Shea v. Az Registrar

CourtCourt of Appeals of Arizona
DecidedNovember 3, 2020
Docket1 CA-CV 19-0718
StatusUnpublished

This text of Shea v. Az Registrar (Shea v. Az Registrar) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shea v. Az Registrar, (Ark. Ct. App. 2020).

Opinion

NOTICE: NOT FOR OFFICIAL PUBLICATION. UNDER ARIZONA RULE OF THE SUPREME COURT 111(c), THIS DECISION IS NOT PRECEDENTIAL AND MAY BE CITED ONLY AS AUTHORIZED BY RULE.

IN THE ARIZONA COURT OF APPEALS DIVISION ONE

SHEA CONNELLY DEVELOPMENT LLC, Plaintiff/Appellant,

v.

ARIZONA REGISTRAR OF CONTRACTORS, et al., Defendants/Appellees.

No. 1 CA-CV 19-0718 FILED 11-3-2020

Appeal from the Superior Court in Maricopa County No. LC2019-000048-001 The Honorable Douglas Gerlach, Judge

AFFIRMED

COUNSEL

DKL Law PLLC, Tempe By David W. Lunn Counsel for Plaintiff/Appellant

Arizona Attorney General’s Office, Phoenix By John R. Tellier Counsel for Defendant/Appellee AZ Registrar

Fidelis V. Garcia Attorney at Law, Chandler By Fidelis V. Garcia Counsel for Defendant/Appellee Revive SHEA v. AZ REGISTRAR, et al. Decision of the Court

MEMORANDUM DECISION

Presiding Judge Randall M. Howe delivered the decision of the Court, in which Judge Kent E. Cattani and Judge Cynthia J. Bailey joined.

H O W E, Judge:

¶1 Shea-Connelly Development, LLC (“SCD”) appeals the Arizona Registrar of Contractor’s (“ROC”) suspension of SCD’s contractor’s license for violations of Arizona’s Prompt Pay Act and associated statutes, namely A.R.S. § 32–1183.1 SCD argues that the administrative law judge (“ALJ”) was required to consider offset, accord and satisfaction, and recoupment in making its disciplinary determination to the ROC. For the foregoing reasons, we affirm.

FACTS AND PROCEDURAL HISTORY

¶2 SCD and Revive Construction and Cleaning, LLC (“Revive”) entered construction subcontracts for two different large-scale construction projects. In one, SCD subcontracted Revive to frame the Morningstar Glendale Project (“Glendale Project”) in Glendale. In the other, SCD hired Revive to fix the framing done by a prior sub-contractor at two buildings at the Park Place I Project located in Fountain Hills, Arizona (the “Park Place Project”) The Glendale Project subcontract provided that if Revive defaulted on any contract or subcontract with SCD, it would be deemed to have defaulted on all contracts or subcontracts with SCD. In anticipation of its work at the Glendale Project, Revive submitted an application for payment, SCD paid Revive $58,641.57, and Revive signed a “Conditional Waiver and Release on Progress Payment.” Revive did not, however, perform any work at the Glendale Project.

¶3 The relationship between SCD and Revive deteriorated due to Revive’s work on the Park Place Project. What was initially a $300,000 bid by Revive, turned into invoices totaling over $800,000. SCD sent superintendents to review Revive’s work since Revive was well over budget and the work failed inspections. SCD continued to pay Revive’s weekly invoices until late January, when Revive submitted an invoice for

1 The operative statutes have been redesignated and renumbered from A.R.S. §§ 32–1129 to 32–1129.07 as A.R.S. §§ 32–1181 to 32–1188.

2 SHEA v. AZ REGISTRAR, et al. Decision of the Court

work done solely on things that failed inspection. SCD did not object to that invoice or any subsequent invoices in writing but considered both the Park Place and Glendale Projects subcontracts terminated. At the time of termination, SCD owed Revive for four outstanding invoices from the Park Place Project, #97, #100, #101, and #102, totaling $68,783.25.

¶4 Revive filed a complaint with the ROC claiming SCD owed $68,783.25 for the outstanding invoices. The ROC notified SCD that a complaint had been filed against it, explaining that SCD was “free to raise any issues or affirmative defenses to this complaint . . . .” SCD timely replied that it did not owe Revive because it had made an accord and satisfaction with Revive that mitigated Revive’s damages.

