Essex Electro Engineers, Inc. v. The United States

702 F.2d 998, 30 Cont. Cas. Fed. 70,904, 1983 U.S. App. LEXIS 13567
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 11, 1983
DocketAppeal 26-82
StatusPublished
Cited by44 cases

This text of 702 F.2d 998 (Essex Electro Engineers, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Essex Electro Engineers, Inc. v. The United States, 702 F.2d 998, 30 Cont. Cas. Fed. 70,904, 1983 U.S. App. LEXIS 13567 (Fed. Cir. 1983).

Opinions

EDWARD S. SMITH, Circuit Judge.

This is an appeal from the decision of the Department of Transportation Contract Appeals Board1 (board), in which the board determined the amount of the uncompensated cost of performance of a contract, terminated for convenience, between the Federal Aviation Administration (FAA) and Essex Electro Engineers (Essex). The board found that Essex was entitled to an equitable adjustment of $124,709 plus interest, but refused additional recovery for burden and profit2 either on materials returned to suppliers or canceled prior to delivery. The board also held that Essex had elected to proceed under the Contract Disputes Act of 19783 (act) and therefore was entitled to interest only from the date it certified its claims pursuant to the act. We affirm in all respects.

I.

On June 15, 1978, the FAA awarded Essex a fixed-price contract (in the amount of $504,142) for 35 diesel engine generator sets. Before commencing production, Essex was to provide drawings and prototype units for Government inspection and testing. Essex was unable to produce prototypes acceptable to FAA contracting officials, and so on March 12, 1979, the contracting officer terminated the contract for default.

Essex appealed the default termination to the board under the disputes clause of the contract on March 14, 1979. The board docketed the appeal on July 16, 1979, and notified Essex in a letter of that date. The board enclosed a copy of its new rules and procedures under the Contract Disputes Act (which had become effective on March 1, 1979), and asked Essex to choose the procedure under which it wanted to proceed. The letter did not refer to the act, but the enclosed rules were headed by a note explaining applicability of the act and of the rules and clearly presenting the option to proceed under the act or to follow the procedures in effect when the contract was entered. By letter dated August 6, 1979, Essex chose to have a hearing before the board under one of the new procedures implementing the act.

On August 15, 1979, Essex filed a complaint with the board, requesting conversion of the default termination to a termination for the convenience of the Government and requesting an equitable adjustment of $327,694 (65 percent of the total contract price) for its uncompensated cost of performance under the contract. Pursuant to an agreement between counsel, Essex submitted a quantum schedule (settlement proposal) to the Government on February 22, 1980, detailing the source of the costs in its complaint. On February 26, 1980, Essex also amended its complaint to add a breach of contract claim for $419,244.

The quantum schedule was treated by the board as a claim submitted to the contracting officer and the Government therefore [1000]*1000requested an order from the board directing Essex to certify its claim pursuant to section 6(c)(1) of the act, 41 U.S.C. § 605(c)(1). Essex contested this motion on the ground that certification was not required by the act under the circumstances; it did not challenge the applicability of the act. The board ordered Essex to file an appropriate certification, and Essex accordingly certified that the complaint and the quantum schedule were accurate and submitted in good faith. The certification was received by the contracting officer on April 12,1980.

Soon after the hearing before the board began, the parties reached a partial settlement agreement in which the default termination was converted into a termination for the convenience of the Government, leaving the board to decide the amount due Essex “as if the Contract had been terminated for the convenience of the Government.” The board found that Essex was not entitled to include the cost of material returned to suppliers or canceled prior to delivery as part of the incurred direct costs of performance for the purpose of calculating burden and profit. The board also held that, by choosing to proceed under the board rules implementing the act, Essex had elected to proceed under the act. Accordingly it held that interest accrued from April 12, 1980, the date on which Essex certified its claims pursuant to section 6(c)(1) of the act.

On appeal we will first address the allow-ability of burden and profit on returned and canceled materials. Having thus resolved the underlying claim, we will turn to the question of when interest begins to accrue under the act, pausing first to consider the threshold issue of the validity of Essex’s election to proceed under the act.

