Holmen Concrete Products Co. v. Hardy Construction Co.

2004 WI App 165, 686 N.W.2d 705, 276 Wis. 2d 126, 2004 Wisc. App. LEXIS 608
CourtCourt of Appeals of Wisconsin
DecidedJuly 29, 2004
Docket03-3335
StatusPublished
Cited by1 cases

This text of 2004 WI App 165 (Holmen Concrete Products Co. v. Hardy Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holmen Concrete Products Co. v. Hardy Construction Co., 2004 WI App 165, 686 N.W.2d 705, 276 Wis. 2d 126, 2004 Wisc. App. LEXIS 608 (Wis. Ct. App. 2004).

Opinion

DYKMAN, J.

¶ 1. The Village of Readstown appeals from a summary judgment granted to plaintiffs, Holmen Concrete Products Company and Iverson Construction Company. The circuit court concluded that the Village was responsible for damages resulting from its failure to ensure that a prime contractor had obtained a payment and performance bond under Wis. *130 Stat. § 779.14. 1 The Village asserts it had no duty to assure that the contractor secured a bond because a 1997 revision of § 779.14 deleted this requirement. It also claims that this action is time barred because it was not commenced within twenty days after the Village notified Holmen and Iverson of what fraction of the outstanding amounts it planned to pay each as required by Wis. Stat. § 779.15(4)(a). 2

*131 ¶ 2. We conclude that a municipality is responsible for failure to ensure that a prime contractor obtains a payment bond because the 1997 statutory revision did not remove liability for breach of this duty as explained in Cowin & Co., Inc. v. City of Merrill, 202 Wis. 614, 233 N.W. 561 (1930). Further, we conclude that the twenty-day statute of limitations set forth in Wis. Stat. § 779.15(4)(a) is inapplicable to a cause of action against a municipality for failure to ensure the acquisition of a bond. Therefore, we affirm.

BACKGROUND

¶ 3. In 2001, the Village of Readstown contracted with Hardy Construction Company to be the prime contractor on a construction project known as the Wisconsin Avenue Corridor and Charles Street renovation project. The Village's contract with Hardy required the contractor to obtain a payment and performance bond. Hardy subcontracted with Holmen to provide materials, and with Iverson to provide materials and labor on the project. Holmen and Iverson performed their obligations under the agreement, but Hardy failed to pay them. Holmen and Iverson then submitted claims to the Village of $85,859.10 and $81,279.12, respectively, for unpaid materials and labor.

¶ 4. In late 2001, Village staff became aware that the Village failed to ensure that Hardy had acquired an appropriate payment and performance bond. By letter dated January 24, 2002, the Village informed Holmen and Iverson and other project subcontractors that a bond may not have been issued to Hardy. The letter also outlined the partial payments the Village determined *132 would be paid to each subcontractor. On February 25, 2002, the Village paid Holmen $44,295 and Iverson $41,932.

¶ 5. On May 2, 2002, Holmen and Iverson each gave the Village written notice of their claims against it. On August 30, 2002, they sued Hardy and the Village to recover the unpaid portion of the contracts. They asserted claims of breach of contract against Hardy, claims to enforce their respective liens against public funds under Wis. Stat. § 779.15, and claims for damages stemming from the Village's failure to require Hardy to furnish a payment and performance bond as required by Wis. Stat. § 779.14(lm).

¶ 6. The Village filed a motion for summary judgment contending that Holmen's and Iverson's claims against the Village were barred by the limitations period set forth in Wis. Stat. § 779.15(4)(a), which the Village asserted was triggered by its January 24, 2002 letter. Holmen and Iverson also filed a motion for summary judgment seeking a determination holding the Village liable to the plaintiffs for failure to require or approve a performance and payment bond of Hardy as required by statute.

¶ 7. The trial court denied the Village's motion for summary judgment, and granted Holmen and Iverson's motion for summary judgment. The Village appeals.

STANDARD OF REVIEW

[13

¶ 8. We review a grant or denial of a motion for summary judgment de novo. State Farm Mut. Auto. Ins. Co. v. Langridge, 2004 WI 113, ¶ 12, 275 Wis. 2d 35, 683 N.W.2d 75. Summary judgment methodology is well established and need not be repeated here. See, e.g., *133 Lambrecht v. Estate of Kaczmarczyk, 2001 WI 25, ¶¶ 20-24, 241 Wis. 2d 804, 623 N.W.2d 751.

DISCUSSION

¶ 9. Our review of the circuit court's grant of summary judgment in this case turns entirely on our interpretation of the validity of Holmen's and Iverson's claims against the Village. Whether a complainant alleges a valid claim is a question of law for the court to decide. Powell v. Cooper, 2001 WI 10, ¶ 10, 241 Wis. 2d 153, 622 N.W.2d 265. The validity of Holmen's and Iverson's claims rests on our interpretation of certain provisions of the lien statutes for public contracts. Statutory interpretation is a question of law that we review de novo. Donaldson v. Board of Commissioners of Rock-Koshkonong Lake District, 2004 WI 67, ¶ 15, 272 Wis. 2d 146, 680 N.W.2d 762.

¶ 10. Our interpretative task here involves two issues. The first is whether, under Wis. Stat. § 779.14, a municipality is liable to unpaid subcontractors if the municipality fails to ensure that a prime contractor secures a payment and performance bond. The second is, assuming liability exists under § 779.14, whether resulting claims are subject to the time bar set forth in Wis. Stat. § 779.15(4)(a). We address each issue in turn.

¶ 11. The Wisconsin Supreme Court held in Cowin that a municipality is liable to a subcontractor if the municipality fails to require a prime contractor to furnish the municipality with a bond. 202 Wis. at 617. In Cowin, a firm that had contracted for road construction with the City of Merrill became insolvent and failed to pay its subcontractors. Id. at 614. The City had neglected to obtain from the prime contractor a bond to *134 ensure the payment of labor and materials to subcontractors, as required by former Wis. Stat. § 289.16 (1927). Id. at 614-15. Section 289.16 provided:

(1) All contracts involving one hundred dollars or more ... when the same pertains to or is for ... any ... public improvement, public road ... of whatsoever kind of the state, or of any county, city . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Milwaukee Board of School Directors v. BITEC, Inc.
2009 WI App 155 (Court of Appeals of Wisconsin, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
2004 WI App 165, 686 N.W.2d 705, 276 Wis. 2d 126, 2004 Wisc. App. LEXIS 608, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holmen-concrete-products-co-v-hardy-construction-co-wisctapp-2004.