Riley Construction Co. v. Schillmoeller & Krofl Co.

236 N.W.2d 195, 236 N.W.2d 196, 70 Wis. 2d 900, 1975 Wisc. LEXIS 1377
CourtWisconsin Supreme Court
DecidedDecember 19, 1975
Docket50-52 (1974)
StatusPublished
Cited by15 cases

This text of 236 N.W.2d 195 (Riley Construction Co. v. Schillmoeller & Krofl Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Riley Construction Co. v. Schillmoeller & Krofl Co., 236 N.W.2d 195, 236 N.W.2d 196, 70 Wis. 2d 900, 1975 Wisc. LEXIS 1377 (Wis. 1975).

Opinion

Wilkie, C. J.

This appeal involves three summary judgments in favor of the plaintiff-subcontractors, Riley Construction Company, Arnold P. Johnson, Inc., and Stanley J. Matson, against the defendant-surety, Argonaut Insurance Company, on a payment bond given by the insurance company and the general contractor, Schill-moeller & Krofl Company, Inc.

Summary judgment should not have been granted. It was reversible error for the trial court to impose liability upon Argonaut as surety without even considering whether or not the principal under the bond, the general contractor, was liable for payment under the subcontract. Consideration of the general contractor’s defense to liability under the subcontract would necessarily involve factual issues and, thus, make summary judgment an inappropriate remedy.

The general contractor entered into a contract on July 14, 1971, with the owner and developer of land located in Kenosha, Wisconsin. The contract provided for the construction of condominium apartments to be known as Harbor Villa. Subsequently, the general contractor made contracts with the three subcontractors for various work to be done on the project. The agreement with Riley was made on July 8, 1971; the agreement with Johnson, on July 21, 1971; and the agreement with Matson, on September 24, 1971. All three contracts contained the same provisions regarding payment:

“General Contractor agrees to pay Sub-contractor, if Sub-contractor shall fulfill to the satisfaction of General Contractor and Architect and complete every agreement on its part herein contained, for the performance of the contract, price of ... as follows:
*903 “ ‘During the satisfactory progress of the work and after receipt of satisfactory evidence of Sub-contractor’s payment for labor and material furnished by Sub-contractor, on or before the 10th day of each month, Ninety per cent (90%) of the value of labor and materials wrought into the building up to the 1st day of each month as estimated by General Contractor and subject to the approval of Architect, less aggregate amount of previous payments, if any, after such equivalent payment has been received by General Contractor from Owner. Final payment shall be due within thirty (30) days after completion of the building or project and after final payment is made by Owner to General Contractor. No claim for extras will be allowed unless authorized in advance in writing by General Contractor.’ ”

The general contractor and the insurance company, as principal and surety, respectively, gave a payment bond on November 9, 1971, which provided in relevant part as follows:

“Now, Therefore, the Condition of this Obligation is such that if the Principal shall promptly make payment to all claimants as hereinafter defined, for all labor and material used or reasonably required for use in the performance of the Contract, then this obligation shall be void; otherwise it shall remain in full force and effect, subject, however, to the following conditions:
“2. The above named Principal and Surety hereby jointly and severally agree with the Owner that every claimant as herein defined, who has not been paid in full before the expiration of a period of ninety (90 days) days after the date on which the last of such claimant’s work or labor was done or performed, or materials were furnished by such claimant, may sue on this bond for the use of such claimant, prosecute the suit to final judgment for such sum or sums as may be justly due claimant, and have execution thereon. The Owner shall not be liable for the payment of any costs or expenses of any such suit.”

The three subcontractors afterward performed the work they had agreed to, and there is no question that it was completed according to the specifications of the *904 subcontracts. However, the owner never paid the general contractor the full amount for this work. The general contractor, relying upon the subcontractual provision of no payment until equivalent amounts were received from the owner, in turn did not pay the subcontractors the full amount for their work.

