Aeronetics Division, AAR Brooks & Perkins Corp. v. United States

34 Cont. Cas. Fed. 75,253, 12 Cl. Ct. 132, 1987 U.S. Claims LEXIS 61
CourtUnited States Court of Claims
DecidedApril 9, 1987
DocketNo. 471-86 C
StatusPublished
Cited by18 cases

This text of 34 Cont. Cas. Fed. 75,253 (Aeronetics Division, AAR Brooks & Perkins Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aeronetics Division, AAR Brooks & Perkins Corp. v. United States, 34 Cont. Cas. Fed. 75,253, 12 Cl. Ct. 132, 1987 U.S. Claims LEXIS 61 (cc 1987).

Opinion

DECISION

HORN, Judge.

This case is before the Court on defendant’s motion to dismiss the complaint for lack of jurisdiction. Defendant contends that plaintiff, Aeronetics Division, AAR Brooks & Perkins Corp. (Aeronetics), failed to certify its claim in accordance with Section 6(c)(1) of the Contract Disputes Act of 1978, Pub.L. No. 95-563, 92 Stat. 2383, 41 U.S.C. § 605(c)(1). Plaintiff maintains that its certification meets the requirements of the Act and opposes defendant’s motion.

For the reasons stated below, defendant’s motion to dismiss is hereby granted.

STATEMENT OF FACTS

The facts giving rise to the pending motion to dismiss are as follows. On November 30, 1982, the United States Army Communications Electronics Command (defendant) awarded Aeronetics a contract to manufacture seven hundred and ten (710) directional gyroscopes to Government drawings and specifications, for a total contract price of $3,451,250. The contract provided that the finished product would be made subject to the defendant’s visual inspection.

In its complaint, plaintiff has chronicled a series of events and communications between the parties regarding alleged defects in the specifications for materials to be used in the production. Plaintiff has also alleged certain justifications for plaintiff’s delays in the scheduled delivery of completed gyroscopes, including the defendant’s suspension of progress payments, plaintiff’s suspension of production pending corrective instruction from the defendant after defendant rejected completed gyroscope units for failure to meet the appearance standard, and the defendant’s delay in providing corrective measures. The defendant maintains that the specifications for its materials were valid as originally written and alleges that the defects in the completed units resulted from plaintiff’s use of unspecified materials and improper techniques in the manufacturing process.

On February 7, 1985, plaintiff submitted its initial cost recovery proposal in the amount of $755,286.93 for excess costs incurred to date to defendant’s Administrative Contracting Officer, Joseph Joyce. Plaintiff alleged that the cost recovery proposal related to extraordinary costs, which resulted from the defendant’s defective specifications and failure to provide corrective measures, once plaintiff pointed out the failures. Mr. Joyce responded by letter dated February 11, 1985, in which he summarized the procedures specified in the governing Defense Acquisition Regulations (DAR) 7-103.12 for certification and submission of a claim exceeding $50,000. Mr. Joyce’s letter advised plaintiff to submit a revised claim to the Procuring Contracting [134]*134Officers at “CECOM”, United States Army Communication Electronics Command.

Further communication ensued between the parties regarding a revised delivery schedule and the Government’s summary rejection of eighty completed gyroscope units for failure to meet the visual inspection standards. On May 30, 1985, plaintiff submitted a revised claim to Mr. Joyce. Plaintiff’s claim estimated its defective specification costs to be $2,652,889, assuming the delay continued through December 12, 1985. Plaintiff requested a Final Decision under the Disputes Clause of the contract. Plaintiff’s revised submission was signed by Walter R. Warren, Vice President, and concluded with the following statement under the heading labeled “CERTIFICATION”:

To the best of my knowledge and belief, the attached claim is free from fraud or misrepresentation and fairly reflects the amount the Government owes Aeronetics pursuant to the Contract Disputes Act of 1978, 41 U.S.C. § 601 et seq.

Plaintiff’s revised claim was reviewed by David G. Fieltsch, the Contracting Officer. Mr. Fieltsch issued a Final Decision on July 31, 1985, finding that plaintiff’s claim was not entitled to an equitable adjustment. Subsequently, plaintiff filed suit in this Court seeking review of the Contracting Officer’s Final Decision and the recovery of damages for a breach of contract or, in the alternative, an upward equitable adjustment in the contract price for the revised amount of $2,839,493, plus interest from May 30, 1985.

