Mtr Builders v. Jahan

CourtCourt of Appeals of Arizona
DecidedApril 12, 2016
Docket1 CA-CV 14-0650
StatusUnpublished

This text of Mtr Builders v. Jahan (Mtr Builders v. Jahan) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mtr Builders v. Jahan, (Ark. Ct. App. 2016).

Opinion

NOTICE: NOT FOR OFFICIAL PUBLICATION. UNDER ARIZONA RULE OF THE SUPREME COURT 111(c), THIS DECISION IS NOT PRECEDENTIAL AND MAY BE CITED ONLY AS AUTHORIZED BY RULE.

IN THE ARIZONA COURT OF APPEALS DIVISION ONE

MTR BUILDERS, INC., an Arizona corporation, Plaintiff/Counterdefendant/Appellee/Cross-Appellant,

v.

JAHAN REALTY MANAGEMENT CORPORATION, Defendant/Counterclaimant/Appellant/Cross-Appellee.

No. 1 CA-CV 14-0650 FILED 4-12-2016

Appeal from the Superior Court in Maricopa County No. CV2011-007463 The Honorable Maria Del Mar Verdin, Judge, Retired The Honorable James T. Blomo, Judge

AFFIRMED

COUNSEL

Dickinson Wright PLLC, Phoenix By Denise H. Troy Counsel for Plaintiff/Counterdefendant/Appellee/Cross-Appellant

Wilenchik & Bartness PC, Phoenix By Dennis I. Wilenchik and Tyler Q. Swensen Counsel for Defendant/Counterclaimant/Appellant/Cross-Appellee MTR BUILDERS v. JAHAN Decision of the Court

MEMORANDUM DECISION

Presiding Judge Andrew W. Gould delivered the decision of the Court, in which Judge John C. Gemmill and Judge Margaret H. Downie joined.

G O U L D, Judge:

¶1 MTR Builders Inc. (“Contractor”) and Jahan Realty Management Corporation (“Owner”) both appeal from a jury verdict declaring Owner breached the parties’ contract and awarding Contractor $52,129.18 in damages. For the following reasons we affirm the verdict and rulings of the trial court.

FACTS AND PROCEDURAL BACKGROUND

¶2 In December 2009, Owner and Contractor entered a construction contract to build a shell building for retail space in Tempe. The construction contract contained a draw schedule of five progress payments outlining the amounts Owner would pay Contractor at predetermined stages of construction.1 The project progressed and Contractor reached completion of the fifth and final phase of construction.

¶3 On June 1, 2011, Contractor emailed Owner with an invoice seeking payment of Draw 5 and requesting a final walkthrough. Owner responded via email on June 10 stating that a few outstanding matters needed to be resolved pursuant to the contract before scheduling a final walkthrough; Owner requested issuance of a Certificate of Occupancy by the City of Tempe and final written approval by the Owner’s appointed third-party inspector.

¶4 Owner and its architect, who acted as the third-party inspector, walked through the building and created a punch list that was sent to Contractor on June 29, 2011. Contractor responded on July 12, stating (1) it had remedied all punch-list items for which it was contractually responsible, and (2) requesting Owner’s inspector to re- inspect the property and issue final approval. However, the inspector

1 During the course of construction the parties signed an amendment to the contract extending the completion date and increasing payment to Contractor for various change orders.

2 MTR BUILDERS v. JAHAN Decision of the Court

declined to re-inspect the property unless at Owner’s direction, explaining that he could not sign a certificate of substantial completion without a certificate of completion first being issued by Tempe.

¶5 On July 24, 2011, Contractor informed Owner that it needed a certificate of special inspection to be signed by Owner before Tempe would issue a certificate of completion.2 In the communication, Contractor again requested payment for the work it had performed in the amount of $59,224.18.

¶6 The parties continued to disagree over some items required to complete the contract. Owner required Contractor to test and balance A/C units it installed. Contractor maintained that any outstanding items were warranty items that would be remedied after Owner paid the final payment in completion of the contract. Owner also requested Contractor to provide an unconditional lien waiver indemnifying Owner from any subcontractor claims.

¶7 At one point, Owner obtained a certified check in the amount Contractor was requesting for final payment, and the only outstanding issue appeared to be Contractor’s lien waivers. Additionally, the record shows the City of Tempe did issue a certificate of completion, although both parties were unable to produce the document at trial, and Owner continued to demand that Contractor provide it.3

¶8 Ultimately, the parties’ differences could not be resolved and communication between them broke down. Contractor then filed a complaint for breach of contract against Owner on August 3, 2011.