¶5 At the subsequent administrative hearing, SCD’s owner, Bart Shea testified that SCD had terminated the Park Place Project subcontract because of Revive’s inadequate workmanship, which SCD deemed a material default. Because of the cross-default provision in the Glendale Project subcontract, SCD considered Revive in default on the Glendale Project and terminated that subcontract as well. SCD then requested Revive return the Glendale Project payment. Revive refused, and Shea considered those funds payment for the outstanding invoices from January and February in the Park Place Project. Shea further testified that to make the Park Place Project pass inspection, SCD hired another subcontractor to fix Revive’s work. Shea argued that any amount required to fix Revive’s work would offset, or be deducted from, the invoice amount. Therefore, SCD did not owe Revive, but Revive owed SCD.

¶6 Revive’s witness, Rogelio Vazquez, declined to answer questions about the Glendale Project. He did, however, verify the contracts and the unpaid Park Place Project invoices. He further testified that SCD notified Revive that it would not pay the invoices but did not provide any written explanation.

¶7 The ALJ found that SCD provided no written evidence that it paid invoices #97, #100, #101, and #102. She further found that SCD provided no authority to establish that the Registrar considers offsets when assessing whether a contractor has violated the Prompt Pay Act. She made no findings, however, whether she found any witnesses credible, nor any other finding related to offset, recoupment, or accord and satisfaction. The ALJ consequently found that SCD violated both A.R.S. § 32–1154(A)(10) and Arizona’s Prompt Pay Act. Pursuant to A.R.S. § 32–1154(B)(3), the ALJ recommended the ROC suspend SCD’s license until it paid Revive the amount of the invoices it owed, and the ROC adopted the recommendation.

3 SHEA v. AZ REGISTRAR, et al. Decision of the Court

The superior court affirmed the ROC determination on factual grounds, inferring the material facts at issue to affirm the ALJ. SCD timely appealed.

DISCUSSION

¶8 SCD appeals the suspension of its license under A.R.S. 32– 1154(B)(3), arguing that the ALJ’s recommendation and ROC’s determination improperly precluded evidence of offset, recoupment, and accord and satisfaction. We review an administrative action based on an interpretation of law de novo. See Forest Guardians v. Wells, 201 Ariz. 255, 259 ¶9 (2001).

¶9 We interpret statutes to give effect to the legislature's intent, looking first to the statutory language itself. Baker v. Univ. Physicians Healthcare, 231 Ariz. 379, 383 ¶ 8 (2013). When the language is clear and unambiguous, and thus subject to only one reasonable meaning, we apply the language without using other means of statutory construction. State v. Gomez, 212 Ariz. 55, 57 ¶ 11 (2006). Specifically, “[s]tatutory construction requires that provisions of a statute be read and construed in the context of related provisions and in light of its place in the statutory scheme.” Id. at 176. In doing so, we give effect to all provisions of a statute and harmonize those provisions. Sw. Gas Corp. v. Indus. Comm'n, 200 Ariz. 292, 297 ¶ 16 (App. 2001).

I. The ALJ did not abuse her discretion when she rejected SCD’s claim that it had an accord and satisfaction with Revive.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robert Baker v. University Physicians Healthcare
296 P.3d 42 (Arizona Supreme Court, 2013)
Kromko v. Arizona Board of Regents
165 P.3d 168 (Arizona Supreme Court, 2007)
State v. Gomez
127 P.3d 873 (Arizona Supreme Court, 2006)
WJ Kroeger Co. v. Travelers Indemnity Company
541 P.2d 385 (Arizona Supreme Court, 1975)
Morris v. Achen Const. Co., Inc.
747 P.2d 1206 (Court of Appeals of Arizona, 1986)
Stonecreek Bldg. Co., Inc. v. Shure
162 P.3d 675 (Court of Appeals of Arizona, 2007)
Southwest Gas Corp. v. Industrial Commission
25 P.3d 1164 (Court of Appeals of Arizona, 2001)
Jackie Abbott v. Banner Health Network
372 P.3d 933 (Arizona Supreme Court, 2016)
Guardians v. Wells
34 P.3d 364 (Arizona Supreme Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
Shea v. Az Registrar, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shea-v-az-registrar-arizctapp-2020.