The defendant has responded to plaintiff’s complaint with a motion to dismiss, arguing that this Court lacks jurisdiction over plaintiff’s suit because the amount sought exceeds $50,000 and plaintiff has failed to follow the procedures required to perfect its claim. Defendant argues that since the Court’s jurisdiction over claims exceeding $50,000 extends only to certified claims, without certification, jurisdiction is lacking.

DISCUSSION

General jurisdiction of this Court to render judgment upon any claim arising under the Contract Disputes Act of 1978 (Contract Disputes Act, 41 U.S.C. §§ 601-613) is conferred by 28 U.S.C. § 1491. However, this general jurisdictional provision is subject to certain procedural requirements of the Contract Disputes Act, which may limit the bases upon which jurisdiction must be predicated. For a contract claim to withstand a jurisdictional challenge, such as has been filed with the Court in defendant’s motion to dismiss, the procedural requirements of the Contract Disputes Act, as well as of 28 U.S.C. § 1491, must be satisfied. The defendant has argued that because plaintiff has failed to comply with the procedural requirements of the Contract Disputes Act, jurisdiction is lacking in this proceeding.

The Contract Disputes Act requires that all claims by contractors against the Government relating to a contract shall be submitted in writing to a contracting officer. 41 U.S.C. § 605(a). Section 605(c)(1) provides, in pertinent part, that:

For claims of more than $50,000, the contractor shall certify that the claim is made in good faith, that the supporting data are accurate and complete to the best of his knowledge and belief, and that the amount requested accurately reflects the contract adjustment for which the contractor believes the government is liable. 41 U.S.C. § 605(c)(1).

Section 605(c)(2) provides that the contracting officer shall issue a decision or notify the contractor when the decision will be issued within sixty days if a certified claim exceeds $50,000.1

Once the requirements of Section 605 have been met, Section 609(a) of the Contract Disputes Act authorizes contractors to bring actions directly in the Claims Court, notwithstanding any rule of law to the contrary. The jurisdictional authority of Section 609(a), therefore, can only be relied on by a plaintiff who has filed a [135]*135properly certified claim and who has received a contracting officer’s decision, or failed to receive one within sixty days, in accordance with Section 605 of the Act.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scan-Tech Security, L.P. v. United States
46 Fed. Cl. 326 (Federal Claims, 2000)
Witherington Construction Corp. v. United States
45 Fed. Cl. 208 (Federal Claims, 1999)
Sipco Services & Marine Inc. v. United States
39 Cont. Cas. Fed. 76,633 (Federal Claims, 1994)
Young Enterprises, Inc. v. United States
26 Cl. Ct. 858 (Court of Claims, 1992)
Alcan Electrical & Engineering Co. v. United States
37 Cont. Cas. Fed. 76,250 (Court of Claims, 1992)
Ingersoll-Rand Co. v. United States
37 Cont. Cas. Fed. 76,248 (Court of Claims, 1991)
Choggiung Ltd. v. United States
37 Cont. Cas. Fed. 76,200 (Court of Claims, 1991)
Cupey Bajo Nursing Home, Inc. v. United States
37 Cont. Cas. Fed. 76,133 (Court of Claims, 1991)
Robin Industries, Inc. v. United States
36 Cont. Cas. Fed. 76,006 (Court of Claims, 1991)
Century Construction Co. v. United States
36 Cont. Cas. Fed. 75,970 (Court of Claims, 1990)
Lakeview Construction Co. v. United States
36 Cont. Cas. Fed. 75,933 (Court of Claims, 1990)
Westech Corp. v. Fireman's Fund Insurance
36 Cont. Cas. Fed. 75,885 (Court of Claims, 1990)
American National Bank & Trust Co. v. United States
36 Cont. Cas. Fed. 75,871 (Court of Claims, 1990)
National Surety Corp. v. United States
36 Cont. Cas. Fed. 75,865 (Court of Claims, 1990)
Spirit Leveling Contractors v. United States
36 Cont. Cas. Fed. 75,770 (Court of Claims, 1989)
Embrey v. United States
35 Cont. Cas. Fed. 75,692 (Court of Claims, 1989)
Gardner Machinery Corp. v. United States
34 Cont. Cas. Fed. 75,441 (Court of Claims, 1988)
Technassociates, Inc. v. United States
34 Cont. Cas. Fed. 75,435 (Court of Claims, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
34 Cont. Cas. Fed. 75,253, 12 Cl. Ct. 132, 1987 U.S. Claims LEXIS 61, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aeronetics-division-aar-brooks-perkins-corp-v-united-states-cc-1987.