Milwaukee Board of School Directors v. BITEC, Inc.

2009 WI App 155, 775 N.W.2d 127, 321 Wis. 2d 616, 2009 Wisc. App. LEXIS 707
CourtCourt of Appeals of Wisconsin
DecidedSeptember 9, 2009
Docket2008AP3022
StatusPublished
Cited by1 cases

This text of 2009 WI App 155 (Milwaukee Board of School Directors v. BITEC, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Milwaukee Board of School Directors v. BITEC, Inc., 2009 WI App 155, 775 N.W.2d 127, 321 Wis. 2d 616, 2009 Wisc. App. LEXIS 707 (Wis. Ct. App. 2009).

Opinion

CURLEY, P.J.

¶ 1. Milwaukee Board of School Directors (MBSD) appeals the order granting summary judgment to Atlantic Mutual Insurance Company (Atlantic Mutual). 1 At issue is whether Atlantic Mutual in its capacity as surety on a performance bond is liable for its principal's, Specialty Associates, Inc., n/k/a GRS Wisconsin Inc. (SAI), warranty obligations under the construction contract. We agree with MBSD that Atlantic Mutual would be liable if SAI is found at fault. *619 Accordingly, we reverse that portion of the trial court's ruling at summary judgment dismissing MBSD's claims against Atlantic Mutual and remand for further proceedings consistent with this decision.

I. Background.

¶ 2. In late summer 2002, MBSD solicited bids for the replacement of the roof at the Cooper Elementary School in Milwaukee, Wisconsin. MBSD sent bid documents to potential bidders providing them with information regarding the scope of the project. Included within these documents was the provision that the bidder would be required to obtain a performance bond. In addition, the general conditions of the bid documents specified: "Article 12. MATERIALS AND WORKMANSHIP: . . . All Work of every kind shall be delivered upon completion of the Project in a perfect and undamaged condition, free of flaws or defects."

¶ 3. In September 2002, MBSD contracted with SAI to install the new roofing system. SAI was to receive $361,495 as payment for the project. As required by the bid documents, Atlantic Mutual provided the performance bond on the project as SAI's surety. Atlantic Mutual was also a party to the contract, which incorporated the bid documents and SAI's proposal.

¶ 4. SAI completed the project by December 26, 2002, and issued a "Five Year Limited Roof Warranty" to MBSD. This went into effect for five years, starting on December 26, 2002. MBSD made its final payment to SAI in February 2003.

¶ 5. In the summer of 2005, MBSD noticed problems with the roof. In November 2007, MBSD filed suit against BITEC (the supplier of the roofing materials involved), BITEC's insurer, SAI, and SAI's insurer. After *620 filing suit, MBSD learned that it could not obtain relief from SAI because SAI was bankrupt and had obtained a discharge of any obligation to MBSD. MBSD then amended its complaint and sued Atlantic Mutual, which, as noted, issued a performance bond for the project. In its amended complaint, MBSD alleged: "SAI, Atlantic's principal, breached its contract obligations by, among other things, failing to properly install the roofing materials, failing to inspect work completely and properly, and allowing insufficient adhesion of materials that allowed water and weather to infiltrate and cause damage to the building roof and structure."

¶ 6. Atlantic Mutual subsequently moved for summary judgment on grounds that its duties under the original roofing contract had "long ago" expired and on the basis that it was not a party to the five-year limited roof warranty issued by SAI. Its motion was granted. MBSD now appeals. The specific contractual language at issue will be provided in the remainder of this opinion.

II. Analysis.

A. Standard of review.

¶ 7. This case was decided on summary judgment; thus, our review is de novo. See Green Spring Farms v. Kersten, 136 Wis. 2d 304, 315-17, 401 N.W.2d 816 (1987). Summary judgment is appropriate when there is no genuine issue as to any material fact and the moving party is entitled to judgment as a matter of law. Wis. Stat. § 802.08(2). Further, Atlantic Mutual is a paid surety; as such, its contract is interpreted and applied as an insurance contract. See Wiegel v. Sentry *621 Indem. Co., 94 Wis. 2d 172, 179, 287 N.W.2d 796 (1980) (explaining that "the contracts of [p]aid sureties are to be treated as insurance contracts"). Our review of a trial court's interpretation of a contract is also de novo. Teacher Ret. Sys. of Texas v. Badger XVI Ltd. P'ship, 205 Wis. 2d 532, 555, 556 N.W.2d 415 (Ct. App. 1996). In this regard, the following principles guide our analysis:

The lodestar of contract interpretation is the intent of the parties. In ascertaining the intent of the parties, contract terms should be given their plain or ordinary meaning. If the contract is unambiguous, our attempt to determine the parties' intent ends with the four corners of the contract, without consideration of extrinsic evidence.

Huml v. Vlazny, 2006 WI 87, ¶ 52, 293 Wis. 2d 169, 716 N.W.2d 807 (citations omitted).

B. Atlantic Mutual is liable under its performance bond.

¶ 8. MBSD argues that Atlantic Mutual is liable under the performance bond, which did not expire when the roof was installed, and further asserts that, due to the coextensive nature of Atlantic Mutual's and SAI's liability, Atlantic Mutual liability "includes performance to correct latent defects over the same time period for which its principal is liable." Atlantic Mutual disagrees, contending that its liability under the bond for post-completion obligations is limited by contractual language requiring a one-year warranty. Because the problems with the roof were discovered after the expiration of that period, Atlantic Mutual asserts that it is not liable.

*622 ¶ 9. "The rule in Wisconsin is that a surety's obligation is derived from its principal and the liability of the surety is measured by the liability of the principal." Waukesha Concrete Prods. Co. v. Capitol Indem. Corp., 127 Wis. 2d 332, 339, 379 N.W.2d 333 (Ct. App. 1985); see also Riley Constr. Co. v. Schillmoeller & Krofl Co., 70 Wis. 2d 900, 905, 236 N.W.2d 195 (1975) ("Because the surety's obligation is derived from that of the principal debtor, the liability of the surety is ordinarily measured by the liability of the principal. If the principal is not liable to the claimant, then the surety is not liable either."). "The bond issued by the surety and the contract which it secures should be construed together." Waukesha Concrete, 127 Wis. 2d at 339.

¶ 10. Reviewing the performance bond first, we note that it incorporates the underlying construction contract insofar as it is conditioned upon SAI's faithful performance of its contractual obligations. The performance bond reads, in relevant part:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blenker Bldg. Sys., Inc. v. Array Fin. Servs.
340 F. Supp. 3d 792 (W.D. Wisconsin, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
2009 WI App 155, 775 N.W.2d 127, 321 Wis. 2d 616, 2009 Wisc. App. LEXIS 707, Counsel Stack Legal Research, https://law.counselstack.com/opinion/milwaukee-board-of-school-directors-v-bitec-inc-wisctapp-2009.