Isles Engineering & Construction, Inc. v. United States

38 Cont. Cas. Fed. 76,326, 26 Cl. Ct. 240, 1992 U.S. Claims LEXIS 223, 1992 WL 104537
CourtUnited States Court of Claims
DecidedMay 13, 1992
DocketNo. 90-75C
StatusPublished
Cited by3 cases

This text of 38 Cont. Cas. Fed. 76,326 (Isles Engineering & Construction, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Isles Engineering & Construction, Inc. v. United States, 38 Cont. Cas. Fed. 76,326, 26 Cl. Ct. 240, 1992 U.S. Claims LEXIS 223, 1992 WL 104537 (cc 1992).

Opinion

ORDER

MOODY R. TIDWELL, III, Judge:

This case is before the court on defendant’s motion to dismiss. Defendant alleged that plaintiff failed to comply with the certification requirements of the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (1988) (CDA), and consequently plaintiff’s complaint should be dismissed for lack of subject matter jurisdiction.

FACTS

On September 30, 1986, the United States, acting through the Department of the Navy, awarded a firm-fixed price contract to plaintiff, Isles Engineering & Construction, Inc. (Isles), in the amount of $234,000.00. Isles was to unearth, repair, and rebury certain water mains, valves, and hydrants at Kingsville Naval Air Station, Kingsville, Texas. The Navy provided Isles with plans, supplied by the Navy’s [241]*241contract architect-engineer, which purported to identify the location of the buried mains and valves. The Navy issued a Notice to Proceed on October 14, 1986, and all work was to be completed by February 12, 1987.

The project was delayed because certain pipes could not be found in the locations indicated on the contract drawings, while other pipes were found that were not shown on the drawings. Delays also arose because valves that were needed to cut-off water to certain pipes were not closed in a timely fashion. The contract was substantially completed on April 17, 1987.

Between March and May, 1987, Isles submitted forty-two requests for equitable adjustment totalling $64,063.57 for extra work associated with changes and delays it encountered in performance. Attempts to reach a negotiated settlement of the claims were unsuccessful. On August 14, 1987, the Navy issued unilateral modification P00003 for “unforseen conditions encountered while repairing water mains,” which increased the contract price by $28,515.54, and increased the performance time by 17.3 days. On the same day, the Navy issued modification P00004 which increased the performance time by nineteen days due to weather delays. In the letter accompanying the modifications, the Navy stated that it would also consider further adjustment to the contract for late delivery of twenty-inch gate valves if plaintiff provided sufficient documentation for the delay. The Navy stated that if Isles “disagreed with [defendant] concerning any of the above items, [Isles] may request a final decision by the Contracting Officer following the procedures detailed in Contract Clause 35 (FAR 52.233-1 DISPUTES).”

On September 8, 1987, the Navy reminded plaintiff that the contract required Isles to submit as-built drawings. Defendant also stated that if plaintiff did not intend to submit the information on the tardy twenty-inch gate valves, plaintiff was liable for $2,800.00 in liquidated damages pursuant to the contract. The Navy’s letter also stated that if plaintiff disagreed “with the [defendant’s position] concerning any of the above items, you may request a final decision of the Contracting Officer____” By letter of September 11, 1987, Isles informed the Navy that it did not agree with the “total amounts indicated as increase to the contract,” and that it would assert a “formal claim ... encompassing all aspects of the contract ... not later than 30 days from the date of this letter.” Isles did not submit a claim within its self-imposed thirty-day deadline.

On March 16, 1988, Isles submitted a Request for Equitable Adjustment (REA) in which it sought $184,030.00 in proposed costs for improper assessment of liquidated damages, extended overhead due to delays to the construction schedule, and costs due to defective plans and differing site conditions. The REA was certified, as required for claims to the contracting officer under the CD A, but did not request a contracting officer’s final decision. Instead, the letter requested a meeting within twenty days to discuss the matter, and possible settlement. The contracting officer denied the REA by letter of March 31, 1988, and also stated that because Isles had not forwarded the information requested about the gate valve delay, liquidated damages would accrue as a result. The contracting officer also agreed to release the retainage for the as-built drawings as soon as Isles submitted, and the Navy approved, the drawings. On May 9, 1988, Isles responded, stating that it “formally requested] a final decision by the Contracting Officer at the earliest possible date____” Isles again reiterated its desire to negotiate a solution to the dispute.

On January 25, 1989, the contracting officer issued a final decision under the CD A, denying Isle’s REA and asserting a counterclaim for $10,302.00. The decision stated that $7,800.00 of the counterclaim would be satisfied with the amount of the contract retained to ensure performance. On January 23, 1990, Isles filed its complaint in this court, seeking $184,030.00, plus interest. On April 20, 1991, defendant counterclaimed for the $10,302.00 demanded by the contracting officer.

[242]*242DISCUSSION

For the purposes of a motion to dismiss for lack of subject matter jurisdiction pursuant to RUSCC 12(b)(1), the court must accept as true any undisputed allegations of fact made by plaintiff. Scheuer v. Rhodes, 416 U.S. 232, 236, 94 S.Ct. 1683, 1686, 40 L.Ed.2d 90 (1974). Where there are disputed facts relevant to the issue of jurisdiction, the court is required to decide those facts. Reynolds v. Army and Air Force Exchange Service, 846 F.2d 746, 747 (Fed.Cir.1988). The burden is on plaintiff to establish jurisdiction. Metzger, Shadyac & Schwartz v. United States, 10 Cl.Ct. 107, 109 (1986).

The government argued that Isles’ REA and its letter of May 9, 1988 requesting a final decision of the contracting officer did not constitute a claim within the meaning of the CDA. Alternatively, the government argued that even if these documents did constitute a valid claim under the CDA, they lacked certification and therefore were defective. The court addresses each of these arguments in turn.

The Adequacy of Plaintiff s Claim

The Contract Disputes Act states that “[a]ll claims by a contractor against the government relating to a contract shall be in writing and shall be submitted to the contracting officer for a decision.” 41 U.S.C. § 605(a) (1988). While the CDA does not explicitly enumerate the requirements for a valid claim under the Act, “a claim’s sufficiency may properly be evaluated against regulations implementing the CDA, the language of the contract in dispute, and the facts of the case.” Dawco Constr., Inc. v. United States, 930 F.2d 872, 877 (Fed.Cir.1991). See also Paragon Energy Corp. v. United States, 645 F.2d 966, 227 Ct.Cl. 176 (1981). The United States Court of Appeals for the Federal Circuit has determined that there is

no requirement in the [CDA] that a ‘claim’ must be submitted in any particular form or use any particular wording.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coastal Industries, Inc. v. United States
38 Cont. Cas. Fed. 76,489 (Federal Claims, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
38 Cont. Cas. Fed. 76,326, 26 Cl. Ct. 240, 1992 U.S. Claims LEXIS 223, 1992 WL 104537, Counsel Stack Legal Research, https://law.counselstack.com/opinion/isles-engineering-construction-inc-v-united-states-cc-1992.