Brookfield Construction Co. v. United States

661 F.2d 159, 29 Cont. Cas. Fed. 81,878, 228 Ct. Cl. 551, 1981 U.S. Ct. Cl. LEXIS 485
United States Court of Claims·Decided September 23, 1981·No. No. 555-79C·Published·Cited by 64 cases

Opinion

DAVIS, Judge,

delivered the opinion of the court:

The Contract Disputes Act of 1978, Pub. L. No. 95-563, 92 Stat. 2383, 41 U.S.C. 601 et seq. (Supp III, 1979) — in its summary transitional provision for the interim between, on the one hand, complete non-coverage by the new statute of government contracts, and, on the other, full prospective coverage for wholly new agreements made after the Act became law — presents numerous problems of interpretation.1 These are transient, of course, but many of them are important for both contractors and Government. The present case falls into that class. It involves a pre-Act agreement and contract-claims filed with the contracting officer years before the March 1, 1979 effective date of the Act, but decided by the contracting officer after the Act went into operation. The several questions before us all concern interest on the claim-awards. The chief of these issues is whether a contractor which has elected to proceed under the Act may recover interest on its subsequently-allowed claims for periods of time prior to the effective date of the Act. We hold that the Act does not allow such retroactive interest, and that plaintiffs recovery is limited to simple, variable-rate interest running from the effective [553] date of the Act (March 1,1979) until December 13,1979, the date of payment of the underlying claims.

I

The case is here on cross-motions for summary judgment, and the facts are not in dispute. Under the 1965 contract on which this action is based, plaintiff joint venture2 agreed to construct a hurricane barrier for the United States Army Corps of Engineers for the fixed price of $8,083,075. During the course of construction (April 1965-October 1968) plaintiff experienced various changes, changed conditions and suspensions of work which eventually resulted in the submission of approximately 42 claims for equitable adjustments. Most of the claims were settled and paid, and modifications issued, before March 1, 1979. As of that date, no formal decision had been issued for seven claims. Oral agreement had been reached, however, on three of these claims before the March 1st effective date, but no final modification, memorandum of understanding, or other writing had been issued at that time due to an alleged lack of program funds to pay for the settlements. Final modifications settling all of the claims were executed in October 1979, and payment was made on December 13 of that year.

By letter of June 26, 1979, plaintiffs counsel informed defendant that it would seek interest under the Disputes Act on the amounts finally paid for all claims pending before the contracting officer on the March 1,1979 effective date. The contract itself contained no interest provision.3 The statutory interest claim was denied by the contracting officer in a final decision of August 28, 1979. Plaintiff timely appealed this decision and elected to proceed at once to this court under the Disputes Act’s "direct access” provision, 41 U.S.C. § 609(a)(1) (Supp. Ill 1979). A petition [554] was filed here in December 1979, seeking interest only. These cross-motions for summary judgment followed.

II

There is no doubt (and it is conceded) that, at least as to four of its seven claims unpaid on March 1, 1979, Brook-field-Baylor had the statutory right to proceed under the Disputes Act. Those claims were fully outstanding on that date, and no contracting officer’s decision of any kind was made until a later time. Section 16 of the Act provides that:

This Act shall apply to contracts entered into one hundred twenty days after the date of enactment [November 1, 1978]. Notwithstanding any provision in a contract made before the effective date of this Act [March 1, 1979], the contractor may elect to proceed under this Act with respect to any claim pending then before the contracting officer or initiated thereafter. [41 U.S.C. § 601 (note).]

On June 26,1979, plaintiff made such an election.

We begin with the most significant question in the case— whether a pre-Act contractor properly electing to proceed under the Disputes Act is entitled to interest on those pre-Act claims from the time the claims were made to the contracting officer (before the Act became effective). For its affirmative answer, plaintiff rests, first, on the proposition that, once the Act is properly invoked by a pre-Act contractor on pre-Act claims, every provision of the Act must be applied to that contractor as if this were a post-Act contract, and, second, on the Act’s specific provision giving interest on claims from the time when the contracting officer receives the claim pursuant to the Act (section 12 of the Disputes Act, 41 U.S.C. § 611).4

The first of these contentions has already been rejected outright by the court in the broad form plaintiff (and amicus) put it. In both Folk Construction Co. and Gregory Lumber Co., supra, note 1, we refused to apply the Act’s [555] certification requirements to pre-Act claims which the contractors properly brought here under the "direct access” part of the Act.5 Those rulings show that there can be no mechanical application of each and every provision of the Act to contractors who elect under section 16, supra. The purpose, scope, and meaning of the particular provision must be examined to see its reach and effect on pre-Act claims. That is what we did in Folk and Gregory, and what we must do here. This principle of specific examination is consistent with section 16, supra, which says no more than that the electing contractor "may elect to proceed” under the Act, and does not clamp down the precise application of any specific part of the Act to pre-Act claims or pre-Act contracts.

Free access — add to your briefcase to read the full text and ask questions with AI

Brookfield Construction Co. v. United States, 661 F.2d 159, 29 Cont. Cas. Fed. 81,878, 228 Ct. Cl. 551, 1981 U.S. Ct. Cl. LEXIS 485 (cc 1981).

661 F.2d 159 (Brookfield Construction Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Wit Associates, Inc. v. United States
122 Fed. Cl. 1 (Federal Claims, 2015)
Precision Pine & Timber, Inc. v. United States
75 Fed. Cl. 80 (Federal Claims, 2006)
Usibelli Coal Mine v. United States
54 Fed. Cl. 373 (Federal Claims, 2002)
Johnson Controls World Services, Inc. v. United States
43 Cont. Cas. Fed. 77,463 (Federal Claims, 1999)
Quiman, S.A. de C.V. v. United States
42 Cont. Cas. Fed. 77,227 (Federal Claims, 1997)
NRG Co. v. United States
31 Fed. Cl. 659 (Federal Claims, 1994)
Whitney Benefits, Inc. v. United States
30 Fed. Cl. 411 (Federal Claims, 1994)
Markey v. United States
27 Fed. Cl. 615 (Federal Claims, 1993)
Servidone Construction Corp. v. United States
36 Cont. Cas. Fed. 75,797 (Court of Claims, 1990)
Clark v. United States
19 Cl. Ct. 220 (Court of Claims, 1990)
Illinois v. United States
19 Cl. Ct. 180 (Court of Claims, 1989)
Cecile Industries, Inc. v. United States
35 Cont. Cas. Fed. 75,756 (Court of Claims, 1989)
District of Columbia v. C.J. Langenfelder & Son, Inc.
558 A.2d 1155 (District of Columbia Court of Appeals, 1989)
Hettich and Company, Gmbh v. The United States
873 F.2d 1451 (Federal Circuit, 1989)
Fors v. United States
14 Cl. Ct. 709 (Court of Claims, 1988)