On July 2, 1973, the three subcontractors, as claimants under the bond, commenced separate legal actions against the general contractor and the insurance company. Riley sought judgment in the amount of $54,579.43; Johnson, in the amount of $13,873.92; and Matson, in the amount of $6,310. These actions were consolidated for trial and the subcontractors were granted summary judgment against the insurance company alone.

I. Liability of the surety.

In its answer to the complaint, and in its affidavit in opposition to the motion for summary judgment, the surety asserted the defense that it was not liable on the bond because the principal-general contractor was not liable on the subcontracts for the payment of which the bond was given. The basis of this defense was the sub-contractual provision that payment was not to be made to the subcontractors until a certain time after it was received from the owner. The surety (as had the general contractor in its answer) argued that this provision established a condition precedent, and did not merely fix a time for payment. During the argument on the motion for summary judgment, the surety also offered to provide specific evidence at a later trial regarding the circumstances under which the subcontract was made, which would show that the general contractor and the subcontractor intended to share the risk of nonpayment by the owner.

The trial court, however, limited its consideration to the provisions of the surety bond. It refused to allow the surety to assert a defense which the general contractor had under the subcontracts, and to even consider these *905 subcontracts or the liability of the general contractor thereunder. The basis for its grant of summary judgment was its interpretation of the surety bond, exclusive of the subcontracts it was given to secure. The trial court decided that the surety became absolutely liable for payment to the subcontractors after ninety days had passed without payment by the general contractors, irrespective of whether the general contractor was liable to the subcontractors under the subcontracts.

But the law of suretyship is to the contrary. Because the surety’s obligation is derived from that of the principal debtor, the liability of the surety is ordinarily measured by the liability of the principal. If the principal is not liable to the claimant, then the surety is not liable either. In addition, the surety may normally set up any defense available to the principal. 1 Although Wisconsin has never enunciated these precise rules, cases decided in other jurisdictions have unanimously followed them. 2 In Wisconsin this court has long adhered to a rule which is thoroughly consistent with these rules, namely, that the bond and the contract which it secures should be construed together. 3 Thus, the conclusion is inescapable *906

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Milwaukee Board of School Directors v. BITEC, Inc.
2009 WI App 155 (Court of Appeals of Wisconsin, 2009)
Capitol Steel Fabricators, Inc. v. Mega Constr. Co.
58 Cal. App. 4th 1049 (California Court of Appeal, 1997)
Koch v. Construction Technology, Inc.
924 S.W.2d 68 (Tennessee Supreme Court, 1996)
Energy Complexes, Inc. v. Eau Claire County
449 N.W.2d 35 (Wisconsin Supreme Court, 1989)
Hopkins v. INA Underwriters Insurance
542 N.E.2d 679 (Ohio Court of Appeals, 1988)
Nagle Hart, Inc. v. United Pacific Insurance
417 N.W.2d 36 (Court of Appeals of Wisconsin, 1987)
Waukesha Concrete Products Co. v. Capitol Indemnity Corp.
379 N.W.2d 333 (Court of Appeals of Wisconsin, 1985)
H. H. Robertson Co. v. Lumbermen's Mutual Casualty Co.
94 F.R.D. 578 (W.D. Pennsylvania, 1982)
Maynard v. Port Publications, Inc.
297 N.W.2d 500 (Wisconsin Supreme Court, 1980)
Lake View Trust & Savings Bank v. Filmore Construction Co.
393 N.E.2d 714 (Appellate Court of Illinois, 1979)
Watson Construction Co. v. Reppel Steel & Supply Co.
598 P.2d 116 (Court of Appeals of Arizona, 1979)
City of Madison v. Ayers
271 N.W.2d 101 (Wisconsin Supreme Court, 1978)
Amelco Electric v. Donald M. Drake Co.
583 P.2d 648 (Court of Appeals of Washington, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
236 N.W.2d 195, 236 N.W.2d 196, 70 Wis. 2d 900, 1975 Wisc. LEXIS 1377, Counsel Stack Legal Research, https://law.counselstack.com/opinion/riley-construction-co-v-schillmoeller-krofl-co-wis-1975.