Zumar v. Caymus

418 P.3d 936
CourtCourt of Appeals of Arizona
DecidedNovember 16, 2017
Docket1 CA-CV 16-0423
StatusPublished

This text of 418 P.3d 936 (Zumar v. Caymus) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zumar v. Caymus, 418 P.3d 936 (Ark. Ct. App. 2017).

Opinion

IN THE ARIZONA COURT OF APPEALS DIVISION ONE

ZUMAR INDUSTRIES, INC., Plaintiff/Appellee,

v.

CAYMUS CORPORATION, Defendant/Appellant.

No. 1 CA-CV 16-0423 FILED 11-16-2017

Appeal from the Superior Court in Maricopa County No. CV2014-012421 The Honorable James T. Blomo, Judge

REVERSED AND REMANDED

COUNSEL

Snell & Wilmer, LLP, Tucson By Jason Ebe, Andrew M. Jacobs, W. Danny Green Counsel for Plaintiff/Appellee

Miranda Law Firm, Gilbert By Daniel L. Miranda Counsel for Defendant/Appellant

OPINION

Judge Maria Elena Cruz delivered the opinion of the Court, in which Acting Presiding Judge Peter B. Swann and Judge Michael J. Brown joined. ZUMAR v. CAYMUS Opinion of the Court

C R U Z, Judge:

¶1 Caymus Corporation (“Caymus”) appeals the superior court’s (1) grant of summary judgment in favor of Zumar Industries, Inc. (“Zumar”) and (2) denial of its motion to add counterclaims. Because we hold the court incorrectly applied the Arizona Prompt Pay Act (“Act”) to a contractor-subcontractor dispute on a federal work project, we reverse and remand for proceedings consistent with this decision.

FACTUAL AND PROCEDURAL HISTORY1

¶2 The National Park Service (“NPS”) is a bureau of the U.S. Department of the Interior, a federal agency. In 2013, NPS hired Caymus to provide and install road signs at Grand Canyon National Park. The contract price was $292,300. Caymus was prepared to bond the project, but NPS’s representative told Caymus a bond was not required because the contract was a service contract, not a construction contract. Caymus hired Zumar, a supplier of traffic signs and related highway safety products with offices in Arizona, California, and Washington, to supply the sign panels. Zumar quoted $92,793.60 for the job; Caymus accepted the quote and agreed to Zumar’s credit application, which provided that Caymus would pay according to the terms of sale stated on Zumar’s invoices.

¶3 In March 2014, Zumar delivered sign panels to the job site; NPS raised immediate concerns about defective and missing panels. Thereafter, the parties and NPS had ongoing discussions regarding completion of the sign panels work. On June 30, though, Caymus submitted a pay application to NPS, certifying the sign panels line item was 100% completed. In total, Caymus requested and received $98,800 from NPS for the sign panels scope of work.

¶4 Zumar invoiced Caymus in full for the sign panels. Caymus paid Zumar $59,278.10, but withheld $35,632.33 pending Zumar’s

1 We view the facts and inferences drawn therefrom in the light most favorable to Caymus, the party against which summary judgment was entered. Weitz Co. L.L.C. v. Heth, 235 Ariz. 405, 408, ¶ 2 (2014).

2 ZUMAR v. CAYMUS Opinion of the Court

satisfactory performance.2 To resolve the parties’ dispute, in October 2014, Zumar’s counsel proposed the following:

Although Caymus has not facilitated a discussion with NPS to attempt to resolve this matter, NPS has contacted Zumar, and proposed to release payment through Caymus to Zumar of the principal amount of $30,632.33 now, with the final principal amount of $5,000.00 to be paid by NPS through Caymus to Zumar upon Zumar’s completion of the items on the enclosed punch list. This proposed resolution is acceptable to Zumar, and we understand NPS has or will contact you to seek your consent. Of course, both payments need to be by joint check, executed first by Caymus, to ensure that Zumar actually receives payment as intended by NPS.

