liquidated damages, constitutes a contractor, not a government, claim. Since liquidated damages represent a contractor claim, defendant’s argument continues, the entire claim in plaintiff’s October 23, 1989 letter must be certified, in that the total amount requested by plaintiff exceeds $50,000.00. 41 U.S.C. § 605(c). Defendant also asserts that the attempted certification by Mr. Alvarez is insufficient because it does not state that the supporting documentation was accurate and complete to the best of his knowledge. The court allowed plaintiff to respond and defendant to reply by brief.
Plaintiff acknowledges that its October 23, 1989 letter states a claim in excess of $50,000.00, but characterizes the withholding of $18,400.00 in liquidated damages as a government claim, which should not be included when calculating whether plaintiff’s claim reached the $50,000.00 threshold. Alternatively, if certification is required, it is plaintiff’s position that Mr. Alvarez’s certification substantially complies with the requirements of the CDA.
Defendant relies on Placeway Construction Corp. v. United States, 920 F.2d 903 (Fed.Cir.1990), and three Claims Court cases, Elgin Builders, Inc. v. United States, 10 Cl.Ct. 40 (1986); Z.A.N. Co., 6 Cl.Ct. 298; and Warchol Construction Co. v. United States, 2 Cl.Ct. 384 (1983).
In Elgin Builders the contracting officer (the “CO”) assessed liquidated damages to-talling $54,000.00. The contractor responded by seeking recovery in the form of time extensions and additional compensation. The court stated:
The assessment of liquidated damages is a government claim against the con-tractor____ Thus, plaintiff may proceed to contest the CO’s decision in the instant action. That defense, however, would be limited to the nature of, and the issues present in, the assessment itself—that is, for example, to contest that there was any delay in contract completion.
Where, however, the contractor seeks to contest the assessment of liquidated damages by claiming entitlement to time extensions or other relief, the court is presented with a claim by the contractor against the government and that must first be presented to the CO. {The requirement for certification is not determined based on the amount of liquidated damages being contested but on the amount of money, if any, claimed by the contractor.) See, Z.A.N. Company v. United States, 6 Cl.Ct. 298 (1984). [I]f plaintiff intends—in connection with its contest of the assessment—to raise any issue of relief to which it might be [475] entitled, such as the contractor’s claim of entitlement to time extensions, such claims must first be presented to the CO....
Elgin Builders, 10 Cl.Ct. at 44 (emphasis added).
Z.A.N. involved a setting wherein a government contractor had its contract terminated for default by the CO. The CO subsequently assessed plaintiff with the excess cost of reprocurement. The Claims Court explained:
In addition to the nature and specificity of the claim, it may also be relevant to consider the identity of the party which is asserting the claim, particularly inasmuch as a given circumstance may generate assertions of rights by both parties to the contract____
For example, the assertion of its right to collect liquidated damages by reason of the contractor’s tardiness is clearly a claim by the government against the contractor, and a CO’s decision in this connection is final; this finality is not diminished by any absence of certification by the contractor when it seeks solely to defend against the government’s assertion of its claim for liquidated damages. See Ruhnau-Evans Ruhnau Assoc, v. United States, 3 Cl.Ct. 217 (1983). On the other hand, if the contractor further asserts, in addition to its defense of the government’s claim, its right to additional relief such as extensions of time and/or money ..., then this portion of the dispute may be identified as a claim by the contractor against the government requiring submission in writing and, if in excess of $50,000, certification. See, e.g., Warchol Constr. Co. Inc. v. United States, 2 CI.Ct. 384 (1983).
Z.A.N., 6 Cl.Ct. at 304 (footnote omitted).
In Warchol the contractor sought recovery based on the improper assessment of liquidated damages and differing site conditions. Defendant contended that plaintiff failed to properly certify its claim. The court held:
The contracting officer felt that the liquidated damages of $147,900 for delays attributable to plaintiff was appropriate. Plaintiff believing it was not responsible for any delays, felt that the assessment of liquidated damages in any amount was inappropriate. Before the contracting officer, plaintiff sought time extensions sufficient to cover a period of time that would preclude any assessment of liquidated damages against it. Accordingly, the dispute between the parties centered on responsibility for the delays in the completion of the contract.
Warchol, 2 Cl.Ct. at 393.
After the contracting officer reduced the liquidated damages by $48,000.00, from $147,900.00 to $99,000.00,
[p]laintiff appealed from that decision in Count II of its complaint seeking to recover the $99,000 the contracting officer withheld from it as liquidated damages. Count II of its complaint constitutes a clear refutation of plaintiff’s argument that its claim is not a monetary claim. It is concluded that the claim before the contracting officer and the claim asserted in Count II of the complaint represent a claim that must be certified for purposed of direct access to this cou[r]t.
Id. at 393 (footnotes omitted).
Synthesized, these three Claims Court cases instruct that if a contractor contends that no delay occurred in contract performance, the assessment of liquidated damages is a government claim for which certification is unnecessary. However, if a contractor asserts an entitlement to time extensions or other relief that would offset the assessment of liquidated damages, such a claim is a contractor claim, but only to the extent that the contractor is requesting a set off. To that extent, the contractor must certify its claim before jurisdiction vests in the Claims Court.
The Federal Circuit, however, has simplified the inquiry into when certification is a jurisdictional prerequisite. In Placeway, 920 F.2d 903, the Government withheld $297,226.12 in contract funds from the contractor. Plaintiff submitted an uncertified claim to the contracting officer, seeking recovery for the contract funds. The contracting officer denied the claim, reasoning that plaintiff failed to complete the con[476] tract in a timely fashion. In Count II of its complaint filed in the Claims Court, plaintiff sought recovery of the $297,226.12, plus interest. The Federal Circuit, in holding that the uncertified claim was properly before the Claims Court, adopted the Claims Court’s characterization that the Government’s withholding of contract funds was tantamount to adjusting the contract’s terms. 920 F.2d at 906. This government action constituted a government claim, for which certification was not required. Id.