Revive v. Shea-Connelly

CourtCourt of Appeals of Arizona
DecidedDecember 28, 2021
Docket1 CA-CV 21-0133
StatusUnpublished

This text of Revive v. Shea-Connelly (Revive v. Shea-Connelly) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Revive v. Shea-Connelly, (Ark. Ct. App. 2021).

Opinion

NOTICE: NOT FOR OFFICIAL PUBLICATION. UNDER ARIZONA RULE OF THE SUPREME COURT 111(c), THIS DECISION IS NOT PRECEDENTIAL AND MAY BE CITED ONLY AS AUTHORIZED BY RULE.

IN THE ARIZONA COURT OF APPEALS DIVISION ONE

REVIVE CONSTRUCTION AND CLEANING, LLC, Plaintiff/Appellant,

v.

SHEA-CONNELLY DEVELOPMENT, LLC, Defendant/Appellee.

No. 1 CA-CV 21-0133 FILED 12-28-2021

Appeal from the Superior Court in Maricopa County No. CV2018-093863 The Honorable Daniel G. Martin, Judge

AFFIRMED

COUNSEL

Zazueta Law PLLC, Scottsdale By Fabian Zazueta, Garrett Respondek Co-Counsel for Plaintiff/Appellant

Degnan Law PLLC, Phoenix By Mark W. Horne, David Degnan Co-Counsel for Plaintiff/Appellant

DKL Law PLLC, Tempe By David W. Lunn, Kathryn A. Lunn Counsel for Defendant/Appellee REVIVE v. SHEA-CONNELLY Decision of the Court

MEMORANDUM DECISION

Presiding Judge Cynthia J. Bailey delivered the decision of the Court, in which Judge Jennifer M. Perkins and Judge Maria Elena Cruz joined.

B A I L E Y, Judge:

¶1 Revive Construction and Cleaning, LLC (“Revive”) appeals the judgment the superior court entered in favor of Shea-Connelly Development (“SCD”) for breach of contract. For the following reasons, we affirm.

FACTS AND PROCEDURAL HISTORY

¶2 SCD contracted with Revive to perform work on two construction projects, the Morningstar building in Glendale (“Glendale Project”) and the Park Place apartment complex in Fountain Hills (“Park Place Project”). After SCD became dissatisfied with Revive’s work on the Park Place Project, it withheld payment on four invoices and terminated both contracts.

¶3 Revive filed a complaint with the Registrar of Contractors (“ROC”) seeking payment of the four invoices. After a hearing, an Administrative Law Judge (“ALJ”) found that SCD violated the Arizona Prompt Pay Act, see Ariz. Rev. Stat. (“A.R.S.”) §§ 32-1181 to -1188; see also A.R.S. § 32-1154(A)(10), (12), by failing to pay the four invoices, which totaled $68,783.25. The ALJ made no findings on SCD’s allegations of faulty work. The ALJ recommended the ROC suspend SCD’s license unless SCD provided documentation that it paid Revive on the four invoices. The ROC adopted the ALJ’s recommendation, and the superior court and the court of appeals affirmed the ROC order. See Shea Connelly Dev. LLC v. Ariz. Registrar of Contractors (“Shea Connelly”), 1 CA-CV 19-0718, 2020 WL 6503616 (Ariz. App. Nov. 3, 2020) (mem. decision).

¶4 Revive then sued SCD seeking further payment on the Glendale Project. SCD counterclaimed to recover the amounts it paid on the Glendale Project and for damages it incurred in repairing Revive’s faulty work on the Park Place Project.

¶5 Revive moved to dismiss SCD’s counterclaim, arguing the ROC’s decision precluded SCD from litigating whether Revive performed

2 REVIVE v. SHEA-CONNELLY Decision of the Court

faulty work on the Park Place Project. The superior court denied the motion, reasoning the ROC did not decide that issue. At a bench trial, the court denied Revive’s motion for a directed verdict and then found for SCD on its breach of contract claim related to the Park Place Project, awarding $57,400 in damages for the amounts SCD paid to repair Revive’s defective work. The court denied both parties’ claims related to the Glendale Project. The court awarded SCD its attorneys’ fees and costs as the prevailing party and denied Revive’s motions for new trial and reconsideration.

¶6 We have jurisdiction over Revive’s timely appeal under Article 6, Section 9, of the Arizona Constitution and A.R.S. §§ 12- 120.21(A)(1) and 12-2101(A)(1).

DISCUSSION

¶7 Revive argues the superior court erred in (1) denying its motion to dismiss the counterclaim on the Park Place Project based on the preclusive effect of the ROC’s order; (2) denying its motion for a directed verdict on SCD’s counterclaim on the Park Place Project; (3) denying its motions for new trial and reconsideration seeking to reduce the judgment by setoff or recoupment; and (4) awarding attorneys’ fees to SCD.

