Watson Construction Co. v. Reppel Steel & Supply Co.

598 P.2d 116, 123 Ariz. 138, 1979 Ariz. App. LEXIS 529
CourtCourt of Appeals of Arizona
DecidedJune 12, 1979
Docket1 CA-CIV 3744
StatusPublished
Cited by19 cases

This text of 598 P.2d 116 (Watson Construction Co. v. Reppel Steel & Supply Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Watson Construction Co. v. Reppel Steel & Supply Co., 598 P.2d 116, 123 Ariz. 138, 1979 Ariz. App. LEXIS 529 (Ark. Ct. App. 1979).

Opinion

OPINION

HAIRE, Judge.

The basic issue on this appeal is whether a general contractor is liable to its subcontractor for breach of contract when the underlying construction project is terminated prior to its completion. The action in the trial court originated when Amfac Mortgage Corporation filed its complaint in foreclosure after construction had stopped on what was intended to be a regional shopping center in Tempe, Arizona. Although numerous other claims and parties were involved in the trial court proceedings the questions on this appeal concern only the general contractor, Watson Construction Co., and its.steel subcontractor, Reppel *140 Steel & Supply Co., Inc. Both Watson and Reppel were defendants in the foreclosure proceedings because they had filed lien claims against the subject real property. Defendant Reppel filed a cross-claim against defendant Watson for damages for breach of three separate subcontracts relating to the furnishing and erection of steel for the project. After considerable discovery, the trial court granted summary judgment in Reppel’s favor and against the general contractor in the amount of $1,714,-846.59.

On appeal from that summary judgment Watson contends that because of specific provisions in the subcontracts, it never became liable to Reppel, but that in any event, even if it became liable, there were genuine issues of material fact relating to the question of damages which precluded summary judgment.

Considering first the issue of liability, Watson contends that the subcontractor had no right to receive payment from the general contractor unless and until the general contractor had received payment from the owner. 1 The essence of this argument is that the subcontractor agreed to look exclusively to such fund for payment, and that the existence of such fund therefore became a condition precedent to liability on the part of the general contractor to the subcontractor.

The provisions of the subcontracts that Watson relies upon in support of its condition-precedent argument are as follows:

“THE CONTRACTOR AGREES AS FOLLOWS:
‡ * * * sf: *
“C. ... to pay the Sub-Contractor, promptly upon receipt thereof from the Owner, the amount received by the Contractor on account of the Sub-Contractor’s work to the extent of the SubContractor’s interest therein.
“D. ... At all times subcontractor shall be paid to the extent that the contractor has been paid on his account.”

Reppel urges that the above-quoted provisions of the subcontracts do not create a condition precedent conditioning the general contractor’s obligations so as to limit Reppel’s right of recovery to a fund created by the owner’s payment to the general contractor. Rather, Reppel urges, the subcontract agreements created fixed obligations with the quoted provisions merely providing a convenient or normal time for payment. We agree that the trial court correctly resolved this issue in favor of Reppel.

As a general rule conditions precedent are not favored and the courts are not inclined to construe a contractual provision as a condition precedent unless such construction is plainly and unambiguously required by the language of the contract. See Minthorne v. Seeburg Corp., 397 F.2d 237 (9th Cir. 1968), cert. denied 397 U.S. 1036, 90 S.Ct. 1357, 25 L.Ed.2d 647 (1970); Restatement of Contracts § 261 (1932). Although we have not found any case involving contractual language identical to that contained in the subcontracts before this Court, we have reviewed several decisions involving similar provisions, and the majority hold, as a matter of law, that no condition precedent limiting recovery to a specific fund is created by provisions of this nature.

The Arizona decision most squarely in point is Darrell T. Stuart Contractor of Arizona v. J. A. Bridges & Rust-Proofing, Inc., 2 Ariz.App. 63, 406 P.2d 413 (1965). That decision involved an action by a sub-subcontractor to recover the balance claimed due from a subcontractor under an assumption agreement. The sub-subcontractor had agreed to perform work that the subcontractor had originally contracted to perform. The subcontract contained the following provision:

“The contractor shall pay the subcontractor’s pay estimate (less ten percent (10%) retainage within ten days after receipt of payment by the contractor and as allowed by the Government. The 10% *141 retainage shall be paid to the subcontractor upon completion of all work required of the contractor, and final acceptance and payment by the government.”
2 Ariz.App. at 64, 406 P.2d at 414.

