Stonecreek Bldg. Co., Inc. v. Shure

162 P.3d 675, 216 Ariz. 36, 509 Ariz. Adv. Rep. 13, 2007 Ariz. App. LEXIS 139
CourtCourt of Appeals of Arizona
DecidedJuly 26, 2007
Docket1 CA-CV 06-0372
StatusPublished
Cited by7 cases

This text of 162 P.3d 675 (Stonecreek Bldg. Co., Inc. v. Shure) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stonecreek Bldg. Co., Inc. v. Shure, 162 P.3d 675, 216 Ariz. 36, 509 Ariz. Adv. Rep. 13, 2007 Ariz. App. LEXIS 139 (Ark. Ct. App. 2007).

Opinion

OPINION

PORTLEY, Judge.

¶ 1 Mavis Shure and Lanny I. Hecker (“Appellants”) appeal from the final judgment in favor of Stonecreek Budding Company and the denial of their motion for new trial. We find that the Prompt Pay Act (“the Act”) was intended to ensure payment to contractors for work acceptably completed and that withholding payment on an invoice which does not charge for any allegedly defective work violates the Act.

FACTUAL AND PROCEDURAL BACKGROUND

¶ 2 Appellants entered into a contract with Stonecreek to construct a custom residence. During construction, Appellants complained of defective workmanship, particularly with the masonry work. Stonecreek, however, assured Appellants that payment would not be made to the masonry contractor until the masonry was corrected to their satisfaction, so they continued to make timely progress payments.

¶ 3 In April 2004, Appellants’ attorney sent a letter to Stonecreek expressing dissatisfaction with the masonry work, as well as the heating, ventilation, and air conditioning system (“HVAC”). Two days later, Appellants received a Pay Application No. 8 (“invoice”) from Stonecreek which was approved by the architect and billed $122,447 for a variety of work, 1 including the HVAC system. Appellants withheld payment of $100,000 of the invoice based on alleged deficiencies in masonry work and the HVAC. Consequently, Stonecreek suspended performance, and Appellants terminated the contract alleging Stonecreek faded to remedy deficiencies in construction.

¶4 Stonecreek filed suit against Appellants. Two days later Appellants filed suit against Stonecreek. The cases were later consolidated.

¶ 5 Among Stonecreek’s claims was that Appellants violated the Act 2 by withholding payment for work that was not listed in the invoice. Stonecreek further alleged that requisite approval of the invoice was satisfied by Appellants, either because of the architect’s certification or because it was “deemed approved” because of Appellants’ failure to file a timely written objection. 3

*38 ¶ 6 Stonecreek filed a motion for partial summary judgment which the trial court granted. Although the court found the April 2004 letter satisfied the statutory requirement of a timely, written objection, it also found that under the Act an owner can withhold payment only to the extent that it disapproves work included in the invoice. The trial court held Appellants were entitled to withhold $26,781 for the disputed HVAC work because, arguably, the work on the invoice was the same as the HVAC work identified in Appellants’ letter. The parties eventually resolved their other claims by a settlement agreement.

¶ 7 In its final judgment, the court awarded Stonecreek $73,219 as damages for the Act violation, which Appellants now appeal, along with the denial of their motion for new trial. We have jurisdiction pursuant to A.R.S. §§ 12-2101(B) and (F) (2003).

DISCUSSION

¶8 The parties stipulated that the sole issue on appeal is whether Appellants were permitted under the Act to withhold payment on an invoice for alleged problems with the masonry work even though the invoice did not request payment for masonry work.

¶ 9 The Prompt Pay Act, A.R.S. §§ 32-1129 to -1129.06, provides in part that an owner shall make progress payments to a contractor “on the basis of a duly certified and approved billing or estimate of the work performed and the materials supplied during the preceding thirty day billing cycle.” A.R.S. § 32-1129.01(A). 4 Those payments are to be made within seven days after the date the billing or estimate is certified and approved. Id. A construction contract cannot alter the rights of a contractor, subcontractor or supplier to receive “prompt and timely progress payments” as provided in the Act. A.R.S. § 32-1129.0KJ).

¶ 10 Appellants argue that they were entitled to withhold payments for work other than that billed in the invoice. Specifically, the Act provides:

A biking or estimate shak be deemed approved and certified fourteen days after the owner receives the bkling or estimate, unless before that time the owner or the owner’s agent prepares and issues a written statement detailing those items in the billing or estimate that are not approved and certified. An owner may decline to approve and certify a billing or estimate or portion of a bkling or estimate for unsatisfactory job progress, defective construction work or materials not remedied, disputed work or materials, fakure to comply with other material provisions of the construction contract, third party claims filed or reasonable evidence that a claim wih be filed, fakure of the contractor or a subeon *39 tractor to make timely payments for labor, equipment and materials, damage to the owner, reasonable evidence that the construction contract cannot be completed for the unpaid balance of the construction contract sum or a reasonable amount for retention.

A.R.S. § 32-1129.0KD).

¶ 11 The first sentence of subsection D provides that a billing is deemed approved unless the owner issues a written statement “detailing those items in the billing” that are not approved. This expressly limits the approval or disapproval to the work covered in a particular bill. However, subsection D also sets forth grounds for disapproval that may not be attributable to a particular billing item, i.e., “unsatisfactory job progress,” “failure to comply with other material provisions of the construction contract,” “third party claims,” and “construction cannot be completed for the unpaid balance ... or a reasonable amount for retention.”

¶ 12 Appellants cite to A.R.S. § 32-1129.01(E) to explain the discrepancy. They argue that an owner “may withhold from a progress payment only an amount that is sufficient to pay the direct expenses the owner reasonably expects to incur to correct any items set forth in writing pursuant to subsection D,” A.R.S. § 32-U29.01(E), and that “any items” refers to items in the owner’s written objection rather than items included in a billing application. Appellants contend it is unreasonable to find the Legislature intended to require an owner to continue to make progress payments after the owner becomes aware of defective work even if that work had previously been approved.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Revive v. Shea-Connelly
Court of Appeals of Arizona, 2021
Shea v. Az Registrar
Court of Appeals of Arizona, 2020
SK Builders, Inc. v. Smith
436 P.3d 519 (Court of Appeals of Arizona, 2019)
Zumar v. Caymus
418 P.3d 936 (Court of Appeals of Arizona, 2017)
Mtr Builders v. Jahan
Court of Appeals of Arizona, 2016
Grand v. Nacchio
217 P.3d 1203 (Court of Appeals of Arizona, 2009)
GRAND v. NACCHIO McMASTER QWEST COMMUNICATIONS
Court of Appeals of Arizona, 2009

Cite This Page — Counsel Stack

Bluebook (online)
162 P.3d 675, 216 Ariz. 36, 509 Ariz. Adv. Rep. 13, 2007 Ariz. App. LEXIS 139, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stonecreek-bldg-co-inc-v-shure-arizctapp-2007.