I. Issue Preclusion

¶8 Revive argues the ROC found Revive did not perform faulty work and thus the ROC order precludes SCD’s counterclaim on the Park Place Project.

¶9 We review de novo the superior court’s application of issue preclusion. Crosby-Garbotz v. Fell, 246 Ariz. 54, 56-57, ¶ 9 (2019) (citation omitted). Issue preclusion applies when a fact “was actually litigated in a previous suit, a final judgment was entered, and the party against whom the doctrine is to be invoked had a full opportunity to litigate the matter and actually did litigate it, provided such issue or fact was essential to the prior judgment.” Chaney Bldg. Co. v. City of Tucson, 148 Ariz. 571, 573 (1986) (citations omitted). Courts may apply issue preclusion to a decision of an administrative agency when the agency is acting in a judicial capacity and that decision resolves issues of fact “which the parties have had an adequate opportunity to litigate.” Campbell v. Superior Court, 18 Ariz. App. 287, 290 (1972) (quoting United States v. Utah Constr. & Mining Co., 384 U.S. 394, 422 (1966), superseded by statute on other grounds as recognized in Essex Electro Eng’rs, Inc. v. United States, 702 F.2d 998, 1002 n.7 (Fed. Cir. 1983)); see also J.W. Hancock Enters., Inc. v. Ariz. State Registrar of Contractors, 142 Ariz. 400, 410 (App. 1984) (holding that an ROC finding that the contractor was

3 REVIVE v. SHEA-CONNELLY Decision of the Court

required to install insulation precluded the contractor from bringing a declaratory judgment action on that question).

¶10 Here, the ROC did not assess the quality of Revive’s work on the Park Place Project. It concluded only that SCD violated the Arizona Prompt Pay Act by withholding payment on the four invoices. In that proceeding, the ROC did not permit SCD to litigate its allegation that Revive’s work was faulty. Moreover, the Prompt Pay Act is designed to ensure subcontractors are paid for the work performed, but the general contractor “retains all civil remedies for breach of contract and tort claims against a [sub]contractor” and prompt payment is not “conclusive that the work was properly performed.” Stonecreek Bldg. Co. v. Shure, 216 Ariz. 36, 40, ¶ 18 (App. 2007) (citation omitted). For this reason, the superior court properly declined to apply issue preclusion.

II. Motion for a Directed Verdict

¶11 Revive argues the superior court erred in denying its motion for a directed verdict on SCD’s counterclaim related to the Park Place Project.

¶12 A superior court may grant a motion for a directed verdict “if the facts produced in support of the claim or defense have so little probative value, given the quantum of evidence required, that reasonable people could not agree with the conclusion advanced by the proponent of the claim or defense.” Orme Sch. v. Reeves, 166 Ariz. 301, 309 (1990). We review the court’s ruling on a motion for directed verdict de novo. Warne Invs., Ltd. v. Higgins, 219 Ariz. 186, 194, ¶ 33 (App. 2008). We view the evidence and all reasonable inferences in the light most favorable to the nonmoving party. Id. (citation omitted).

¶13 Through testimony at trial, SCD presented substantial evidence to support its claim that Revive’s work on the Park Place Project was faulty.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Utah Construction & Mining Co.
384 U.S. 394 (Supreme Court, 1966)
Essex Electro Engineers, Inc. v. The United States
702 F.2d 998 (Federal Circuit, 1983)
Chaney Building Co. v. City of Tucson
716 P.2d 28 (Arizona Supreme Court, 1986)
J.W. Hancock Enterprises, Inc. v. Arizona State Registrar of Contractors
690 P.2d 119 (Court of Appeals of Arizona, 1984)
Campbell v. SUPERIOR CT, IN & FOR CTY. OF MARICOPA
501 P.2d 463 (Court of Appeals of Arizona, 1972)
Conant v. Whitney
947 P.2d 864 (Court of Appeals of Arizona, 1997)
Black v. Black
560 P.2d 800 (Arizona Supreme Court, 1977)
Orme School v. Reeves
802 P.2d 1000 (Arizona Supreme Court, 1990)
Orfaly v. Tucson Symphony Society
99 P.3d 1030 (Court of Appeals of Arizona, 2004)
Stonecreek Bldg. Co., Inc. v. Shure
162 P.3d 675 (Court of Appeals of Arizona, 2007)
Warne Investments, Ltd. v. Higgins
195 P.3d 645 (Court of Appeals of Arizona, 2008)
Kent v. Carter-Kent
332 P.3d 56 (Court of Appeals of Arizona, 2014)
Crosby-Garbotz v. Hon. fell/state
434 P.3d 143 (Arizona Supreme Court, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
Revive v. Shea-Connelly, Counsel Stack Legal Research, https://law.counselstack.com/opinion/revive-v-shea-connelly-arizctapp-2021.