¶9 Contractor’s complaint alleged Owner had breached its contract, Owner was unjustly enriched thereby, and Owner had violated the Prompt Pay Act in failing to pay Contractor’s invoice. Owner replied

2 Although the contract refers to a certificate of occupancy, both parties agree that what was actually required was a certificate of completion. The building is a shell building that would not be occupied until tenant improvements were performed; therefore, completion of Contractor’s work on the building would be marked by a certificate of completion.

3 We conclude that a certificate of completion was finally issued because Owner admitted it was able to occupy the property.

3 MTR BUILDERS v. JAHAN Decision of the Court

and filed a counterclaim alleging Contractor was the party who had breached.

¶10 Before trial, the parties filed cross-motions for summary judgment on Contractor’s Prompt Pay Act claim. Contractor argued it submitted an invoice requesting final payment pursuant to the Act on June 1, 2011, and Owner had failed to provide a written objection to the billing within the required time. Owner responded that Contractor’s request for final payment was premature. Additionally, Owner claimed it did object to Contractor’s requested billing in its June 10 email response and the punch list generated by its inspector on June 29. Owner also sought dismissal of the unjust enrichment claim because a contract governed the parties’ relationship.

¶11 The court granted summary judgment for Owner on both the Prompt Pay Act and the unjust enrichment claims. The court concluded that Contractor’s request for final payment was premature and that Owner had timely objected in its email and punch list.

¶12 Just before start of trial, Owner filed a motion for judgment as a matter of law. Owner argued the contract contained conditions precedent to final payment that precluded Contractor from prevailing on its breach of contract claim. Owner asserted that Contractor did not obtain the third- party inspector’s final approval or the City of Tempe’s certificate of completion before seeking final payment. Thus, under American Continental Life Insurance Co. v. Ranier Construction Co., 125 Ariz. 53 (1980), Owner concluded it was entitled to judgment as a matter of law.

¶13 The court denied Owner’s motion and proceeded with the trial. During trial, Contractor presented evidence that it had substantially performed its duties under the contract. Further, Contractor showed that the City of Tempe eventually issued a certificate of completion, and Owner was able to occupy the premises. Owner’s expert testified that Contractor had grossly deviated from the contract and the cost of required repairs exceeded the amount of the final payment. Contractor’s rebuttal expert countered that many of the complained-of deficiencies were minor and incidental to any construction project.

¶14 Having found there was sufficient evidence to support both parties’ breach of contract theories, the court instructed the jury on substantial performance and anticipatory breach. The jury returned a verdict in favor of Contractor on its breach of contract claim and awarded

4 MTR BUILDERS v. JAHAN Decision of the Court

$52,129.18 in damages; the jury also entered a verdict denying Owner’s breach of contract claim against Contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Samsel v. Allstate Insurance
59 P.3d 281 (Arizona Supreme Court, 2002)
Hawkins v. State, Dept. of Economic SEC.
900 P.2d 1236 (Court of Appeals of Arizona, 1995)
Gardner v. Royal Development Company
465 P.2d 386 (Court of Appeals of Arizona, 1970)
American Continental Life Insurance v. Ranier Construction Co.
607 P.2d 372 (Arizona Supreme Court, 1980)
Watson Construction Co. v. Reppel Steel & Supply Co.
598 P.2d 116 (Court of Appeals of Arizona, 1979)
Valley National Bank v. Cotton Growers Hail Insurance
747 P.2d 1225 (Court of Appeals of Arizona, 1987)
L. Harvey Concrete, Inc. v. Agro Construction & Supply Co.
939 P.2d 811 (Court of Appeals of Arizona, 1997)
Pioneer Roofing Co. v. Mardian Construction Co.
733 P.2d 652 (Court of Appeals of Arizona, 1986)
Nelson v. Phoenix Resort Corp.
888 P.2d 1375 (Court of Appeals of Arizona, 1994)
Miller v. Crouse
506 P.2d 659 (Court of Appeals of Arizona, 1973)
Dawson v. Withycombe
163 P.3d 1034 (Court of Appeals of Arizona, 2007)
In Re Estate of Lamparella
109 P.3d 959 (Court of Appeals of Arizona, 2005)
Stonecreek Bldg. Co., Inc. v. Shure
162 P.3d 675 (Court of Appeals of Arizona, 2007)
Grosvenor Holdings, L.C. v. Figueroa
218 P.3d 1045 (Court of Appeals of Arizona, 2009)
Greenwood v. State
175 P.3d 687 (Court of Appeals of Arizona, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Mtr Builders v. Jahan, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mtr-builders-v-jahan-arizctapp-2016.