To this end, Bryan Gregory, a contracting officer with NPS, asked Randy Ringleb, Caymus’ president:

Can you provide the status of payments to Zumar? Zumar has expressed a desire to perform needed repairs, but had concerns about payment. Understandably, there may be some amount that is withheld until completion. However, I would encourage you to continue to work with Zumar to get things wrapped up, particularly since we are so near. If you have not already made plans for an interim payment, you may consider doing so to keep things moving in a positive direction. The Government has withheld less than 10% of the contract value. Perhaps you could take a similar approach?

Caymus would not agree to the proposal absent agreement by Zumar to warranty the sign panels or assurance from NPS that it would accept them in as-is condition.

2 Zumar’s quote was $92,793.60 and it later sought $35,632.33 in unpaid invoices. Caymus claims it paid Zumar $50,000 and Zumar and Caymus both acknowledge that Zumar also applied a separate 10% deposit of $9,278.10 towards the balance. Incorporating that 10% deposit, Zumar would have been paid $59,278.10 to date. Given Zumar’s claim of $35,632.33 owing, Zumar’s resulting receipts would total $94,910.43; $2,116.83 more than its original quote for the job. We note this potential discrepancy for the superior court’s consideration on remand.

3 ZUMAR v. CAYMUS Opinion of the Court

¶5 In December 2014, NPS submitted to Zumar and Caymus a punch list of items required to complete the sign panels work. Several months later, NPS sent a Cure Notice, alleging that twenty-two sign panels needed repair and three were missing. Caymus completed the work at a cost of $15,000. NPS withheld final payment to Caymus of $35,367.96 pending resolution of a dispute based in part on the sign panels.

¶6 In the meantime, in September 2014, Zumar brought this breach of contract action against Caymus, seeking damages of $35,632.33. The matter proceeded to compulsory arbitration. Zumar prevailed, and Caymus appealed. Zumar moved for summary judgment, arguing Caymus violated state and federal prompt pay laws, which constituted a material breach of the subcontract. The superior court agreed and granted the motion. While the motion was pending, Caymus moved to add counterclaims for breach of contract, breach of warranty, and (in the alternative) unjust enrichment. The court denied that motion and Caymus’ subsequent motion for reconsideration. The court entered a final judgment and Caymus timely appealed. We have jurisdiction pursuant to Arizona Revised Statutes (“A.R.S.”) section 12-2101(A)(1).

DISCUSSION

I. Motion for Summary Judgment

¶7 Summary judgment is appropriate where no genuine issue of material fact exists and the moving party is entitled to judgment as a matter of law. Johnson v. Earnhardt’s Gilbert Dodge, Inc., 212 Ariz. 381, 385, ¶ 15 (2006). A motion for summary judgment should be granted “if the facts produced in support of the claim or defense have so little probative value, given the quantum of evidence required, that reasonable people could not agree with the conclusion advanced by the proponent of the claim or defense.” Orme Sch. v. Reeves, 166 Ariz. 301, 309 (1990); see Ariz. R. Civ. P. 56(a). We review whether summary judgment was proper based on the record made in the superior court, “but we determine de novo whether the entry of judgment was proper.” Schwab v. Ames Constr., 207 Ariz. 56, 60, ¶ 17 (App. 2004).

A. Arizona Prompt Pay Act

¶8 Caymus argues Zumar failed to establish it was entitled to judgment as a matter of law based on Caymus’ alleged violation of the Act. See A.R.S. § 32-1129 through -1129.07. We agree.

4 ZUMAR v. CAYMUS Opinion of the Court

¶9 “[T]he primary purpose of the Act is to establish a framework for ensuring timely payments from the owner to the contractor and down the line to the subcontractors and suppliers whose work has been approved.” Stonecreek Bldg. Co., Inc. v. Shure, 216 Ariz. 36, 39, ¶ 16 (App. 2007). Caymus argues the Act does not apply to agencies of the federal government, as they cannot be “owners” under the Act.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
418 P.3d 936, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zumar-v-caymus-arizctapp-2017.