In addition, the assumption agreement provided:

“5. Payments to be made to the sub-sub-contractor (assumption agreement) ‘shall be made within ten (10) days after receipt of payments by Darell T. Stuart Contractor of Arizona from Dale Benz, Inc., — J. W. Wells — B. H. Oates under the subcontract marked Exhibit “A” and attached hereto.’ ”
2 Ariz.App. at 64, 406 P.2d at 414 (Emphasis added).

The sole issue was whether the above-quoted paragraph 5 constituted a condition precedent which barred the plaintiff’s recovery until 10 days after receipt of payment by the defendant subcontractor from the general contractor. The Court held that the plaintiffs had not agreed to look to a specific fund from which, and only from which, payment was to be made, and quoted extensively from a leading decision in this area, Thomas J. Dyer Co. v. Bishop International Engineering Co., 303 F.2d 655 (6th Cir. 1962), as follows:

“It is, of course, basic in the construction business for the general contractor on a construction project of any magnitude to expect to be paid in full by the owner for the labor and material he puts into the project. * * * The solvency of the owner is a credit risk necessarily incurred by the general contractor, * *. This expectation and intention of being paid is even more pronounced in the case of a subcontractor whose contract is with the general contractor, not with the owner. * * * he is primarily interested in the solvency of the general contractor with whom he has contracted. He looks to him for payment. Normally and legally, the insolvency of the owner will not defeat the claim of the subcontractor against the general contractor. Accordingly, in order to transfer this normal credit risk incurred by the general contractor from the general contractor to the subcontractor, the contract between the general contractor and subcontractor should contain an express condition clearly showing that to be the intention of the parties.”
Darrell T. Stuart Contractor of Arizona, supra, 2 Ariz.App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mtr Builders v. Jahan
Court of Appeals of Arizona, 2016
flash/schillinger v. Samons
Court of Appeals of Arizona, 2015
Cumis Ins. Society, Inc. v. Merrick Bank Corp.
680 F. Supp. 2d 1077 (D. Arizona, 2010)
L. Harvey Concrete, Inc. v. Agro Construction & Supply Co.
939 P.2d 811 (Court of Appeals of Arizona, 1997)
Nadel v. Nadel
105 F.3d 665 (Ninth Circuit, 1996)
Barnes v. Wood
750 P.2d 1226 (Court of Appeals of Utah, 1988)
Valley National Bank v. Cotton Growers Hail Insurance
747 P.2d 1225 (Court of Appeals of Arizona, 1987)
Pioneer Roofing Co. v. Mardian Construction Co.
733 P.2d 652 (Court of Appeals of Arizona, 1986)
Realty Associates v. Valley National Bank
738 P.2d 1121 (Court of Appeals of Arizona, 1986)
World Wide Lease, Inc. v. Woodworth
728 P.2d 769 (Idaho Court of Appeals, 1986)
Autonumerics, Inc. v. Bayer Industries, Inc.
696 P.2d 1330 (Court of Appeals of Arizona, 1984)
Norton v. Herron
677 P.2d 877 (Alaska Supreme Court, 1984)
Clark v. St. Paul Property & Liability Insurance Companies
639 P.2d 454 (Idaho Supreme Court, 1981)
Peterson v. Wirum
625 P.2d 866 (Alaska Supreme Court, 1981)
American Drilling Service Co. v. City of Springfield
614 S.W.2d 266 (Missouri Court of Appeals, 1981)
AMFAC Mortgage Corp. v. Arizona Mall of Tempe, Inc.
618 P.2d 240 (Court of Appeals of Arizona, 1980)
Continental Life & Accident Co. v. Songer
603 P.2d 921 (Court of Appeals of Arizona, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
598 P.2d 116, 123 Ariz. 138, 1979 Ariz. App. LEXIS 529, Counsel Stack Legal Research, https://law.counselstack.com/opinion/watson-construction-co-v-reppel-steel-supply-co-arizctapp-1979.