II.

A.

Essex contends that it should be able to recover burden and profit on materials returned for credit to suppliers due to termination of the contract. It argues that the applicable regulations permit it to include the cost of these materials in computing its direct costs of performance recoverable in the case of a termination for convenience. According to Essex, burden should be calculated from the material costs and then profit should be calculated from the material costs plus burden. After these three items (material costs, burden, and profit) are totaled, Essex would deduct the cost of the returned materials as a credit to the Government. The result would be that while Essex never paid for the returned materials, nor used them in performance of the contract, it would still recover formulai-cally derived collateral expenses based on the materials.

In contrast to the complex and lengthy argument that Essex constructs to reach this result, we believe that the matter is rather simply resolved by the relevant Federal Procurement Regulations. The provision that covers return of property to suppliers as a result of a termination for convenience,4 41 C.F.R. § 1-8.502-2 (1982), reads, in pertinent part:

Contractors shall not include in their settlement proposals the cost of such property returned to suppliers in accordance with this paragraph. Contractors may include in their settlement proposals as “other costs” the transportation, handling, and restocking charges with respect to the property so returned.

The regulation is straightforward. Costs not actually incurred are not to be charged to the Government. Therefore materials returned for credit — and thus not paid for by the contractor- — should not be charged. It follows that if the cost of returned materials may not be included, costs based on such materials are also not to be included.

There are, of course, expenses associated with the acquisition and return of materials, which are legitimately part of the direct costs of performance. These are the costs which Essex seeks to recover by [1001]*1001applying burden to the cost of returned materials. Section 1-8.502-2, however, covers these costs with its provision for “other costs.” As the “other costs” — transportation, handling, and restocking charges — are roughly what is covered by burden, the regulation must be construed to replace a percentage charge for burden, because otherwise the contractor could obtain double recovery on these items. The regulations’s requirement of itemization of “other costs”5 also precludes the possibility of a percentage burden. Profit as a cost is simply not allowed by the regulations.

This arrangement is reflected in a companion provision of the Federal Procurement Regulations, 41 C.F.R.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Revive v. Shea-Connelly
Court of Appeals of Arizona, 2021
DODS, Inc.
Armed Services Board of Contract Appeals, 2015
J. Spodek v. USPS
Fifth Circuit, 2014
Spodek v. United States Postal Service
551 F. App'x 781 (Fifth Circuit, 2014)
SUFI Network Services, Inc. v. United States
102 Fed. Cl. 656 (Federal Claims, 2012)
Parker v. United States
77 Fed. Cl. 279 (Federal Claims, 2007)
United States v. Nguyen
847 F. Supp. 496 (S.D. Mississippi, 1994)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
City of Tacoma v. United States
38 Cont. Cas. Fed. 76,532 (Federal Claims, 1993)
Youngdale & Sons Construction Co. v. United States
38 Cont. Cas. Fed. 76,467 (Federal Claims, 1993)
Granite Construction Company v. The United States
962 F.2d 998 (Federal Circuit, 1992)
Isles Engineering & Construction, Inc. v. United States
38 Cont. Cas. Fed. 76,326 (Court of Claims, 1992)
KDH Corp. v. United States
37 Cont. Cas. Fed. 76,087 (Court of Claims, 1991)
Kelley v. United States
36 Cont. Cas. Fed. 75,771 (Court of Claims, 1989)
Dawco Construction, Inc. v. United States
35 Cont. Cas. Fed. 75,755 (Court of Claims, 1989)
Hettich and Company, Gmbh v. The United States
873 F.2d 1451 (Federal Circuit, 1989)
Mark Smith Construction Co. v. United States
34 Cont. Cas. Fed. 75,523 (Court of Claims, 1988)
Mayfair Construction Company v. The United States
841 F.2d 1576 (Federal Circuit, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
702 F.2d 998, 30 Cont. Cas. Fed. 70,904, 1983 U.S. App. LEXIS 13567, Counsel Stack Legal Research, https://law.counselstack.com/opinion/essex-electro-engineers-inc-v-the-united-states-cafc-1983.